Shahapur, Thane
Deedo IDDL-THN-SHAHAPUR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects224
Registrations239some projects hold several
Completion still due91114 past their date
Median extension4 months49% of registrations extended
Regulatory cases32on 9 projects
8 in 10 registrations run late here
239 MahaRERA registrations in Shahapur and the places within it
3 completed17 not yet due74 extended, not yet due111 past even the latest date34 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Shahapur
224 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Dream NestingMaitri Homes | Due Apr 2028, extended 4 mo | — | — |
| Galaxy TowerEamkay Enterprises | Due Apr 2027, extended 4 mo | — | — |
| Sava ArcadeSava Developers | 1 mo late | — | — |
| Regal AvenueSagar Prakash Shah | 1 yr 10 mo late | — | — |
| DvineInfinite Assets Property Developers LLP | Due Apr 2029, extended 4 mo | — | — |
| Lotus PridePankaj Pandharinath Jage | Due Apr 2028, extended 4 mo | — | 3% |
| Rustomjee Belle VueKeystone Realtors Limited | Due Apr 2028, extended 4 mo | — | — |
| Shiv Shambho HeightsShiv Shambho Construction | Due Mar 2028 | — | — |
| Devraj Regency 3Shrivighanharta Realty (Opc) Private Limited | Due Mar 2027 | — | — |
| ShubhvastuSavjibhai Bavjibhai Kodinariya | Due Apr 2029, extended 4 mo | — | — |
| Rivera HomesKhushi Developers | Due Apr 2029, extended 4 mo | — | 8% |
| Zayana Resort ResidencesTilak construction co | Due Apr 2031, extended 4 mo | — | — |
| Bhagwati HeightsPerfect Reality | Due Apr 2028, extended 4 mo | — | 23% |
| Maheshvara AvenueKalyani Shivaji Gorale | Due Jun 2029 | — | — |
| Sai Sheetal ApartmentSagar Ganesh Kadav | Due May 2027, extended 4 mo | — | — |
| Vimal ResidencyNirmiti Infra | Due Apr 2028, extended 4 mo | — | 32% |
| Arya ApartmentSeema Ramesh Kadav | Due Apr 2029, extended 4 mo | — | — |
| Suraj OrchidNirmiti Builders & Developers | Completed | — | — |
| Arya ResidencyR P Enterprises | 5 mo late | — | 29% |
| The VeniscapeMivaan Buildcon Private Limited | Due Jul 2030, extended 4 mo | — | — |
| Sawant HeightsAkash Ashok Sawant | Due Apr 2027, extended 4 mo | — | 40% |
| Sitabai ApartmentDosti Construction | Due Mar 2028 | — | 14% |
| Kasturi ParadiseKastuti Developers | Due Jul 2028, extended 4 mo | — | — |
| VisavaRudrik Developers | Due Apr 2028, extended 4 mo | — | — |
| Awasare HeightsRajkumar Tuljaram Aswani | Due Jan 2027, extended 4 mo | — | 7% |
Nearby: other talukas in Thane
Most active promoters
- Jashnani Construction Private Limited8 projects
- Kaiyomerz Cowas Palia3 projects
- St. Angelo's Vnct Ventures Pvt. Ltd3 projects
- Aadinath Builders & Developers2 projects
- Green Lifespaces2 projects
- Jashnani Construction Private Limited2 projects
- Jashnani Constructions Private Limited2 projects
- Jay Service And Consultant2 projects
- Karrm Infrastructure Private Limited2 projects
- Kishor Nana Khambalkar2 projects
Shahapur, in questions
How many projects in Shahapur run late?
8 in 10 MahaRERA registrations (185 of 239): their completion date was extended or has passed, data through 29 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shahapur by Deedo. Medians on fewer than 3 deeds are not shown.
Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology