CompletedBhusawal (Ct), Jalgaon 425201 |Promoter: Prajakt Shivaji Patil
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Completed
- Buildings
- 1
- Land area for this project
- 600 sq m (6,458 sq ft)
- Permissible built-up area
- 1,342 sq m (14,449 sq ft)
- Sanctioned built-up area
- 1,342 sq m (14,449 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Planning authority
- BHUSAWAL MUNICIPAL COUNCIL BHUSAWAL
- Address
- S NO 78/2 P NO 1, At Satare Shivar, At Satare ShivarPIN 425201
- Designated bank account
- Icici Bank Limited
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2027
- Registered
- 29 Oct 2024
- Promised
- 31 Dec 2027
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P49900077768 | 29 Oct 2024 | 31 Dec 2027 | — | Prajakt Shivaji Patil | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Laxmi Heights | 7 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 10 | 16 | 0 | 0 | 26 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Laxmi Heights
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
33 documents held by Deedo, 41 filings listed on MahaRERA's project page
Commencement certificates
Others
- Other1 Mar 2024ViewSource
- Other1 Mar 2024ViewSource
- Other1 Mar 2024ViewSource
- Other1 Mar 2024ViewSource
- Other23 Apr 2024ViewSource
- Other25 Oct 2024ViewSource
- Other18 Jul 2025ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Document library
- Copy of Layout Approval (in case of layout)Layout Laxmi heights.pdf · uploaded 11 Nov 2023View
- Commencement Certificates / NA Order for plotted development7 COMMENCEMENT CERTIFICATE.pdf · uploaded 1 Mar 2024View
- CERSAI details17 Laxmi Heights CERSAI_Search_Report_200298300714_For_Asset_Based_Search_27_02_2024_12_22_24_460.pdf · uploaded 1 Mar 2024View
- Proforma of Allotment letter26 Proforma_Allotment_Letter.pdf · uploaded 1 Mar 2024View
- Copy of the legal title report2 legal title report Laxmi.pdf · uploaded 1 Mar 2024View
- Proforma of Agreement for sale25 Agreement to sales.pdf · uploaded 1 Mar 2024View
- Deviation Report with respect to Allotment letter37 Deviation Report with respect to Allotment letter.pdf · uploaded 1 Mar 2024Source
- Deviation Report with respect to model copy of Agreement38 Deviation Report with respect to model copy of Agreement.pdf · uploaded 1 Mar 2024View
- Disclosure of Interest in Other Real Estate Organizations19 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 1 Mar 2024View
- a Details of encumbrances concerned to Finance3 Details of encumbrances concerned to Finance.pdf · uploaded 1 Mar 2024View
- b Details of encumbrances concerned to Legal3 Details of encumbrances concerned to Finance.pdf · uploaded 1 Mar 2024View
- a Details of encumbrances concerned to Finance4 Details of encumbrances concerned to Legal.pdf · uploaded 1 Mar 2024View
- b Details of encumbrances concerned to Legal4 Details of encumbrances concerned to Legal.pdf · uploaded 1 Mar 2024View
- CERSAI detailsNO SECURITY INTEREST CERTIFICATE CERSAI.pdf · uploaded 1 Mar 2024View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK DECLARATION AS PER FORMAT.pdf · uploaded 11 Mar 2024Source
- Declaration in FORM B9 FORM B PROMOTER PRAJAKT PATIL (2).pdf · uploaded 12 Apr 2024View
- Building Plan Approval / NA Order for plotted development8 Original Layout Plan of Laxmi Heights_11zon.pdf · uploaded 12 Apr 2024View
- Other – TechnicalDeclaration cun undertaking_11zon.pdf · uploaded 23 Apr 2024View
- Declaration about Commencement CertificateFORMAT D LAXMI HEITH.pdf · uploaded 13 Aug 2024View
- Other – LegalEMAIL VERIFICATION LAXMI HEIGHTS.pdf · uploaded 17 Aug 2024View
- Commencement Certificates / NA Order for plotted developmentemail.pdf · uploaded 14 Oct 2024View
- Commencement Certificates / NA Order for plotted developmentEMAIL VERIFICATION.pdf · uploaded 24 Oct 2024View
- Other – LegalEMAIL VERIFICATION.pdf · uploaded 24 Oct 2024View
- Other – Financeclarification on zero land cost.pdf · uploaded 25 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 23 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form no 2.pdf · uploaded 23 Jan 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 23 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form no 2.pdf · uploaded 23 Jan 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 23 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form no 2.pdf · uploaded 23 Jan 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARICHITECT SIGN_11zon.pdf · uploaded 15 Apr 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER SIGN_11zon.pdf · uploaded 15 Apr 2025View
- Occupational Certificatecompletion certification with email screen short.pdf · uploaded 18 Jul 2025View
Promoter documents
Technical documents
Other legal documents
Financial documents
- Other – Financeclarification on zero land cost.pdf · uploaded 25 Oct 2024View
Proforma allotment letter
- Proforma allotment letter26 Proforma_Allotment_Letter.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bhusawal (CT), Bhusawal taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
S NO 78/2 P NO 1
Boundaries
- North
- Plot No 34 35 And 36
- South
- 24 Mtr Wide Road
- East
- Plot No 2
- West
- Sarve No 63
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Prashant Shivaji Patil | — |
| Chartered accountant | Ca Darshan Ramesh Jain | — |
| Engineer | Milind S Rathi | — |
| Engineer | Prashant Shivaji Patil | — |
Source: MahaRERA project page. Contact details are not shown.