Krushna City Phase 3
CompletedChalisgaon, Jalgaon 424101 |Promoter: Global Builders
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Buildings
- 2
- Unit types
- Residential84 units in all
- Land area for this project
- 2,413 sq m (25,978 sq ft)
- Permissible built-up area
- 2,894 sq m (31,149 sq ft)
- Sanctioned built-up area
- 2,894 sq m (31,149 sq ft)
- Address
- Survey No 421/1, Dhule Road, ChalisgaonPIN 424101
- Designated bank account
- Kotak Mahindra Bank Limited
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2019
The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 9 Apr 2018
- Promised
- 31 Dec 2019
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P49900015922 | 9 Apr 2018 | 31 Dec 2019 | — | Global Builders | Project page |
2 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
84 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| A Wing | Residential | 18.82 sq m · 203 sq ft | 6 |
| A Wing | Residential | 20.54 sq m · 221 sq ft | 2 |
| A Wing | Residential | 21.84 sq m · 235 sq ft | 6 |
| A Wing | Residential | 22.98 sq m · 247 sq ft | 1 |
| A Wing | Residential | 23.04 sq m · 248 sq ft | 2 |
| A Wing | Residential | 23.94 sq m · 258 sq ft | 1 |
| A Wing | Residential | 30.11 sq m · 324 sq ft | 6 |
| A Wing | Residential | 30.76 sq m · 331 sq ft | 6 |
| A Wing | Residential | 33.54 sq m · 361 sq ft | 12 |
| B Wing | Residential | 18.82 sq m · 203 sq ft | 6 |
| B Wing | Residential | 20.45 sq m · 220 sq ft | 2 |
| B Wing | Residential | 21.84 sq m · 235 sq ft | 6 |
| B Wing | Residential | 22.98 sq m · 247 sq ft | 1 |
| B Wing | Residential | 23.04 sq m · 248 sq ft | 2 |
| B Wing | Residential | 23.94 sq m · 258 sq ft | 1 |
| B Wing | Residential | 30.11 sq m · 324 sq ft | 6 |
| B Wing | Residential | 30.76 sq m · 331 sq ft | 6 |
| B Wing | Residential | 33.54 sq m · 361 sq ft | 12 |
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| A Wing | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| A Wing | Open Space | 0 | 0 | 0 | 0 | 0 |
| B Wing | Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| B Wing | Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
A Wing
B Wing
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
18 documents held by Deedo, 22 filings listed on MahaRERA's project page
Completions
Others
Document library
- Declaration in FORM BDECLARATION IN FORM B.pdf · uploaded 30 Mar 2018View
- Details of encumbrancesSELF DECLARATION REGARDING ENCUMBRANCES.pdf · uploaded 30 Mar 2018View
- Proforma of Allotment letterALLOTMENT DEED.pdf · uploaded 30 Mar 2018View
- Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 30 Mar 2018View
- Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 30 Mar 2018View
- Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 30 Mar 2018View
- Building Plan Approval (IOD)BUILDING PLAN APPROVAL.pdf · uploaded 30 Mar 2018View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)MAHA RERA AUDIT REPORT.pdf · uploaded 18 May 2020View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Notes to RERA Report.pdf · uploaded 18 May 2020View
- Architect’s Certificate on Completion of Project (Form 4)GLOBAL BUILDERS.pdf · uploaded 7 Aug 2021View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentkwc 3 completion later_1.pdf · uploaded 7 Aug 2021View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentkwc 2 campletion and inward later.pdf · uploaded 7 Aug 2021View
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)MAHA RERA AUDIT REPORT.pdf · uploaded 7 Aug 2021View
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Notes to RERA Report.pdf · uploaded 7 Aug 2021View
- Status of Formation of Legal Entity (Society/Co Op etc.)society kwc 3.pdf · uploaded 12 Aug 2021View
- Status of Formation of Legal Entity (Society/Co Op etc.)society kwc 2.pdf · uploaded 12 Aug 2021View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDECLARATION1.pdf · uploaded 12 Oct 2021View
Promoter documents
Technical documents
Proforma allotment letter
- Proforma allotment letterALLOTMENT DEED.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Chalisgaon, Chalisgaon taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
SURVEY NO 421/1
Boundaries
- North
- S No 420
- South
- S No 432
- East
- S No 421 2
- West
- S No 422
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Niraj R Mantri | — |
| Engineer | Nilesh Suvalal Kankariya | — |
| Other | Ravindra Laxman Kumavat | — |
| Other | Sadik Musa Khatik | — |
Source: MahaRERA project page. Contact details are not shown.