7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects452
Registrations490some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects

7 in 10 registrations run late here

490 MahaRERA registrations in Bhiwandi and the places within it

3 completed90 not yet due189 extended, not yet due163 past even the latest date45 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhiwandi

452 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
R N PlazaR N InfraDue Dec 2032——
Arjun HeightsQuba VentureDue Apr 2030, extended 4 mo——
Vrundavan Park JaswandiShree Vastunirman DevelopersDue Oct 2028, extended 4 mo——
Sukruth AvadhSukruth Buildcon LLPDue Apr 2031, extended 4 mo——
Arunoday PlazaSankalp BuildersDue Apr 2027, extended 4 mo——
Vistara WorldVistara BuildconDue Oct 2029, extended 4 mo——
PushpanjaliRamlal Shankarlal JatDue Apr 2035, extended 4 mo——
Bhumi World SkyGebi LLPDue Dec 2028, extended 4 mo——
Millat ArcadeR K Buildcon5 mo late——
Leo Business ComplexLeo Infra And DeveloperDue Apr 2028, extended 4 mo——
Samruddhi ResidencyShree Samruddhi AssociatesDue Apr 2028, extended 4 mo——
Classic PlazaNew Classic ConstructionDue Apr 2029, extended 4 mo——
Vighnaharta ApartmentVinayak InfrabuildDue Jan 2027——
Radha Krishna NivasNitin Gajanan KaleDue Apr 2030, extended 4 mo——
Samruddhi KalashShree Samruddhi AssociatesDue Apr 2028, extended 4 mo——
Al-HasanAryan ConstructionDue Apr 2031, extended 4 mo——
Yuvan PrimeRanjana EnterprisesDue Sep 2028, extended 4 mo——
Kalyan EliteKalyan BuildconDue Feb 2028, extended 4 mo——
Nirvana HeightsShreeji DevelopersDue Dec 2029, extended 4 mo——
Puranjay HeightsRiddhi Siddhi LuxuriaDue Apr 2030, extended 4 mo——
Siyara CrownSiyara Realty Private LimitedDue Dec 2029——
Jangid EmpireJangid AssociatesDue Jul 2029, extended 4 mo——
Mb Green CourtMb DeveloperDue Apr 2030, extended 4 mo——
Padamavati HeavenSujeet Kumar Jeetpratap SinghDue Jul 2028, extended 4 mo——
Siyara Business ParkSiyara Realty Private LimitedDue Apr 2030, extended 4 mo——
Bhiwandi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Macrotech Developers Limited17 projects
  2. Lodha Developers Limited14 projects
  3. Arihant Enterprises7 projects
  4. Shakti Realty6 projects
  5. Infini Developers5 projects
  6. Adrika Developers Private Limited4 projects
  7. Al Araaf Infra Private Limited4 projects
  8. Siyara Realty Private Limited4 projects
  9. Kgi Realty Private Limited3 projects
  10. Maya Developer3 projects

Bhiwandi, in questions

How many projects in Bhiwandi run late?

7 in 10 MahaRERA registrations (352 of 490): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology