Kavesar, Thane
Deedo IDDL-THN-KAVESAR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects15
Registrations17some projects hold several
Completion still due116 past their date
Median extension4 months71% of registrations extended
Regulatory cases1on 1 project
8 in 10 registrations run late here
17 MahaRERA registrations in Kavesar
4 not yet due7 extended, not yet due6 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Kavesar
15 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Hiranandani Westgate - HampsteadShoden Developers Private Limited | Due Apr 2033 | — | — |
| Snehkiran TowerSnehkiran Buildcon Private Limited | Due Sep 2027, extended 4 mo | — | — |
| Rosa Manhattan Phase 3Sai Uma Construction Private Limited | Due Oct 2032, extended 4 mo | — | — |
| Rosa SephoraAakash Darshan Buildcorp LLP | Due Apr 2030, extended 4 mo | — | — |
| Tropical BlissAmaatra Tropical Buildwell Pvt. Ltd. | Due Jan 2029, extended 4 mo | — | — |
Nearby: other villages in Thane
Thane (M Corp.) · 898 projectsNavi Mumbai (M Corp.) · 271 projectsMirabhayandar (M Corp.) · 225 projectsBhayandar · 118 projectsMira Bhayandar (M Corp.) · 106 projectsNaupada · 72 projectsPanchpakhadi · 65 projectsNerul · 58 projectsGhansoli · 57 projectsMajiwade · 43 projectsMumbra · 28 projectsOwale · 28 projects
Most active promoters
- Shoden Developers Private Limited2 projects
- Unnathi Estates2 projects
- Aakash Darshan Buildcorp LLP1 project
- Amaatra Tropical Buildwell Pvt. Ltd1 project
- Aniline Construction Company Private Limited1 project
- Godrej Macbricks Private Limited1 project
- Jangid Contructions1 project
- Lake Scape1 project
- Prescon Realtors & Infrastructures Pvt. Ltd1 project
- Sagar Enterprise1 project
Kavesar, in questions
How many projects in Kavesar run late?
8 in 10 MahaRERA registrations (13 of 17): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kavesar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology