Vihang Infrastructure Pvt Ltd

Company or firm · 6 projects · 6 MahaRERA registrations

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
vihang valleyP51700007077Thane (M Corp.)2017Not reported30 Dec 2026—On date
Metro Hive D-1P51700020335Owale2019Not reported30 Dec 2026—On date
Evana D-2P51700034145Owale2022Not reported31 Dec 2029—On date
Elita D3P51700034754Thane2022Not reported31 Dec 202931 Dec 2030+12 months
Commercial Building 10P51700046036Thane2022Not reported31 Dec 202430 Dec 2025+12 months
Elysia D-4P51700080101Thane2025Not reported31 Dec 2031—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • vihang valleyOn date
  • Metro Hive D-1On date
  • Evana D-2On date
  • Elita D3+12 mo
  • Commercial Building 10+12 mo
  • Elysia D-4On date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Elita D3 (P51700034754).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology