RERA projects in Jalgaon

232 projects under 232 MahaRERA registrations across 31 localities, registered 2017–2026. 5% have a completion date extended beyond the one promised.

232RERA projectsin 31 localities
232Registrations
22Completion still due177 past their completion date, 130 marked completed
13 monthsMedian extension beyond promised date5% of registrations extended
20Regulatory caseson 12 projects
445Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201755
201826
201920
202028
202118
202220
202317
202410
20254
20261

Localities in Jalgaon

By number of registered projects. Talukas and localities as MahaRERA names them.

All 31 localities

Projects in Jalgaon

232 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Gauri Nandan ApartmentPatil MahajanPM113000260043815 May 202631 Dec 2028—Not yet due0
One High StreetAshtavinayak EnterprisesP499000810023 Oct 20251 Oct 2026—Promised date passed0
The Lake ParadiseJivraj BuildconP499000807897 Jul 202531 Mar 2027—Not yet due0
Krushna HeightsM/s Shree Swami Samarth Traders Builders and DeveloprsP4990007904031 Jan 202531 Aug 2025—Promised date passed0
Casa De RoyaleRaka ConstructionsP4990007896324 Jan 202531 Dec 2027—Not yet due0
Samarths SuvruddhiSamarth Constrowell Private LimitedP4990007838710 Dec 202431 Mar 2029—Not yet due0
JK EleganceJK EleganceP4990007793513 Nov 20247 May 2027—Not yet due0
Laxmi HeightsPrajakt Shivaji PatilP4990007776829 Oct 202431 Dec 2027—Completed0
Ajinkyatara AppartmentRakesh Bhimrao BorseP499000773449 Aug 202431 Dec 2025—Promised date passed0
Majestique LandmarkOrnate PropertiesP4990007696710 Jul 202430 Sep 2026—Completed0
Sai Charan ResidencyN & L AssociatesP4990007673221 Jun 202430 Jun 2026—Promised date passed0
AntarikshSumeet Prakashchand MuthaP4990005620021 May 202431 Dec 2026—Not yet due0
Om ResidencyJalgaon Projects Pvt LtdP499000560066 May 202430 Sep 2025—Promised date passed0
Krushnaji ArcadeM/S. Shreyash RealtiesP4990005571515 Apr 202431 Jan 2028—Not yet due0
Mundada High StreetMundada RealtyP4990005456231 Jan 202430 Apr 2026—Completed0
Sukruti SuratnaSuratna Infra LLPP4990005235721 Aug 20233 Apr 2027—Completed0
VighnarajPatil MahajanP499000518867 Jul 202318 Feb 2025—Completed0
Rupchand Ramchand ComplexAshish Punamchand AgrawalP4990005167427 Jun 202320 Jan 2028—Completed0
Shiv Maan HeightsJain InfraP499000513608 Jun 202331 Mar 2026—Promised date passed0
Shiv NamanJain BuildconP499000512768 Jun 202331 Mar 2025—Promised date passed0
SSD ComplexJay Narayan DevelopersP499000508519 May 202330 Sep 2024—Promised date passed0
Anvika ArcadeKailash Vinayak KasarP4990005072128 Apr 202330 Jun 2025—Promised date passed0
Sai Prakash HeightsJain BuildconP4990005046617 Apr 202331 Dec 2024—Completed0
PPRL Basera - JaynagarVinaykumar Uttamchand ParakhP4990005021127 Mar 202330 Dec 2025—Promised date passed0
Pride ResidencySumit Mahendra ChordiaP4990005025227 Mar 202331 Dec 2024—Promised date passed0
Gokuldas HousingGokuldas HousingP499000498456 Mar 202331 Dec 2025—Promised date passed0
Vastu VandanManohar Ganpat WaniP499000500256 Mar 202331 Jul 2025—Promised date passed0
Vastu NinePride Leela Builders And DevelopersP4990004970022 Feb 202331 Dec 2025—Completed0
VrindavanRaka ConstructionsP4990004955815 Feb 202331 Dec 2025—Completed0
Bhagavanti HeightsShiv Gajanan ConstructionP4990004901224 Jan 202331 Oct 2024—Completed0
Sai Krushanasha HeightSai Krushna AssociatesP4990004900624 Jan 202331 Mar 2025—Completed0
Udyog IshwarM/S. Faith Build ConstructionsP4990004861710 Jan 202331 Dec 2027—Not yet due0
Vasant ViharAaradhya InfraprojectsP4990004828622 Dec 202231 Dec 2023—Completed0
Shri Gajanan ComplexRajani Dinkar PatilP4990004814912 Dec 202231 Dec 2025—Promised date passed0
M SquareAaradhya InfraprojectsP499000480468 Dec 202231 Dec 2027—Not yet due0
Morya PlazaTrimurti ContructionsP4990004779828 Nov 202231 Mar 2026—Promised date passed0
Omkara ResidencyJalgaon Projects Pvt LtdP4990004661725 Aug 202231 Mar 2025—Completed0
Sahyadri ShikharSahyadri ShikharP4990004642720 Jul 202230 Sep 2024—Promised date passed0
Ganpati NagarGiriraj DevelopersP4990004601715 Jun 202231 Mar 2025—Completed0
Shivnery ParkSuperealty Buildcon LLPP4990004580415 Jun 20222 Dec 2026—Not yet due0
Sukruti CentrumArihant ConstructionP4990004554224 May 202231 Mar 2025—Completed0
Suryadarshan ResidencyGanesh Gopal ChaudhariP4990004548924 May 202231 Mar 2025—Promised date passed0
Chhoriya Fortune City -Parola plottingAnmol Chhoriya And AssociatesP4990004542418 May 202231 Dec 2029—Completed0
Sunshine TowerSachin Suryakant BhamreP4990004533112 May 202231 Dec 2025—Completed1
Arihannt SapphireArihannt SapphireP4990003491228 Apr 202220 Mar 2026—Promised date passed0
Jk PrideJaju & Khandelwal ConstructionsP4990003426530 Mar 202231 Dec 2024—Completed0
Mannat heightsAjmal khan Musa KhanP4990003402417 Mar 202231 Dec 2023—Promised date passed0
Aarohi HeightsPiyush Ashok BedmuthaP4990003397014 Mar 202231 Dec 2024—Promised date passed0
Shambho ResidencyAnita Vilas AhirraoP4990003388914 Mar 202231 Dec 2024—Promised date passed0
Jamuna ResidencyJamuna InfraP499000337868 Mar 202230 Jun 2025—Promised date passed0
Shivaay SquareIshanavi Construtech Pvt LtdP4990003275524 Jan 202212 Aug 2023—Completed0
Sukruti SerenityArihant DevelopersP4990003265117 Jan 202231 Dec 2024—Completed0
Park RoyaleMahaveer BuildconP4990003227422 Dec 202131 Dec 2024—Completed0
Morya HeightMorya Builders And DevelopersP4990003226020 Dec 202131 Mar 2024—Completed0
Shree Swami Samarth SankulKadam And Patil DevelopersP499000311245 Oct 202131 Mar 2023—Completed0
Varad HeightsToke And Dhake AssociatesP499000311335 Oct 202115 Aug 2026—Completed0
Sai DhamJb AssociatesP499000310411 Oct 202131 Aug 2026—Promised date passed0
Navkar HeightsRajesh Construction And BuildersP4990003101829 Sep 202130 Jun 2030—Completed0
Ramai Keshav Vihar Phase 3Vishal Rajendra NatkarP4990003087220 Sep 202131 Dec 2023—Completed0
Navkar ResidencyGlobal BuildersP499000306378 Sep 202113 Aug 2026—Promised date passed0
PrabhulilaVastu BuildersP499000307228 Sep 202131 Dec 2023—Completed0
Kamlai ResidencyDnyaneshwar Pundlik PatilP499000306081 Sep 202118 Jun 2024—Promised date passed0
Mundada EstateAmey Omprakash MundadaP4990003052930 Aug 202131 Dec 2023—Completed0
Shree Balaji PrideShree Balaji DevelopersP499000301745 Aug 202131 Dec 2022—Promised date passed0
Swami Apartment 2Devendra Pandurang SonawaneP499000301625 Aug 202130 Mar 2023—Promised date passed0
Laxman AvenueLakshman Daulat MaliP4990002945629 May 202130 Apr 2022—Promised date passed0
RadhakrishnaShankheshwar AssociatesP4990002929118 May 202131 Mar 2024—Completed0
Sai JyotsnaiV B Wani And CompanyP4990002928318 May 202131 Dec 2023—Promised date passed0
New Anand KrushnaM/S Shree Swami Samarth Traders Builders And DevelopersP4990002908726 Apr 202130 Oct 202230 Jun 2023Completed0
Sai KrushanashaSai Krushna AssociatesP499000285108 Mar 202130 Sep 2022—Completed0
Shobharam HeightsShriram ConstructionP4990002758516 Dec 202030 Sep 2022—Promised date passed0
Ramai Keshav Vihar Phase-2Vishal Rajendra NatkarP499000273252 Dec 202030 Mar 2023—Completed0
Sinhagadh Villas Phase IHarish Manikaro SurveP4990002708213 Nov 202030 Sep 2022—Completed0
Patil HeightsPrajakt Shivaji PatilP4990002703310 Nov 202030 Dec 2024—Promised date passed0
ShubhamRajesh RakaP499000265472 Oct 202030 Jun 2023—Completed0
Gopal Krushna Residency Phase 2Thepade BuildersP4990002652730 Sep 202030 Sep 2024—Promised date passed0
TulasRajesh RakaP4990002636311 Sep 202030 Jun 2023—Completed0
Sayed Zahidali JamataliZahidali Jamatali SayedP4990002609419 Aug 202030 Mar 2024—Promised date passed0
Shri Krishna AvenueGanesh LadheP4990002582918 Jul 202030 Jun 2022—Completed0
Kunal ParkM/S Shree Swami Samarth Traders Builders And DevelopersP499000257317 Jul 202028 Aug 2023—Completed0
Shivtirth ApartmentPramod Madhukar GhugeP499000257194 Jul 202030 Sep 2022—Completed0
Shri ApartmentMilan Devanand PrajapatiP499000257224 Jul 202030 Sep 2023—Promised date passed0
Krupa ApartmentAbraham Thomas MullesserilP499000256291 Jul 202030 Jun 2022—Completed0
Mangalam ParkMangalam InfraP499000256791 Jul 202030 Sep 202329 Sep 2028Extended 60 mo0
Sai Yash HeightsJain BuildconP4990002553328 Jun 202030 Sep 2022—Completed0
Swami Pushpa ApartmentPoonam Ramesh DeoreP499000255098 Jun 202030 Dec 2022—Completed0
Ganesha Chaitanyadeepak prakash sarafP4990002542829 May 20209 Mar 2024—Completed0
Ganesha DivineGurudatta Global DevelopersP4990002538915 May 20209 Jun 2024—Completed0
Nayantara Arcade City PrideNayantara DevelopersP4990002532414 Apr 202030 Jun 2025—Completed0
Vandan HeightsGovinda Ghanshyam NagoriP499000253025 Apr 202016 Mar 2022—Promised date passed0
Shakuntala HeightsShiv ConstructionP4990002521323 Mar 202030 Mar 2022—Completed0
Shreeram ResidencyNarendra Atmaram PatilP4990002523923 Mar 202030 Mar 2021—Completed0
Ramai Keshav Vihar Phase-1Vishal Rajendra NatkarP4990002437510 Feb 20201 Jan 2023—Promised date passed0
Labhoni Kamal VillaNarendra Nihalchand JainP4990002416723 Jan 202030 Mar 2023—Promised date passed0
R D TowerM/S Shree Swami Samarth Traders Builders And DevelopersP4990002394514 Jan 202030 Dec 2022—Completed0
Shri Sai ViharPushpak Onkar NarkhedeP4990002389610 Jan 20201 Dec 2020—Completed0
Moreshwar ApartmentPatil MahajanP499000238849 Jan 20201 Dec 2023—Promised date passed0
Shakun EstatesRajesh RakaP499000238427 Jan 202030 Jun 2023—Completed0
Behede Deshpande ComplexBehede & Deshpande GroupP4990002358320 Dec 201930 Dec 2023—Completed0
Aditya Gold CityAditya Builders And DevelopersP4990002347816 Dec 201930 Dec 2030—Not yet due2

Other districts

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Shree N T Mundada Park4 projects
  2. Arihant Developers3 projects
  3. Jain Buildcon3 projects
  4. M/S Shree Swami Samarth Traders Builders And Developers3 projects
  5. Parakh Plexus Realty Ltd.3 projects
  6. Patil Mahajan3 projects
  7. Rajesh Raka3 projects
  8. Sagar Pandit Tade3 projects
  9. Vishal Rajendra Natkar3 projects
  10. Aaradhya Infraprojects2 projects
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology