RERA projects in Chalisgaon
14 projects under 14 MahaRERA registrations, registered 2017–2025. 7% have a completion date extended beyond the one promised.
14RERA projects
14Registrations
2Completion still due12 past their completion date, 8 marked completed
8 monthsMedian extension beyond promised date7% of registrations extended
0Regulatory casesnone on MahaRERA's lists
44Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
| 2018 | 3 |
| 2019 | 0 |
| 2020 | 2 |
| 2021 | 1 |
| 2022 | 2 |
| 2023 | 1 |
| 2024 | 1 |
| 2025 | 1 |
Projects in Chalisgaon
14 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Krushna HeightsM/s Shree Swami Samarth Traders Builders and Developrs | P49900079040 | 31 Jan 2025 | 31 Aug 2025 | — | Promised date passed | 0 |
| Ajinkyatara AppartmentRakesh Bhimrao Borse | P49900077344 | 9 Aug 2024 | 31 Dec 2025 | — | Promised date passed | 0 |
| SSD ComplexJay Narayan Developers | P49900050851 | 9 May 2023 | 30 Sep 2024 | — | Promised date passed | 0 |
| Shivnery ParkSuperealty Buildcon LLP | P49900045804 | 15 Jun 2022 | 2 Dec 2026 | — | Not yet due | 0 |
| Shambho ResidencyAnita Vilas Ahirrao | P49900033889 | 14 Mar 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| New Anand KrushnaM/S Shree Swami Samarth Traders Builders And Developers | P49900029087 | 26 Apr 2021 | 30 Oct 2022 | 30 Jun 2023 | Completed | 0 |
| Kunal ParkM/S Shree Swami Samarth Traders Builders And Developers | P49900025731 | 7 Jul 2020 | 28 Aug 2023 | — | Completed | 0 |
| Swami Pushpa ApartmentPoonam Ramesh Deore | P49900025509 | 8 Jun 2020 | 30 Dec 2022 | — | Completed | 0 |
| Rudra ApartmentMohan Bhimaji Lad | P49900017309 | 2 Aug 2018 | 30 Dec 2026 | — | Completed | 0 |
| Krushna City Phase 3Global Builders | P49900015922 | 9 Apr 2018 | 31 Dec 2019 | — | Completed | 0 |
| Aanand-KrishnaShree Swami Samarth Traders Builders And Developers | P49900015788 | 26 Mar 2018 | 31 Dec 2019 | — | Promised date passed | 0 |
| Krushnaworld CityGlobal Builders And Developers | P49900014135 | 9 Nov 2017 | 31 Dec 2017 | — | Completed | 0 |
| Krishna CityGlobal Infrastructure | P49900013989 | 7 Nov 2017 | 31 Dec 2017 | — | Completed | 0 |
| Maharana Pratap Sahkari Gruh Nirman Sanstha LimitedMaharana Pratap Sahkari Gruh Nirman Sanstha Limited | P49900003684 | 6 Aug 2017 | 31 Jan 2021 | — | Completed | 0 |
Other localities in Chalisgaon
- Khadaki Bk.1 project
- Takali Pra.Cha1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- M/S Shree Swami Samarth Traders Builders And Developers2 projects
- Anita Vilas Ahirrao1 project
- Global Builders1 project
- Global Builders And Developers1 project
- Global Infrastructure1 project
- Jay Narayan Developers1 project
- Maharana Pratap Sahkari Gruh Nirman Sanstha Limited1 project
- Mohan Bhimaji Lad1 project
- M/s Shree Swami Samarth Traders Builders and Developrs1 project
- Poonam Ramesh Deore1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology