Vihang Infrastructure Pvt Ltd
Deedo IDDD-HPC4Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
5 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| vihang valleyP51700007077 | Owale | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
| Metro Hive D-1P51700020335 | Owale | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| Evana D-2P51700034145 | Owale | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
| Elita D3P51700034754 | Owale | Certificate Signed | 31 Dec 2029 | 31 Dec 2030 | +12 mo |
| Commercial Building 10P51700046036 | Thane | Certificate Signed | 31 Dec 2024 | 30 Dec 2025 | +23 mo* |
| Elysia D-4P51700080101 | Thane | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
Vihang Infrastructure Pvt Ltd, in questions
Does Vihang Infrastructure Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Vihang Infrastructure Pvt Ltd registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 1 completed on MahaRERA.
Does Vihang Infrastructure Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.