RERA projects in Kopri
1 project under 1 MahaRERA registration, registered 2024–2024. None has an extended completion date on record.
1RERA projects
1Registrations
1Completion still due0 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2024 | 1 |
Projects in Kopri
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Amar PushpakunjAvighna Redevelopers | P51700054590 | 31 Jan 2024 | 31 Dec 2027 | — | Not yet due | 0 |
Other localities in Thane
- Thane (M Corp.)1,174 projects
- Navi Mumbai (M Corp.)414 projects
- Mirabhayandar (M Corp.)264 projects
- Mira Bhayandar (M Corp.)113 projects
- Bhayandar79 projects
- Panchpakhadi25 projects
- Nerul18 projects
- Vartaknagar14 projects
- Navghar10 projects
- Kalwa9 projects
- Kolshet9 projects
- Majiwade9 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Avighna Redevelopers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology