RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51700020335
Metro Hive D-1 · Owale, Thane · Vihang Infrastructure Pvt Ltd
Promised for 30 Dec 2026, extended to 30 Apr 2027, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2026 to 30 Apr 2027.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51700020335
Is Metro Hive D-1 delayed?
Its completion moved from 30 Dec 2026 to 30 Apr 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51700020335. The completion date moved from 30 Dec 2026 to 30 Apr 2027.
Who is the promoter?
MahaRERA records Vihang Infrastructure Pvt Ltd as the promoter of P51700020335.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700020335.