RERA projects in Balkum
4 projects under 4 MahaRERA registrations, registered 2022–2026. None has an extended completion date on record.
4RERA projects
4Registrations
4Completion still due0 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2022 | 1 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 0 |
| 2026 | 2 |
Projects in Balkum
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vaikunth Cluster 3 Tower 3PEPL Developers Pvt Ltd | PR1332022601156 | 13 Jul 2026 | 30 Jun 2032 | — | Not yet due | 0 |
| Estella - Tower C and DAgile Real Estate Dev Private Limited | PR1331012600027 | 6 Apr 2026 | 30 Jun 2032 | — | Not yet due | 0 |
| Sumeet EliteVedant Construction | P51700048753 | 17 Jan 2023 | 31 May 2027 | — | Not yet due | 0 |
| Shraddha PeninsulaPadmagriha Heights | P51700045788 | 9 Jun 2022 | 31 Dec 2026 | — | Not yet due | 0 |
Other localities in Thane
- Thane (M Corp.)1,174 projects
- Navi Mumbai (M Corp.)414 projects
- Mirabhayandar (M Corp.)264 projects
- Mira Bhayandar (M Corp.)113 projects
- Bhayandar79 projects
- Panchpakhadi25 projects
- Nerul18 projects
- Vartaknagar14 projects
- Navghar10 projects
- Kalwa9 projects
- Kolshet9 projects
- Majiwade9 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Agile Real Estate Dev Private Limited1 project
- Padmagriha Heights1 project
- PEPL Developers Pvt Ltd1 project
- Vedant Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology