Thane (M Corp.), Thane
Deedo IDDL-THN-THANE-39 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects898
Registrations993some projects hold several
Completion still due392601 past their date
Median extension4 months46% of registrations extended
Regulatory cases106on 32 projects
9 in 10 registrations run late here
993 MahaRERA registrations in Thane (M Corp.)
15 completed89 not yet due303 extended, not yet due586 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Thane (M Corp.)
898 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shivnath SkycityShivnath Developer | Due Apr 2029, extended 4 mo | — | — |
| JVM's CYNERGYZenith Home Maker | Due Apr 2029, extended 4 mo | — | — |
| Markandey SquareAarti Enterprises | Due Apr 2029, extended 4 mo | — | — |
| The OliveEkatva Buidcon | Due Apr 2029, extended 4 mo | — | 29% |
| Urban HeritageUrban Space Buildcon Private Limited | Due Apr 2027, extended 4 mo | — | 16% |
| Jivan Shanti Chs LtdMahesh Shriram Borkar | Completed | — | — |
| Krishna Wing CK Rudraksh Realtors LLP | Due Apr 2030, extended 4 mo | — | — |
| Krishna SolitaireInspiration SG Infracon LLP | Due Apr 2027, extended 4 mo | — | — |
| Tharwani StellaTharwani Realtors | Due Apr 2030, extended 4 mo | — | — |
| Dosti Westcounty - Phase 6 - Dosti MapleDosti Enterprises | Due Apr 2029, extended 4 mo | — | 9% |
| Raghunath Coop Housing SocietyShree Developers | 1 yr 5 mo late | — | — |
| Green Square Bldg. No 2bSquarefeet Enterprises | Due Apr 2028, extended 4 mo | — | 10% |
| Matru MandirParnad Anil Gupte | Due Dec 2026 | — | — |
| Veer VishwaVeer Life Spaces LLP | Due Jun 2027, extended 4 mo | — | — |
| The Address by GS Tower DRaymond Realty Limited | Due Jul 2029, extended 4 mo | — | 80% |
| Haware My First Home Shil PhataHaware Properties LLP | Due Apr 2031, extended 4 mo | — | — |
| Haware My First Home Shil Phata Phase 1 Bldg 2Haware Properties LLP | Due Apr 2031, extended 4 mo | — | — |
| Blue BerryAshwamedh Corporation | Due Jun 2027 | — | 59% |
| Intelligentia Segment by Haware PropertiesSuresh Kashinath Haware | Due Apr 2028, extended 4 mo | — | — |
| O22 Business ParkMidas Touch | Due Apr 2027, extended 4 mo | — | 30% |
| Ace AristoGaurav Land Corporation | 1 mo late | — | — |
| TEN X ERA Raymond Realty Tower ARaymond Realty Limited | Due Dec 2029, extended 4 mo | — | 69% |
| Virat SkyrosParam Developers | Due Apr 2031, extended 4 mo | — | — |
| Rameshwar Co-Op Housing Society Ltd.Aditya Associates | Due Jul 2027, extended 4 mo | — | 52% |
| Horizon BhumiMajestic Horizon Bhumi Developers | Due Jul 2028, extended 4 mo | — | 37% |
Nearby: other municipal areas in Thane
Navi Mumbai (M Corp.) · 271 projectsMirabhayandar (M Corp.) · 225 projectsBhayandar · 118 projectsMira Bhayandar (M Corp.) · 106 projectsNaupada · 72 projectsPanchpakhadi · 65 projectsNerul · 58 projectsGhansoli · 57 projectsMajiwade · 43 projectsMumbra · 28 projectsOwale · 28 projectsVashi · 28 projects
Most active promoters
- Roma Builders Private Limited24 projects
- Macrotech Developers Limited14 projects
- Lodha Developers Limited11 projects
- Raymond Realty Limited9 projects
- Sai Shrushti Enterprises9 projects
- Agile Real Estate Pvt. Ltd8 projects
- Acme Housing India Private Limited7 projects
- Aditya Associates7 projects
- Provident Housing Limited6 projects
- Puranik Builders Limited6 projects
Thane (M Corp.), in questions
How many projects in Thane (M Corp.) run late?
9 in 10 MahaRERA registrations (889 of 993): their completion date was extended or has passed, data through 14 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Thane (M Corp.) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology