Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P50500008330
Suvarnabhoomi · Dongargaon (535927), Nagpur · Tirupati Developers
Promised for 30 Sep 2020, extended to 31 Mar 2026 — and that date has passed without the project marked complete on MahaRERA.
6 years and 2 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2020 to 31 Mar 2026.
- !Risk: The latest completion date on record, 31 Mar 2026, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 18
Orders 0
No MahaRERA order or list names this number.
Questions about P50500008330
Is Suvarnabhoomi delayed?
Yes. MahaRERA records a promised completion of 30 Sep 2020, revised to 31 Mar 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500008330. The completion date moved from 30 Sep 2020 to 31 Mar 2026.
Who is the promoter?
MahaRERA records Tirupati Developers as the promoter of P50500008330.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500008330.
Answers are generated from the record.