Deedo IDDP-THN-3TZHCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.
Khativali, Thane 421601 · by Savjibhai Bavjibhai Kodinariya
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 31 May 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- G Wing8 floors · 88 units0% booked
- H Wing7 floors · 56 units0% booked
- I Wing7 floors · 49 units0% booked
- J Wing7 floors · 49 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700056449
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700056449 | 31 May 2024 | 31 Dec 2028 | 30 Apr 2029 | Savjibhai Bavjibhai Kodinariya | Project page |
Documents109
1 document held by Deedo, 108 filings listed on MahaRERA's project page
Finance
Show all 109 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardPAN SAVJIBHAI.pdf · uploaded 29 Mar 2024Source
- 1 a Details of encumbrances concerned to FinanceENCUMBRANCE LEGAL.pdf · uploaded 29 Mar 2024Source
- 1 b Details of encumbrances concerned to LegalENCUMBRANCE LEGAL.pdf · uploaded 29 Mar 2024Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 29 Mar 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBP 1.pdf · uploaded 29 Mar 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentBP 2.pdf · uploaded 29 Mar 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentBP 3.pdf · uploaded 29 Mar 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentBP 4.pdf · uploaded 29 Mar 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentBP 5.pdf · uploaded 29 Mar 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC COPY 1.pdf · uploaded 29 Mar 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCC COPY 2.pdf · uploaded 29 Mar 2024Source
- 1 Declaration about Commencement CertificateDECLARATION COMMENCEMENT CERTIFICATE.pdf · uploaded 29 Mar 2024Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 29 Mar 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST.pdf · uploaded 29 Mar 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf · uploaded 29 Mar 2024Source
- 1 Deviation Report with respect to Allotment letterDEVIATION REPORT AL.pdf · uploaded 29 Mar 2024Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT AFS.pdf · uploaded 29 Mar 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 2 Apr 2024Source
- 1 Proforma of Allotment letterDRAFT ALLOTMENT LETTER.pdf · uploaded 2 Apr 2024Source
- 1 Other – TechnicalDECLARATION CUM UNDERTAKING NEW.pdf · uploaded 4 Apr 2024Source
- 1 Other – FinancePOWER OF ATTORNEY.pdf · uploaded 16 Apr 2024Source
- 3 Commencement Certificates / NA Order for plotted developmentCC MAIL.pdf · uploaded 24 Apr 2024Source
- 1 Other – LegalSALE DEED PART 1 OF 3.pdf · uploaded 24 Apr 2024Source
- 2 Other – LegalSALE DEED PART 2 OF 3.pdf · uploaded 24 Apr 2024Source
- 3 Other – LegalSALE DEED PART 3 OF 3.pdf · uploaded 24 Apr 2024Source
- 4 Other – Legal7-12 EXTRACT.pdf · uploaded 24 Apr 2024Source
- 2 a Details of encumbrances concerned to FinanceENCUMBRANCE FINANCE.pdf · uploaded 25 Apr 2024Source
- 2 b Details of encumbrances concerned to LegalENCUMBRANCE FINANCE.pdf · uploaded 25 Apr 2024Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 25 Apr 2024Source
- 1 Copy of the legal title reportTITLE.pdf · uploaded 11 May 2024Source
- 1 Proforma of Agreement for saleAFS Royal Developers.pdf · uploaded 11 May 2024Source
- 1 Proforma of Agreement for saleRERA_Draft_for_Plot_No-7 PDF FORMAT.pdf · uploaded 7 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 -JUNE-24.pdf · uploaded 27 Dec 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-2 JUNE-24.pdf · uploaded 27 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-1 -JUNE-24.pdf · uploaded 27 Dec 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHI-1 SEP-24.pdf · uploaded 28 Dec 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form- 3 june-24pdf.pdf · uploaded 28 Dec 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form- 3 Sep-24pdf.pdf · uploaded 28 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng-2 JUNE-24.pdf · uploaded 28 Dec 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng-2 SEP-24.pdf · uploaded 28 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form-1 -compressed.pdf · uploaded 31 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3.pdf · uploaded 31 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form-2.pdf · uploaded 31 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3 Q-2-.pdf · uploaded 12 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form-1.pdf · uploaded 26 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form- 2.pdf · uploaded 26 Apr 2025Source
- Form 1FORM 1 MAR 25.pdf · uploaded 14 Jul 2025Source
- Form 2FORM 2 MAR 25.pdf · uploaded 14 Jul 2025Source
- Form 3FORM 3 MAR 25.pdf · uploaded 14 Jul 2025Source
- Disclosure of Sold and Booked InventorySOLD UNSOLD MAR 25.pdf · uploaded 14 Jul 2025Source
- Form 1FORM 1 JUN 25.pdf · uploaded 26 Nov 2025Source
- Form 2FORM 2 JUN 25.pdf · uploaded 26 Nov 2025Source
- Form 3FORM 3 JUN 25.pdf · uploaded 26 Nov 2025Source
- Disclosure of Sold and Booked InventorySOLD UNSOLD JUN 25.pdf · uploaded 26 Nov 2025Source
- Form 1FORM 1 SEPT 25.pdf · uploaded 29 Nov 2025Source
- Form 2FORM 2 SEPT 25.pdf · uploaded 29 Nov 2025Source
- Form 3FORM 3 SEPT 25.pdf · uploaded 29 Nov 2025Source
- Disclosure of Sold and Booked InventorySOLD UNSOLD SEPT 25.pdf · uploaded 29 Nov 2025Source
- Form 5 (FY 2024-2025)FORM 5 25.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1FORM 1 DEC 25.pdf · uploaded 13 Mar 2026Source
- Withdrawal Update Form 2FORM 2 DEC 25.pdf · uploaded 13 Mar 2026Source
- Withdrawal Update Form 3FORM 3 DEC 25.pdf · uploaded 13 Mar 2026Source
- Form 2A (FY 2024-2025)FORM 2A 24-25.pdf · uploaded 9 Apr 2026Source
- Withdrawal Update Form 1FORM 1 MAR 26.pdf · uploaded 19 Jun 2026Source
- Withdrawal Update Form 2FORM 2 MAR 26.pdf · uploaded 19 Jun 2026Source
- Withdrawal Update Form 3Form 3 Mar 26.pdf · uploaded 19 Jun 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 20 Aug 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 20 Aug 2026Source
- Withdrawal Update Form 3FORM-3_compressed.pdf · uploaded 20 Aug 2026Source
Technical
- DocumentLAYOUT PLAN.pdf · uploaded 29 Mar 2024Source
- DocumentBP 1.pdf · uploaded 29 Mar 2024Source
- DocumentBP 2.pdf · uploaded 29 Mar 2024Source
- DocumentBP 3.pdf · uploaded 29 Mar 2024Source
- DocumentBP 4.pdf · uploaded 29 Mar 2024Source
- DocumentBP 5.pdf · uploaded 29 Mar 2024Source
- Other – TechnicalDECLARATION CUM UNDERTAKING NEW.pdf · uploaded 4 Apr 2024Source
- DocumentLAYOUT PLAN.pdf · uploaded 10 Jan 2026Source
- DocumentBP 6.pdf · uploaded 10 Jan 2026Source
- DocumentBP 7.pdf · uploaded 10 Jan 2026Source
- DocumentBP 8.pdf · uploaded 10 Jan 2026Source
- DocumentBP 1.pdf · uploaded 9 Apr 2026Source
- DocumentBP 2.pdf · uploaded 9 Apr 2026Source
- DocumentBP 3.pdf · uploaded 9 Apr 2026Source
- DocumentBP 4.pdf · uploaded 9 Apr 2026Source
- DocumentBP 5.pdf · uploaded 9 Apr 2026Source
- DocumentBP 6.pdf · uploaded 9 Apr 2026Source
- DocumentBP 7.pdf · uploaded 9 Apr 2026Source
- DocumentBP 8.pdf · uploaded 9 Apr 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 7 GUT NO 122 123 124 125 126 127 128 131 134 140 143A 143B 144 146A 146B 147
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK242 units in all
- Address
- Plot No 7 Gut No 122 123 124 125 126 127 128 131 134 140 143a 143b 144 146a 146b 147, Plot No 7, KhativaliPIN 421601
- Village
- Khativali, Shahapur taluka
- Location
- 19.42130, 73.27258
- Land area for this project
- 4,158 sq m (44,756 sq ft)
- Permissible built-up area
- 10,802 sq m (1,16,274 sq ft)
- Sanctioned built-up area
- 10,802 sq m (1,16,274 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 7 GUT NO 122 123 124 125 126 127 128 131 134 140 143A 143B 144 146A 146B 147
Boundaries
- North
- Gut No 142
- South
- Gut No 140 Part
- East
- Gut No 141 203 206
- West
- 12 Mtr Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking242 units
0 of 242 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| G Wing | 1BHK | 32.19 sq m · 346 sq ft | 44 | 0 |
| G Wing | 1BHK | 34.35 sq m · 370 sq ft | 44 | 0 |
| H Wing | 1BHK | 32.19 sq m · 346 sq ft | 56 | 0 |
| I Wing | 1BHK | 26.42 sq m · 284 sq ft | 21 | 0 |
| I Wing | 1BHK | 30.14 sq m · 324 sq ft | 28 | 0 |
| J Wing | 1BHK | 26.42 sq m · 284 sq ft | 21 | 0 |
| J Wing | 1BHK | 30.14 sq m · 324 sq ft | 28 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Destination Architecture Interior Designs | — |
| Chartered accountant | R V Thakkar & Associates | — |
| Engineer | Hemal Mahendrabhai Shankhala | — |
| Engineer | Shravani Consultants | — |
Source: MahaRERA project page. Contact details are not shown.