Elita D3 · Owale, Thane · Vihang Infrastructure Pvt Ltd
Promised for 31 Dec 2029, extended once to 31 Dec 2030, which is still ahead.
The revised date is 1 year after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2029 to 31 Dec 2030 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700034754
Is Elita D3 delayed?
Its completion moved from 31 Dec 2029 to 31 Dec 2030; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700034754. The completion date moved from 31 Dec 2029 to 31 Dec 2030.
Who is the promoter?
MahaRERA records Vihang Infrastructure Pvt Ltd as the promoter of P51700034754.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700034754.