Deedo IDDL-JLG-BHUSAWAL3 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects35
Registrations35
Completion still due425 past their date
Median extension18 months14% of registrations extended
Regulatory cases0none on MahaRERA's lists
3 in 10 registrations run late here
35 MahaRERA registrations in Bhusawal and the places within it
18 completed1 not yet due1 extended, not yet due9 past even the latest date6 no date on record
Extended registrations moved their completion date by a median of 18 months.
Projects in Bhusawal
35 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Gauri Nandan ApartmentPatil Mahajan | Due Apr 2029, extended 4 mo | — | — |
| Casa De RoyaleRaka Constructions | Due Dec 2027 | — | — |
| Laxmi HeightsPrajakt Shivaji Patil | Completed | — | — |
| VighnarajPatil Mahajan | Completed | — | — |
| Pride ResidencySumit Mahendra Chordia | 1 yr 11 mo late | — | 10% |
Nearby: other talukas in Jalgaon
Most active promoters
- Patil Mahajan3 projects
- Rajesh Raka3 projects
- Vishal Rajendra Natkar3 projects
- Nashik Housing And Area Development Board2 projects
- Prajakt Shivaji Patil2 projects
- Raka Constructions2 projects
- Sumit Mahendra Chordia2 projects
- Ajmal Khan Musa Khan1 project
- Chintamani Construction1 project
- Kalpana Sudhakar Phalak1 project
Bhusawal, in questions
How many projects in Bhusawal run late?
3 in 10 MahaRERA registrations (10 of 35): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhusawal by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology