RERA projects in Daighar

2 projects under 2 MahaRERA registrations, registered 2024–2026. 100% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
2Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20241
20250
20261

Projects in Daighar

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Central VistaThe Capitalist RealtyPR133000250216823 Jan 202631 Dec 203030 Apr 2031Extended 4 mo0
Bhoomi Castle, Phase IGajra Ventures Private LimitedP517000546442 Feb 202431 Dec 203030 Apr 2031Extended 4 mo0

Other localities in Thane

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Gajra Ventures Private Limited1 project
  2. The Capitalist Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology