Tirupati Developers

Company or firm · 56 projects · 64 MahaRERA registrations · 6 reported completed

56Projects64 RERA registrations
6Completedas reported on MahaRERA project pages
69%Kept RERA date18 of 26 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 8 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Dhanbhoomi 1P50500008320Panjari2017Completed30 Sep 202030 Mar 2026+66 months
SuvarnabhoomiP50500008330Dongargaon (535927)2017Lapsed30 Sep 202031 Mar 2026+66 months
RajatbhoomiP50500017735Nagpur (Rural)2018Not reported31 Dec 201930 Sep 2025+69 months
Rajatbhoomi - 3P50500017744Nagpur (Rural)2018Not reported31 Dec 201931 Mar 2027+87 months
RajatbhoomiP50500017852Nagpur (Rural)2018Not reported30 Sep 2026—On date
Rajatbhoomi - 5P50500018095Nagpur (Rural)2018Not reported31 Dec 201930 Sep 2025+69 months
Vrindavan ParkP50500018534Khadka2018Completed30 Dec 2022—On date
Silver CityP50500018573Kothewada2018Active30 Sep 2020—On date
Rajatbhoomi 1P50500018588Dongargaon (535897)2018Completed30 Sep 202031 Mar 2025+54 months
Rajatbhoomi-4P50500022256Nagpur (Rural)2019Not reported30 Mar 202130 Jun 2024+39 months
Silver ParkP50500023279Shankarpur2019Not reported30 Dec 2023—On date
Highway GloryP50500023401Nagpur (Rural)2019Not reported30 Sep 202230 Sep 2027+60 months
Dhanbhoomi 2P50500027114Panjari2020Not reported30 Sep 2027—On date
Silverpark - 5P50500028157Shankarpur2021Not reported31 Jul 2024—On date
Silverpark 2P50500028189Shankarpur2021Not reported30 May 2025—On date
Silverpark - 6P50500028267Shankarpur2021Not reported31 Jul 2025—On date
Silverpark - 3P50500028401Shankarpur2021Not reported31 Jul 2024—On date
Rajatbhoomi - 7P50500028937Nagpur (Rural)2021Not reported31 Jan 2025—On date
Rajatbhoomi - 8P50500029000Nagpur (Rural)2021Not reported31 Jan 2024—On date
Silver CityP50500029462Kothewada2021Not reported31 Mar 2027—On date
Rajatbhoomi-10P50500029483Nagpur (Rural)2021Not reported31 May 2025—On date
Rajatbhoomi-9P50500029502Nagpur (Rural)2021Not reported31 May 2025—On date
Vrindavan Park - 2P50500030295Khadka2021Not reported31 Dec 2025—On date
Silver Park - 10P50500032628Shankarpur2022Not reported30 Sep 2026—On date
Silver Park - 9P50500032837Shankarpur2022Not reported30 Sep 2026—On date
Silverpark - 11P50500032908Shankarpur2022Not reported30 Sep 2026—On date
Silverpark - 7P50500032992Shankarpur2022Not reported30 Sep 2026—On date
Samruddhi3P50500033334Sukli2022Not reported31 Jan 2027—On date
Silverpark - 8P50500033401Shankarpur2022Not reported30 Sep 2026—On date
Samruddhi 5P50500033426Nagpur (Rural)2022Not reported31 Jan 2027—On date
Samruddhi 1P50500034791Sukali(Gupchup)2022Not reported31 Mar 2027—On date
Silver Park - 12P50500034842Nagpur (Rural)2022Not reported31 Mar 2027—On date
Samruddhi 2P50500045310Sukali(Gupchup)2022Not reported30 Apr 2027—On date
Samruddhi - 6P50500047388Sukali(Gupchup)2022Not reported31 Jul 2027—On date
Samruddhi 4P50500047743Sukali(Gupchup)2022Not reported31 Oct 2027—On date
Rajatbhoomi 11P50500048070Nagpur (Rural)2022Not reported31 Jul 2027—On date
Silver Icon - 1P50500048096Gotal Panjari2022Not reported31 Jul 2027—On date
Vrindavan Park-5P50500051805Hingna2023Not reported31 May 2028—On date
Silver Park-13P50500052018Shankarpur2023Not reported31 May 2028—On date
Samruddhi 8P50500053273Sukali(Gupchup)2023Not reported31 Mar 2028—On date
Silver Park-14P50500054108Shankarpur2023Not reported30 Nov 2028—On date
Vrindavan Park-3P50500054315Sukali(Gupchup)2024Not reported30 Nov 2028—On date
Vrindavan Park-6P50500054319Sukali(Gupchup)2024Not reported30 Nov 2028—On date
Silver Park 15P50500054435Panjari Farm2024Completed30 Nov 2028—On date
Silver Pride - 1P50500054735Gawasi Manapur2024Not reported27 Dec 2028—On date
Silver Star - 1P50500054832Nagalwadi (Ct)2024Not reported31 Jan 2029—On date
Silver Star-2P50500055267Nagalwadi (Ct)2024Not reported10 Jan 2029—On date
Silver Pride - 3P50500056076Nagpur (Rural)2024Not reported31 Mar 2029—On date
Silver WindsP50500077203Wanadongri2024Not reported31 Jul 2029—On date
Silver Woods 1P50500078257Mondha2024Not reported31 Oct 2029—On date
Silver Star 4P50500078957Nagalwadi (Ct)2025Not reported31 Oct 2029—On date
Vrindavan ParkP50500079234Khadka2025Completed31 Jan 2029—On date
Rajatbhoomi - 13P50500079362Dongargaon (535897)2025Completed31 Dec 2029—On date
Vrindavan ParkP50500080979Sukali(Gupchup)2025Not reported30 Apr 2030—On date
Vrindavan ParkPP1190002500967Sukli2025Not reported31 Dec 2030—On date
Vrindavan ParkPP1190002501032Sukli2025Not reported31 Dec 2030—On date
Silver Star - 5PP1190002501052Nagalwadi (Ct)2025Not reported31 Jan 2030—On date
Vrindavan ParkPP1190002501191Sukali(Gupchup)2025Not reported31 Dec 2030—On date
Silver Star - 6PP1190002501636Nagalwadi (Ct)2025Not reported30 Nov 2030—On date
Vrindavan ParkPP1190002502184Sukali(Gupchup)2026Not reported31 Jan 2031—On date
Vrindavan ParkPP1190002502523Sukali(Gupchup)2026Not reported31 Jan 2031—On date
Rajatbhoomi - 12PP1190002600109Dongargaon2026Not reported31 Mar 2031—On date
Silver EstatePP1190002601377Takali2026Not reported30 Jun 2031—On date
Vrindavan ParkPP1190002602054Sukli2026Not reported30 Sep 2031—On date
Show all 64 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Dhanbhoomi 1+66 mo
  • Suvarnabhoomi+66 mo
  • Rajatbhoomi+69 mo
  • Rajatbhoomi - 3+87 mo
  • RajatbhoomiOn date
  • Rajatbhoomi - 5+69 mo
  • Vrindavan ParkOn date
  • Silver CityOn date
  • Rajatbhoomi 1+54 mo
  • Rajatbhoomi-4+39 mo
Show all 64 registrations
  • Silver ParkOn date
  • Highway Glory+60 mo
  • Dhanbhoomi 2On date
  • Silverpark - 5On date
  • Silverpark 2On date
  • Silverpark - 6On date
  • Silverpark - 3On date
  • Rajatbhoomi - 7On date
  • Rajatbhoomi - 8On date
  • Silver CityOn date
  • Rajatbhoomi-10On date
  • Rajatbhoomi-9On date
  • Vrindavan Park - 2On date
  • Silver Park - 10On date
  • Silver Park - 9On date
  • Silverpark - 11On date
  • Silverpark - 7On date
  • Samruddhi3On date
  • Silverpark - 8On date
  • Samruddhi 5On date
  • Samruddhi 1On date
  • Silver Park - 12On date
  • Samruddhi 2On date
  • Samruddhi - 6On date
  • Samruddhi 4On date
  • Rajatbhoomi 11On date
  • Silver Icon - 1On date
  • Vrindavan Park-5On date
  • Silver Park-13On date
  • Samruddhi 8On date
  • Silver Park-14On date
  • Vrindavan Park-3On date
  • Vrindavan Park-6On date
  • Silver Park 15On date
  • Silver Pride - 1On date
  • Silver Star - 1On date
  • Silver Star-2On date
  • Silver Pride - 3On date
  • Silver WindsOn date
  • Silver Woods 1On date
  • Silver Star 4On date
  • Vrindavan ParkOn date
  • Rajatbhoomi - 13On date
  • Vrindavan ParkOn date
  • Vrindavan ParkOn date
  • Vrindavan ParkOn date
  • Silver Star - 5On date
  • Vrindavan ParkOn date
  • Silver Star - 6On date
  • Vrindavan ParkOn date
  • Vrindavan ParkOn date
  • Rajatbhoomi - 12On date
  • Silver EstateOn date
  • Vrindavan ParkOn date

Track record notes

  • 18 of 26 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 87 months, for Rajatbhoomi - 3 (P50500017744).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology