RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
RegisteredMahaRERA status: Certificate Signed
P50500034791
Samruddhi 1 · Sukali(Gupchup), Nagpur · Tirupati Developers
Promised for 31 Mar 2027 and not extended so far.
4 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 51
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
Commencement certificateView
Show all 51 documents
Layout planView
Layout planView
Layout planView
Title reportView
Title reportView
Layout planView
Title reportView
Title reportView
Title reportView
OtherView
OtherView
OtherView
Form 1View
Allotment letterView
OtherView
Title reportView
Title reportView
Title reportView
Title reportView
Title reportView
Building planView
Building planView
Building planView
Commencement certificateView
Commencement certificateView
Form BView
Form BView
Form BView
Form BView
Form 1View
Form 1View
OtherView
OtherView
OtherView
Form 1View
Form 1View
Form 1View
Form 1View
Layout planView
Layout planView
Layout planView
Encumbrance detailsView
Layout planView
Orders 0
No MahaRERA order or list names this number.
Questions about P50500034791
Is Samruddhi 1 delayed?
Not so far. MahaRERA records a promised completion of 31 Mar 2027, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500034791.
Who is the promoter?
MahaRERA records Tirupati Developers as the promoter of P50500034791.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500034791.
Answers are generated from the record.
Data through23 Nov 2026, 01:44SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology