Kalyan Nagari
Deedo IDDP-THN-C019Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.
Kon (Ct), Thane 421302 · by Honest Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 13 Apr 2018, completion promised 30 Mar 2024, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700016054
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700016054 | 13 Apr 2018 | 30 Mar 2024 | 30 Mar 2024 | Honest Developers | Project page |
Documents117
3 documents held by Deedo, 114 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardPAN OF HONEST DEVELOPERS.pdf · uploaded 5 Apr 2018Source
Legal
Migrated
- 1 PAN CardPAN OF HONEST DEVELOPERS.pdf · uploaded 5 Apr 2018Source
Show all 117 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportSEARCH REPORT.pdf · uploaded 5 Apr 2018Source
- 1 Details of encumbrancesSelf Declaration for non encumbrance.pdf · uploaded 5 Apr 2018Source
- 1 Building Plan Approval (IOD)COMMENCEMENT CERTIFICATE.pdf · uploaded 5 Apr 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 5 Apr 2018Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 5 Apr 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT'S CERTIFICATE.pdf · uploaded 5 Apr 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER'S CERTIFICATE.pdf · uploaded 5 Apr 2018Source
- 1 Proforma of Allotment letterHONEST RERA DRAFT AGREEMENT.pdf · uploaded 5 Apr 2018Source
- 1 Copy of Layout Approval (in case of layout)TYPICAL FLOOR BLDG B2.pdf · uploaded 11 Apr 2018Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 11 Apr 2018Source
- 1 Otherletter for edit.pdf · uploaded 13 Dec 2018Source
- 1 Certificates of CA (Form 5)Honest Developers-Form 5.pdf · uploaded 4 Jan 2019Source
- 2 Proforma of Allotment letterDRAFT AGREEMENT KALYAN NAGARI.pdf · uploaded 2 Sep 2019Source
- 2 Copy of Layout Approval (in case of layout)PLAN.pdf · uploaded 19 Oct 2019Source
- 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 19 Oct 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH.pdf · uploaded 19 Oct 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG.pdf · uploaded 19 Oct 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 (1).pdf · uploaded 15 Nov 2019Source
- 3 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 9 Mar 2020Source
- 4 Copy of Layout Approval (in case of layout)FLOOR_compressed.pdf · uploaded 9 Mar 2020Source
- 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 9 Mar 2020Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH.pdf · uploaded 9 Mar 2020Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG.pdf · uploaded 9 Mar 2020Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT'S CERTIFICATE_compressed (1).pdf · uploaded 18 Aug 2020Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG CERTIFICATE_compressed.pdf · uploaded 18 Aug 2020Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate.pdf · uploaded 27 Oct 2020Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate.pdf · uploaded 27 Oct 2020Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineer-s certificate for Quality Assurance 02-Jan-2021 16-12-31_compressed.pdf · uploaded 18 Jan 2021Source
- 4 Commencement Certificates / NA Order for plotted developmentcommencement certificate 1-3.pdf · uploaded 22 Jan 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 HONEST.pdf · uploaded 5 Feb 2021Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT (1).pdf · uploaded 20 May 2021Source
- 5 Commencement Certificates / NA Order for plotted development20210429160516.pdf · uploaded 20 Jul 2021Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Form 1 17-Jul-2021 13-35-40.pdf · uploaded 20 Jul 2021Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate form 2 17-Jul-2021 13-34-27.pdf · uploaded 20 Jul 2021Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD BOOKED INVENTORY_compressed.pdf · uploaded 20 Jul 2021View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A Honest developers (1).pdf · uploaded 6 Aug 2021Source
- 1 Declaration about Commencement CertificateRERA .pdf · uploaded 14 Aug 2021Source
- 2 Certificates of CA (Form 3)FORM -3 - CA Certificate.pdf · uploaded 14 Aug 2021Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1_compressed.pdf · uploaded 15 Oct 2021Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2_compressed.pdf · uploaded 15 Oct 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A_compressed.pdf · uploaded 15 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5.pdf · uploaded 15 Oct 2021Source
- 5 Copy of Layout Approval (in case of layout)PLANS 1 AND 2.pdf · uploaded 30 Oct 2021Source
- 6 Copy of Layout Approval (in case of layout)plan 3.pdf · uploaded 30 Oct 2021Source
- 7 Copy of Layout Approval (in case of layout)plan 4.pdf · uploaded 30 Oct 2021Source
- 8 Copy of Layout Approval (in case of layout)plan 5.pdf · uploaded 30 Oct 2021Source
- 9 Copy of Layout Approval (in case of layout)plan 6.pdf · uploaded 30 Oct 2021Source
- 10 Copy of Layout Approval (in case of layout)plan 7.pdf · uploaded 30 Oct 2021Source
- 11 Copy of Layout Approval (in case of layout)plan 8.pdf · uploaded 30 Oct 2021Source
- 6 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 30 Oct 2021Source
- 3 Certificates of CA (Form 3)Signed CA Certificate -Kalyan Nagri New Format1 (1).pdf · uploaded 25 Mar 2022Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 8 Apr 2022Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 (3)(1).pdf · uploaded 8 Apr 2022Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A (7).pdf · uploaded 8 Apr 2022Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect form 1.pdf · uploaded 22 Jul 2022Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer form 2.pdf · uploaded 22 Jul 2022Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)kalyan nagari architect form 1.pdf · uploaded 28 Oct 2022Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)kalyan nagari engineer form 2.pdf · uploaded 28 Oct 2022Source
- 2 Certificates of CA (Form 5)FORM 5 HONEST DEVLOPERS FY 21-22.pdf · uploaded 19 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 HONEST DEVLOPERS FY 21-22.pdf · uploaded 19 Jan 2023Source
- 4 Certificates of CA (Form 3)signed CA Certificate -Kalyan Nagri Dec 22 - SIGNED.pdf · uploaded 4 Mar 2023Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT'S CERTIFICATE.pdf · uploaded 5 Apr 2023Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER'S CERTIFICATE.pdf · uploaded 5 Apr 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Daffodil Society Registration Certificate.pdf · uploaded 5 Apr 2023Source
- 5 Certificates of CA (Form 3)CA CERTIFICATE FORM 3 12 20.pdf · uploaded 7 Oct 2023Source
- 6 Certificates of CA (Form 3)FORM -3 08 21.pdf · uploaded 7 Oct 2023Source
- 7 Certificates of CA (Form 3)3 Certificates of CA (Form 3).pdf · uploaded 7 Oct 2023Source
- 8 Certificates of CA (Form 3)4 Certificates of CA (Form 3).pdf · uploaded 7 Oct 2023Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE APRIL TO JUNE.pdf · uploaded 20 Oct 2023Source
- 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE JULY TO SEPTEMBER.pdf · uploaded 20 Oct 2023Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE APRIL TO JUNE.pdf · uploaded 20 Oct 2023Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE JULY TO SEPTEMBER.pdf · uploaded 20 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2 A 2022.pdf · uploaded 20 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 2023.pdf · uploaded 20 Oct 2023Source
- 1 CERSAI detailsCersai Declaration .pdf · uploaded 29 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23.pdf · uploaded 6 Dec 2023Source
- 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Kalyan Nagari - Architect Certificate.pdf · uploaded 12 Jan 2024Source
- 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Kalyan Nagari - Engineer Certificate.pdf · uploaded 12 Jan 2024Source
- 9 Certificates of CA (Form 3)Form 3 June 2023.pdf · uploaded 19 Jan 2024Source
- 10 Certificates of CA (Form 3)Kalyan Nagari form 3 September 2023.pdf · uploaded 3 Feb 2024Source
- 11 Certificates of CA (Form 3)Form 3 Dec 2023 (1).pdf · uploaded 15 Mar 2024Source
- 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 March 2024.pdf · uploaded 17 Apr 2024Source
- 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 March 2024.pdf · uploaded 17 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A March 2024.pdf · uploaded 2 May 2024Source
- 12 Certificates of CA (Form 3)CA CERTIFICATE FORM 3.pdf · uploaded 2 May 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 23-24.pdf · uploaded 23 Nov 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 29 Nov 2024Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 29 Nov 2024Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 engineer Certificate.pdf · uploaded 29 Nov 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 engineer Certificate.pdf · uploaded 29 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 3 Dec 2024Source
Technical
- DocumentCOMMENCEMENT CERTIFICATE.pdf · uploaded 5 Apr 2018Source
- DocumentTYPICAL FLOOR BLDG B2.pdf · uploaded 11 Apr 2018Source
- DocumentPLAN.pdf · uploaded 19 Oct 2019Source
- DocumentLAYOUT.pdf · uploaded 9 Mar 2020Source
- DocumentFLOOR_compressed.pdf · uploaded 9 Mar 2020Source
- DocumentPLANS 1 AND 2.pdf · uploaded 30 Oct 2021Source
- Documentplan 3.pdf · uploaded 30 Oct 2021Source
- Documentplan 4.pdf · uploaded 30 Oct 2021Source
- Documentplan 5.pdf · uploaded 30 Oct 2021Source
- Documentplan 6.pdf · uploaded 30 Oct 2021Source
- Documentplan 7.pdf · uploaded 30 Oct 2021Source
- Documentplan 8.pdf · uploaded 30 Oct 2021Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO.201
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Address
- Survey No.201, Kon Village, BhiwandiPIN 421302
- Village
- kon (CT), Bhiwandi taluka
- Location
- 19.25403, 73.10460
- Land area for this project
- 11,890 sq m (1,27,983 sq ft)
- Permissible built-up area
- 9,223 sq m (99,273 sq ft)
- Sanctioned built-up area
- 8,687 sq m (93,504 sq ft)
- Recreational open space
- 1,944 sq m (20,926 sq ft)
- Designated bank account
- 82
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO.201
Boundaries
- North
- Survey No 200
- South
- Survey No 193
- East
- Survey No 193
- West
- Survey No 193
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals28
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | K K And Associates | — |
| Engineer | K K And Associates | — |
| Registered real estate agent | 4gitsolutionsindiapvtltd | — |
| Registered real estate agent | Ad Homes | — |
| Registered real estate agent | Ajay Shribastak | — |
| Registered real estate agent | Arjun Indaman Chauhan | — |
| Registered real estate agent | Ask Realtors | — |
| Registered real estate agent | Bright Real Estate Consultant | — |
Show all 28 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Registered real estate agent | Dhaval Jayantilal Shingadya | — |
| Registered real estate agent | Dilip Keshav Dhamapurkar | — |
| Registered real estate agent | Gargi Quadri | — |
| Registered real estate agent | Girish Ramchand Valecha | — |
| Registered real estate agent | Horizon Financial & Properties Advisers LLP | — |
| Registered real estate agent | Horizon Financial &Properties Advisers Private Limited | — |
| Registered real estate agent | ICICI Home Finance Company Limited | — |
| Registered real estate agent | Kaushik Sanjay Joshi | — |
| Registered real estate agent | Krishna Kumar Purushottamlal Bhartia | — |
| Registered real estate agent | Manoj Krishna Mhatre | — |
| Registered real estate agent | Meenu Choudhary | — |
| Registered real estate agent | Nilesh Singh | — |
| Registered real estate agent | Oxyzen-Ug | — |
| Registered real estate agent | Prashant Prabhakar Kadam | — |
| Registered real estate agent | Pravin Ramchandra Gole | — |
| Registered real estate agent | Psk Business Solutions LLP | — |
| Registered real estate agent | Tahseen Ali | — |
| Registered real estate agent | The Mw Group | — |
| Registered real estate agent | Vhci Realtors Pvt Ltd | — |
| Registered real estate agent | Vishal Girish Sonis | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kon (Ct)
- Aai Mauli Park Building BRERA P51700081073
- Sai Darshan D WingRERA PR1330002501864
- Millat ArcadeRERA P51700080861
- Kalyan EliteRERA P51700080574
- Kalyan VatikaRERA P51700079636
- Magus City Tower 2 LunarRERA P51700077802
- The LivinRERA P51700055755
- Tahoora ComplexRERA P51700055023
All 34 projects in Kon (Ct) · Compare Kalyan Nagari with another project