RERA projects in Khadavali
8 projects under 8 MahaRERA registrations, registered 2017–2025. 100% have a completion date extended beyond the one promised.
Locality
8RERA projects
8Registrations
7Completion still due1 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
22Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 4 |
| 2025 | 1 |
Projects in Khadavali
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aarti ParkAarti Builders | P51700080241 | 13 May 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Priyadarshini HeightsAgnihotri Realty | P51700077878 | 7 Nov 2024 | 30 Oct 2027 | 29 Feb 2028 | Extended 4 mo | 0 |
| Riviera TowerBlissful Towers LLP | P51700077539 | 20 Aug 2024 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Royal ResidencyAk Builders & Developers | P51700056482 | 5 Jun 2024 | 31 Jan 2029 | 31 May 2029 | Extended 4 mo | 0 |
| Pitambare TowerAditi Builders And Developers | P51700055596 | 4 Apr 2024 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Usha Joshi Park Phase IIIJ K T Group | P51700051064 | 22 May 2023 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Shree Gajanan Fortune CityArun Balu Patil | P51700013810 | 25 Oct 2017 | 30 Dec 2024 | 30 Dec 2026 | Extended 24 mo | 0 |
| Usha Joshi Park Phase BJ K T Builders & Developers | P51700012148 | 1 Sep 2017 | 30 Dec 2021 | 30 Jun 2023 | Extended 18 mo | 0 |
Other localities in Kalyan
Most active promoters
By projects registered here, as named on MahaRERA.
- Aarti Builders1 project
- Aditi Builders And Developers1 project
- Agnihotri Realty1 project
- Ak Builders & Developers1 project
- Arun Balu Patil1 project
- Blissful Towers LLP1 project
- J K T Builders & Developers1 project
- J K T Group1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology