9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects898
Registrations993some projects hold several
Completion still due392601 past their date
Median extension4 months46% of registrations extended
Regulatory cases106on 32 projects

9 in 10 registrations run late here

993 MahaRERA registrations in Thane (M Corp.)

15 completed89 not yet due303 extended, not yet due586 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Thane (M Corp.)

898 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Veer HeightsVeer Life Spaces LLPDue Apr 2028——
Ashar Merac Phase IAjay Pratap AsharDue Apr 2029, extended 4 mo—68%
Chandrangan Residency Phase-VEkveera EnterprisesDue Apr 2028, extended 4 mo—14%
Dosti West County - Phase 7 - Dosti WillowDosti EnterprisesDue Mar 2028——
Maruti HomesJay Shree Krishna EnterprisesDue Mar 2027——
Shree ApartmentJoshi And Yash Developers LLPDue Dec 2026——
Urban Hills Phase 1Lotus GroupDue Apr 2028——
Blue Nile ResidencyBapat ConstructionsDue Apr 2028, extended 4 mo——
Al Balad Residency IIunity realtyDue Oct 2029, extended 4 mo——
Chandrangan Residency Phase-IVEkveera EnterprisesDue Apr 2027, extended 4 mo—38%
Navkamal Pushpa CHSDream Realtors6 mo late—28%
Regency VertexRegency Buildspaces LLPDue Apr 2029, extended 4 mo——
SunshineSiddhivinayak DevelopersDue Apr 2029, extended 4 mo——
Jagjeet ResidencyDream HomesDue Jul 2028, extended 4 mo——
Shivalaya HeightsRudis InfraDue Oct 2028, extended 4 mo—10%
Mahavir Vista And Vista PointVinayak DevelopersDue Apr 2029, extended 4 mo——
Shree Ram Krishna GardenShree Salasar SahakarDue Mar 2029——
Aura Business CenterAum DevelopersDue Apr 2027, extended 4 mo——
SwarajyaSailavkik Realty Private LimitedDue Jul 2027, extended 4 mo—78%
Alhad Co-Op. Hsg. Soc. LtdAnantnath Developers11 mo late——
PrimeraAgile Real Estate Dev Private LimitedDue Dec 2029——
Mukta AvenueMatoshree Space Builders And DevelopersDue Apr 2028, extended 4 mo——
Dosti Planet North - Dosti CrownChalama Infraproperties Private LimitedDue Jul 2028, extended 4 mo—97%
Orbit Business HubEkatva DevelopersDue Apr 2029, extended 4 mo—19%
Deepjyoti Chs LtdBorkar RealtyDue Oct 2028, extended 4 mo——
Thane (M Corp.) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roma Builders Private Limited24 projects
  2. Macrotech Developers Limited14 projects
  3. Lodha Developers Limited11 projects
  4. Raymond Realty Limited9 projects
  5. Sai Shrushti Enterprises9 projects
  6. Agile Real Estate Pvt. Ltd8 projects
  7. Acme Housing India Private Limited7 projects
  8. Aditya Associates7 projects
  9. Provident Housing Limited6 projects
  10. Puranik Builders Limited6 projects

Thane (M Corp.), in questions

How many projects in Thane (M Corp.) run late?

9 in 10 MahaRERA registrations (889 of 993): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Thane (M Corp.) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology