Bhiwandi, Thane
Deedo IDDL-THN-BHIWANDI7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects452
Registrations490some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects
7 in 10 registrations run late here
490 MahaRERA registrations in Bhiwandi and the places within it
3 completed90 not yet due189 extended, not yet due163 past even the latest date45 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Bhiwandi
452 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Rangari HeightsAyesha Constructions | Due May 2030, extended 4 mo | — | — |
| Adelphi A and BLodha Developers Limited | Due Jul 2031, extended 4 mo | — | — |
| Asgar HeightsIconic Builders & Developers | Due Apr 2035, extended 4 mo | — | — |
| Harsha Apartment Co-Operative Housing Society LimitedStonework Developers LLP | Due Apr 2032, extended 4 mo | — | — |
| Al Abbas Building No. 06Ayman Infra Constructions | Due Apr 2036, extended 4 mo | — | — |
| Taj PalaceShibla Developers LLP | Due Apr 2033, extended 4 mo | — | — |
| Samata HeightsSamata Co Op Housing Society Ltd | Due Sep 2030, extended 4 mo | — | — |
| Pentagon HeightsDamji Hari Constructions | Due Apr 2033, extended 4 mo | — | — |
| White OrchidSukte & Manyar Developers LLP | Due Apr 2031, extended 4 mo | — | — |
| Kiran HeightsBansikailas Estates LLP | Due Jul 2030, extended 4 mo | — | — |
| Riddhi Siddhi NXS N Builders and Developers | Due Apr 2030, extended 4 mo | — | — |
| Usha ParadiseSuchitra Developers | Due Apr 2029, extended 4 mo | — | — |
| Vijay Nagar GroupVijay Nagar Co-Operative Housing Society Limited | Due Apr 2030, extended 4 mo | — | — |
| Anaya ApartmentMohammad Azeem Mohiuddin Shaikh | Due Apr 2033, extended 4 mo | — | — |
| Shivmastu GreensSukruth Buildcon LLP | Due Apr 2030, extended 4 mo | — | — |
| Balaji Bliss - B WingBalaji Builders and Developers | Due Apr 2029, extended 4 mo | — | — |
| Kohinoor Uptown T7Kgi Realty Private Limited | Due Apr 2029, extended 4 mo | — | — |
| Morya Creek City Phase IMorya Infraconstruct Private Limited | Due Dec 2029 | — | — |
| Aai Mauli Park Building BHendar Laxman Mhatre | Due Apr 2028, extended 4 mo | — | — |
| Sai Darshan D WingTrimurti Enterprises | Due Apr 2030, extended 4 mo | — | — |
| Arbisha ApartmentArbisha Construction | Due Apr 2033, extended 4 mo | — | — |
| Atlanta LuxuriaSri Balaji Developer | Due Dec 2030 | — | — |
| Shree ParadiseTai Infrastructure | Due Mar 2027 | — | — |
| Silver AnantamSayam Enterprises LLP | Due Nov 2031, extended 4 mo | — | — |
| Rehman Complex Phase 2Iconic Reality | Due Dec 2030 | — | — |
Nearby: other talukas in Thane
Most active promoters
- Macrotech Developers Limited17 projects
- Lodha Developers Limited14 projects
- Arihant Enterprises7 projects
- Shakti Realty6 projects
- Infini Developers5 projects
- Adrika Developers Private Limited4 projects
- Al Araaf Infra Private Limited4 projects
- Siyara Realty Private Limited4 projects
- Kgi Realty Private Limited3 projects
- Maya Developer3 projects
Bhiwandi, in questions
How many projects in Bhiwandi run late?
7 in 10 MahaRERA registrations (352 of 490): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology