RERA projects in Balkum

4 projects under 4 MahaRERA registrations, registered 2022–2026. None has an extended completion date on record.

4RERA projects
4Registrations
4Completion still due0 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221
20231
20240
20250
20262

Projects in Balkum

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vaikunth Cluster 3 Tower 3PEPL Developers Pvt LtdPR133202260115613 Jul 202630 Jun 2032—Not yet due0
Estella - Tower C and DAgile Real Estate Dev Private LimitedPR13310126000276 Apr 202630 Jun 2032—Not yet due0
Sumeet EliteVedant ConstructionP5170004875317 Jan 202331 May 2027—Not yet due0
Shraddha PeninsulaPadmagriha HeightsP517000457889 Jun 202231 Dec 2026—Not yet due0

Other localities in Thane

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Agile Real Estate Dev Private Limited1 project
  2. Padmagriha Heights1 project
  3. PEPL Developers Pvt Ltd1 project
  4. Vedant Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology