RERA projects in Bhandarli
1 project under 1 MahaRERA registration, registered 2020–2020. 100% have a completion date extended beyond the one promised.
1RERA projects
1Registrations
0Completion still due1 past their completion date
12 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
Projects in Bhandarli
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| 1771 EWS and 88 LIG tenements at Survey no.13, Bhandarli, Tal. Dist. Thane PMAY projectVivek Barve | P51700024403 | 11 Feb 2020 | 30 Mar 2023 | 29 Mar 2024 | Extended 12 mo | 0 |
Other localities in Thane
- Thane (M Corp.)1,174 projects
- Navi Mumbai (M Corp.)414 projects
- Mirabhayandar (M Corp.)264 projects
- Mira Bhayandar (M Corp.)113 projects
- Bhayandar79 projects
- Panchpakhadi25 projects
- Nerul18 projects
- Vartaknagar14 projects
- Navghar10 projects
- Kalwa9 projects
- Kolshet9 projects
- Majiwade9 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Vivek Barve1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology