Skip to content
Mixed · 2 buildings · 125 unitsRERA PM1331012500812

Dosti Primus-Phase 1

Deedo IDDP-THN-S990

Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 8% of its units are booked.

Balkum, Thane 400608 · by Dosti Enterprises · 67% of its projects kept the RERA date

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales8% booked10 of 125 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 16 Sep 2025, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1331012500812
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM133101250081216 Sep 202531 Dec 202930 Apr 2030Dosti EnterprisesProject page
Documents109

1 document held by Deedo, 108 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardDosti Enterprise PAN Card.pdf · uploaded 27 Jun 2025Source

Legal

  • Declaration Form B23 B.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 10 POWER OF ATTORNEY.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 10 CONVEYANCE_compressed.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 16C POWER.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 16C CONVEYANCE_compressed (1).pdf · uploaded 25 Jun 2025Source
  • Declaration Form B77 13A POWER.pdf · uploaded 25 Jun 2025Source
Show all 109 documentsShow fewer documents

Legal

  • Declaration Form B77 13A CONVEYANCE_compressed.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 2 CONVEYANCE_compressed.pdf · uploaded 25 Jun 2025Source
  • Declaration Form BRajul Vora Declaration_compressed.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B77 power_compressed.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B77 Conveyance final_compressed_compressed.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 13 DA.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 13 power.pdf · uploaded 25 Jun 2025Source
  • Declaration Form B27 16 B CONVEYANCE.pdf · uploaded 25 Jun 2025Source
  • OthersNSN 23-B 2025 01 04.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 27-2 2025 01 15.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 27-10-B 2025 01 15.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 27-11-B 2025 01 04.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 27-13 2025 01 15.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 27-16-B 2025 01 04.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 27-16-C 2025 06 30.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 77-11 2025 01 15.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 77-13-A 2025 01 15.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 77-13-B 2025 01 04.pdf · uploaded 11 Jul 2025Source
  • OthersNSN 77-14-B 2025 01 15.pdf · uploaded 11 Jul 2025Source
  • OthersDisclosure Of Interest In Other Reai Estate Organization.pdf · uploaded 18 Jul 2025Source
  • OthersDisclosure Of Interest In Other Real Estate Organization (2).pdf · uploaded 18 Jul 2025Source
  • OthersDisclosure Of Interest In Other Real Estate Organization (3).pdf · uploaded 18 Jul 2025Source
  • OthersDisclosure Of Interest In Other Real Estate Organization.pdf · uploaded 18 Jul 2025Source
  • OthersDisclosure Of Interest In Other Resai Estate Organization.pdf · uploaded 18 Jul 2025Source
  • OthersDisclosure Of Interst In Other Real Estate Organizatiation.pdf · uploaded 18 Jul 2025Source
  • OthersNSN 27-3 2025 07 18.pdf · uploaded 21 Jul 2025Source
  • OthersNSN 26-11A 2025 07 18.pdf · uploaded 21 Jul 2025Source
  • OthersNSN 77-13D 2025 07 18.pdf · uploaded 21 Jul 2025Source
  • OthersNSN 77-12 2025 07 18.pdf · uploaded 21 Jul 2025Source
  • OthersCONVEYANCE 77 12_compressed.pdf · uploaded 21 Jul 2025Source
  • OthersDA 27 3.pdf · uploaded 21 Jul 2025Source
  • OthersPOA 27 3.pdf · uploaded 21 Jul 2025Source
  • Declaration Form BTC revised_compressed.pdf · uploaded 21 Jul 2025Source
  • Declaration Form BCONVEYANCE 26 11D.pdf · uploaded 21 Jul 2025Source
  • OthersClause 35 of POA.pdf · uploaded 24 Jul 2025Source
  • OthersPOA 77.pdf · uploaded 24 Jul 2025Source
  • OthersDA 77.pdf · uploaded 24 Jul 2025Source
  • OthersClasue 20 from POA.pdf · uploaded 24 Jul 2025Source
  • OthersPage no 9 from DA.pdf · uploaded 24 Jul 2025Source
  • Declaration Form BDA 77.pdf · uploaded 24 Jul 2025Source
  • Declaration Form B77 power_compressed.pdf · uploaded 24 Jul 2025Source
  • Others27 13 deed of confirmation .pdf · uploaded 11 Aug 2025Source
  • Others27 12 deed of conveyance .pdf · uploaded 11 Aug 2025Source
  • Others27 3 afs .pdf · uploaded 11 Aug 2025Source
  • Others27 3 poa of afs .pdf · uploaded 11 Aug 2025Source
  • Others27 3 confirmation .pdf · uploaded 11 Aug 2025Source
  • Others27 3 poa of confirmation .pdf · uploaded 11 Aug 2025Source
  • Others27 13 deed of confirmation .pdf · uploaded 11 Aug 2025Source
  • Others27 16B deed of confirmation .pdf · uploaded 11 Aug 2025Source
  • Others27 16B POA 2007 .pdf · uploaded 11 Aug 2025Source
  • Others27 16 B confirmation 2011.pdf · uploaded 11 Aug 2025Source
  • Others27 16 B POA 2011.pdf · uploaded 11 Aug 2025Source
  • OthersPOA 77.pdf · uploaded 11 Aug 2025Source
  • Declaration Form BFORM B.pdf · uploaded 9 Sep 2025Source
  • Othersblank document.pdf · uploaded 10 Sep 2025Source
  • Others27 13 AFS_compressed.pdf · uploaded 10 Sep 2025Source
  • Others27 13 POA_compressed.pdf · uploaded 10 Sep 2025Source
  • Others27 13 Deed of Confirmation.pdf · uploaded 10 Sep 2025Source
  • Others27 13 POA Of Confirmation.pdf · uploaded 10 Sep 2025Source
  • Others27 13 Deed of Confirmation 2.pdf · uploaded 10 Sep 2025Source
  • Others27 13 POA of Confirmation 2.pdf · uploaded 10 Sep 2025Source
  • Declaration Form Bblank document.pdf · uploaded 10 Sep 2025Source
  • OthersDeclaration Final.pdf · uploaded 11 Sep 2025Source
  • Othersdosti Enterprises (01) (1).pdf · uploaded 12 Sep 2025Source
  • OthersDosti Enterprises(02) (1).pdf · uploaded 12 Sep 2025Source
  • OthersDosti Enterprises(03) (1).pdf · uploaded 12 Sep 2025Source
  • OthersDosti Enterprisrs(04) (1).pdf · uploaded 12 Sep 2025Source
  • OthersDosti Enterprises(05) (1).pdf · uploaded 12 Sep 2025Source
  • OthersDosti Enterprises(06) (1).pdf · uploaded 12 Sep 2025Source
  • OthersDeed of Confirmation june.pdf · uploaded 12 Sep 2025Source
  • OthersJune POA.pdf · uploaded 12 Sep 2025Source

Migrated

  • Withdrawal Update Form 1Dosti Enterprises DWC Primus Form 1 Mar26.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 2Dosti Enterprises DWC Primus Form 2 Mar26.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 3Dosti Enterprises DWC Primus Form 3 Mar26.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 1FORM 1 SEPT25.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2FORM 2 SEPT25.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3Form3 Dosti Primus PH1 18June2025 Final.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 1FORM 1 Dec25.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 1Dosti Enterprises DWC Primus Form 1 Mar26.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 2FORM 2 Dec25.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 2Dosti Enterprises DWC Primus Form 2 Mar26.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 3FORM 3 Dec25.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 3Dosti Enterprises DWC Primus Form 3 Mar26.pdf · uploaded 8 May 2026Source
  • Form 2A (FY 2025-2026)Form 2A - DWC Dosti Primus.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 1Dosti Enterprises DWC Primus Form 1 Jun26.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 2Dosti Enterprises DWC Primus Form 2 Jun26.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 3Dosti Enterprises DWC Primus Form 3 Jun26.pdf · uploaded 4 Aug 2026Source
  • Form 5 (FY 2025-2026)DE DWC Primus 2025-26.pdf · uploaded 5 Oct 2026Source

Technical

  • DocumentSanction Plan Plot A7.pdf · uploaded 27 Jun 2025Source
  • DocumentApproved Plans.pdf · uploaded 27 Jun 2025Source
  • DocumentSanad dt 2022.pdf · uploaded 27 Jun 2025Source
  • DocumentSanad Order 2019_compressed (1).pdf · uploaded 27 Jun 2025Source
  • OthersForm2 Dosti Primus PH1 18June2025.pdf · uploaded 27 Jun 2025Source
  • OthersForm1 Dosti Primus PH1 18June2025 (1).pdf · uploaded 27 Jun 2025Source
  • OthersForm2A Dosti Primus PH1 18June2025.pdf · uploaded 27 Jun 2025Source
  • OthersCC Confirmation mail.pdf · uploaded 14 Jul 2025Source
  • DocumentOrder no 50.pdf · uploaded 18 Jul 2025Source
  • OthersRERA PLINES & LEGAL PLANS R1.pdf · uploaded 12 Aug 2025Source
  • OthersDeclaration.pdf · uploaded 12 Sep 2025Source

Technical (Architect)

  • DocumentDosti Enterprises DWC Primus Form 1 Jun26.pdf · uploaded 4 Aug 2026Source

Technical (Engineer)

  • DocumentDosti Enterprises DWC Primus Form 2 Jun26.pdf · uploaded 4 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 23B, 26/11A (pt)

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—125 units in all
Address
Balkum, BalkumPIN 400608
Village
Thane (M Corp.), Thane taluka
Land area for this project
4,550 sq m (48,976 sq ft)
Approved layout area
24,240 sq m (2,60,917 sq ft)
Permissible built-up area
17,963 sq m (1,93,352 sq ft)
Sanctioned built-up area
17,963 sq m (1,93,352 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
Yes

Survey, CTS, gat or plot numbers

23B26/11A (pt)27/10B (pt)27/11B27/12(pt)27/13(pt)27/16B (pt)27/16C (pt)27/2(pt)27/3(pt)77/11(pt)77/12 (pt)77/13A (pt)77/13B77/13D77/14B

Land as published on MahaRERA's project page

77/13A (pt), 77/12 (pt), 77/13D, 77/11(pt), 77/13B, 23B, 77/14B, 27/2(pt), 27/11B, 27/10B (pt), 27/3(pt), 27/12(pt), 27/13(pt), 27/16C (pt), 27/16B (pt), 26/11A (pt)

Boundaries

North
30 Mts Hcmtr
South
30 Mts Wide Road
East
Cts No 27/16
West
30 Mt Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking125 units

125 units registered

— · 125 units
BuildingTypeCarpet areaUnits
Bldg No 2——7
Bldg No 3——118

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJay Rajul Vora—
ArchitectNeerja Purandare—
EngineerSwapnil Londhe—
EngineerVaibhav Raghunath Kalambate—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology