Tropical Bliss
Deedo IDDP-THN-2SHSCompletion was pushed back 4 months, to Jan 2029; no MahaRERA orders on record; 0% of its units are booked.
Kavesar, Thane 400615 · Promoter: Amaatra Tropical Buildwell Pvt. Ltd.
Completion was pushed back 4 months, to Jan 2029
- This projectRegistered 3 Mar 2025, completion promised 30 Sep 2028, revised to 30 Jan 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700079373
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700079373 | 3 Mar 2025 | 30 Sep 2028 | 30 Jan 2029 | Amaatra Tropical Buildwell Pvt. Ltd. | Project page |
Documents61
1 document held by Deedo, 60 filings listed on MahaRERA's project page
Finance
Legal
- Declaration Form B09_T Bliss-Form B- Declaration by Promoter.pdf · uploaded 16 Dec 2024Source
- Other – LegalDevelopment Agreement Tropical Blis.pdf · uploaded 11 Feb 2025Source
- Other – LegalPOwer of Attonrney Scan _compressed.pdf · uploaded 11 Feb 2025Source
- Other – LegalDeclration for Landowner.pdf · uploaded 20 Feb 2025Source
- Legal Title reportLTR_merged.pdf · uploaded 20 Feb 2025Source
Show all 61 documentsShow fewer documents
Migrated
- 1 PAN Card01_T Bliss-PAN CARD- Amaatra tropical Buildwell Pvt Ltd.pdf · uploaded 16 Dec 2024Source
- 1 Copy of Layout Approval (in case of layout)05_T Bliss - Layout plan-Approved plan-Sheet -1.pdf · uploaded 16 Dec 2024Source
- 2 Copy of Layout Approval (in case of layout)05_T Bliss -Grd flr plan- Approved plan-Sheet -3.pdf · uploaded 16 Dec 2024Source
- 1 Declaration in FORM B09_T Bliss-Form B- Declaration by Promoter.pdf · uploaded 16 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)11_T Bliss -Form -1- Certificate of Architect -11-12-2024.pdf · uploaded 16 Dec 2024Source
- 1 Commencement Certificates / NA Order for plotted development07_T Bliss -CC- upto 11th floor.pdf · uploaded 16 Dec 2024Source
- 1 Building Plan Approval / NA Order for plotted development05_T Bliss -Grd flr plan- Approved plan-Sheet -3.pdf · uploaded 16 Dec 2024Source
- 2 Building Plan Approval / NA Order for plotted development06_T Bliss - Typical Flr plan-Approved plan-Sheet -4.pdf · uploaded 16 Dec 2024Source
- 1 Declaration about Commencement Certificate08_T Bliss-Declaration about CC.pdf · uploaded 16 Dec 2024Source
- 1 Deviation Report with respect to Allotment letter23_T Bliss- Deviation Report-Allotment Letter.pdf · uploaded 16 Dec 2024Source
- 1 Deviation Report with respect to model copy of Agreement24_T Bliss- Deviation Report-Agreement for Sale.pdf · uploaded 16 Dec 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations18_Disclosure of interst in the other organisation-Annexure A.pdf · uploaded 16 Dec 2024Source
- 1 Disclosure for secured/unsecured finance availed for the project14_Disclosure of secured unsecured finance availed for the project.pdf · uploaded 16 Dec 2024Source
- 2 Disclosure of Interest in Other Real Estate Organizations18_Disclosure of interst in the other organisation-Annexure A-Umesh Gupta.pdf · uploaded 18 Dec 2024Source
- 3 Disclosure of Interest in Other Real Estate Organizations18_Disclosure of interst in the other organisation-Annexure A-Anwar Khan.pdf · uploaded 18 Dec 2024Source
- 1 a Details of encumbrances concerned to FinanceNO incumbrance_Finance and Legal Letter.pdf · uploaded 26 Dec 2024Source
- 1 b Details of encumbrances concerned to LegalNO incumbrance_Finance and Legal Letter.pdf · uploaded 26 Dec 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-02 ENGINEER CERTIFICATE.pdf · uploaded 10 Jan 2025Source
- 1 Other – FinanceANNEXURE A DECLARATION CUM UNDERTAKING .pdf · uploaded 11 Jan 2025Source
- 1 Proforma of Allotment letterSCAN ALLOTMENT DRAFT_11zon.pdf · uploaded 13 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Tropical Bliss CA Certificate final 13 Jan 25.pdf · uploaded 13 Jan 2025Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 27 Jan 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format-A.pdf · uploaded 27 Jan 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 27 Jan 2025Source
- 1 Proforma of Agreement for saleRERA AGREEMENT DRAFT.pdf · uploaded 8 Feb 2025Source
- 2 Other – LegalPOwer of Attonrney Scan _compressed.pdf · uploaded 11 Feb 2025Source
- 1 Other – LegalDevelopment Agreement Tropical Blis.pdf · uploaded 11 Feb 2025Source
- 1 Copy of the legal title reportLTR_merged.pdf · uploaded 20 Feb 2025Source
- 3 Other – LegalDeclration for Landowner.pdf · uploaded 20 Feb 2025Source
- 1 Other – TechnicalForm B feb 2025.pdf · uploaded 28 Feb 2025Source
- Form 1Form 1.pdf · uploaded 25 Aug 2025Source
- Form 2Form 2.pdf · uploaded 25 Aug 2025Source
- Form 3Form 3.pdf · uploaded 25 Aug 2025Source
- Disclosure of Sold and Booked InventorySOLD UNSOLD RERA DATA.pdf · uploaded 25 Aug 2025Source
- Withdrawal Update Form 1Form 1 (Architect Certificate) Q2 July to Sept 25_0002.pdf · uploaded 18 Dec 2025Source
- Withdrawal Update Form 2Form 2 (Engineer Certificate) Q2 July to Sept 25_0001.pdf · uploaded 18 Dec 2025Source
- Withdrawal Update Form 3Form 3 (CA Certificate) - Q2 July to Sept_0001.pdf · uploaded 18 Dec 2025Source
- Withdrawal Update Form 1Architect Certificate Oct to Dec 25.pdf · uploaded 13 Mar 2026Source
- Withdrawal Update Form 2Engg Cert Oct to Dec 25_0001.pdf · uploaded 13 Mar 2026Source
- Withdrawal Update Form 3Form-3Dec25.pdf · uploaded 13 Mar 2026Source
- Withdrawal Update Form 1architect certificate jan to March.pdf · uploaded 16 Jun 2026Source
- Withdrawal Update Form 2Engg cert Jan to March 2026.pdf · uploaded 16 Jun 2026Source
- Withdrawal Update Form 3CA Certificate Tropical Bliss rera Jan to March 26 (1).pdf · uploaded 16 Jun 2026Source
- Withdrawal Update Form 1Form 1 june26.pdf · uploaded 22 Sep 2026Source
- Withdrawal Update Form 2engg cert apr june 26.pdf · uploaded 22 Sep 2026Source
- Withdrawal Update Form 3Form 3 june26.pdf · uploaded 22 Sep 2026Source
Technical
- Document05_T Bliss - Layout plan-Approved plan-Sheet -1.pdf · uploaded 16 Dec 2024Source
- Document05_T Bliss -Grd flr plan- Approved plan-Sheet -3.pdf · uploaded 16 Dec 2024Source
- Document05_T Bliss -Grd flr plan- Approved plan-Sheet -3.pdf · uploaded 16 Dec 2024Source
- Document06_T Bliss - Typical Flr plan-Approved plan-Sheet -4.pdf · uploaded 16 Dec 2024Source
- Other – TechnicalForm B feb 2025.pdf · uploaded 28 Feb 2025Source
Technical (Architect)
- DocumentForm 1 june26.pdf · uploaded 22 Sep 2026Source
Technical (Engineer)
- Documentengg cert apr june 26.pdf · uploaded 22 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals168(pt), 169/2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop63 units in all
- Address
- 168(pt), 169/2, & 170/2, Ghod bunder road, Sector no-6, Kavesar villagePIN 400615
- Village
- Kavesar, Thane taluka
- Location
- 19.25893, 72.96438
- Designated bank account
- 51
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Nala
- South
- ExistIng bldg-Type A
- East
- 30 mtr wide DP road
- West
- Existing bldg- Type B-wing A
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking63 units
0 of 63 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 36.35 sq m · 391 sq ft | 39 | 0 |
| 2BHK | 54.99 sq m · 592 sq ft | 20 | 0 |
| Shop | 21.93 sq m · 236 sq ft | 1 | 0 |
| Shop | 30.56 sq m · 329 sq ft | 1 | 0 |
| Shop | 32.34 sq m · 348 sq ft | 1 | 0 |
| Shop | 40.36 sq m · 434 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ten Folds Architects & consultants | — |
| Chartered accountant | M A Gupta & Associates | — |
| Engineer | Aniket Ramesh Torase | — |
| Engineer | Hansal Parikh & Associates | — |
| Engineer | Rajesh R Lavekar | — |
| Other | Anupams Infra | — |
Source: MahaRERA project page. Contact details are not shown.