Vrindavan Park - 2 · Khadka, Nagpur · Tirupati Developers
Promised for 31 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.
10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 31 Dec 2025, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 45
Show all 45 documents
Orders 0
No MahaRERA order or list names this number.
Questions about P50500030295
Is Vrindavan Park - 2 delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500030295.
Who is the promoter?
MahaRERA records Tirupati Developers as the promoter of P50500030295.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500030295.