Balkum, Thane
Deedo IDDL-THN-BALKUM10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects23
Registrations28some projects hold several
Completion still due1513 past their date
Median extension4 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
28 MahaRERA registrations in Balkum
1 not yet due14 extended, not yet due13 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Balkum
23 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Vaikunth Cluster 3 Tower 3PEPL Developers Pvt Ltd | Due Oct 2032, extended 4 mo | — | — |
| Estella - Tower C and DAgile Real Estate Dev Private Limited | Due Oct 2032, extended 4 mo | — | — |
| One DostiDosti Enterprises | Due Jul 2031, extended 4 mo | — | — |
| Ashok GardensShree Saibaba Construction Co | Due Apr 2031, extended 4 mo | — | — |
| Dosti Primus-Phase 1Dosti Enterprises | Due Apr 2030, extended 4 mo | — | — |
Nearby: other villages in Thane
Thane (M Corp.) · 898 projectsNavi Mumbai (M Corp.) · 271 projectsMirabhayandar (M Corp.) · 225 projectsBhayandar · 118 projectsMira Bhayandar (M Corp.) · 106 projectsNaupada · 72 projectsPanchpakhadi · 65 projectsNerul · 58 projectsGhansoli · 57 projectsMajiwade · 43 projectsMumbra · 28 projectsOwale · 28 projects
Most active promoters
- Dosti Enterprises7 projects
- Siddhi Krish Developers4 projects
- Kalpataru Homes Private Limited2 projects
- Agile Real Estate Dev Private Limited1 project
- Lodha Developers Limited1 project
- Macrotech Developers Limited1 project
- Mangesh Dashrath Gaikar1 project
- Padmagriha Heights1 project
- PEPL Developers Pvt Ltd1 project
- Piramal Estate Private Limited1 project
Balkum, in questions
How many projects in Balkum run late?
10 in 10 MahaRERA registrations (27 of 28): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Balkum by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology