Company or firm · first RERA registration 2017

Dosti Enterprises

Deedo IDDD-5WEG

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects1415 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

12 of 15 registrations with dates moved or missed their RERA date · months late against the original promise

15 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dosti West County - Dosti OakP51700006565BalkumCertificate Signed30 Jun 202230 Jun 2022On date
Dosti Westcounty- Phase 2- Dosti CedarP51700015258BalkumCertificate Signed30 Dec 202330 Dec 2023On date
Dosti Westcounty-Phase 3-Dosti WestwoodP51700015501BalkumCertificate Signed30 Dec 202630 Apr 2027+4 mo
Dosti West County - Phase 4- Dosti PineP51700025834BalkumCertificate Signed30 Dec 202730 Apr 2028+4 mo
Dosti West County - Dosti TulipP51700032666Thane (M Corp.)Certificate Signed31 Oct 202628 Feb 2027+4 mo
Dosti West County - Dosti Nest - Phase 1P51700033640Thane (M Corp.)Certificate Signed30 Jun 202730 Oct 2027+4 mo
Dosti West County - Dosti Nest - Phase 2P51700033663Thane (M Corp.)Certificate Signed30 Jun 202730 Oct 2027+4 mo
Dosti West County Dosti NestP51700049724BalkumCertificate Signed31 Aug 202731 Dec 2027+4 mo
Dosti West County Dosti NestP51700050253BalkumCertificate Signed31 Dec 202730 Apr 2028+4 mo
Dosti West County - Phase 5 - Dosti Olive - Wing BP51700054037ThaneCertificate Signed30 Sep 202830 Jan 2029+4 mo
Dosti Westcounty - Phase 6 - Dosti MapleP51700054424Thane (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
Dosti West County - Phase 7 - Dosti WillowP51700056278Thane (M Corp.)Active31 Mar 2028—On date
Dosti West County - Phase 5 - Dosti Olive - Wing AP51700077484ThaneCertificate Signed30 Sep 202830 Jan 2029+4 mo
Dosti Primus-Phase 1PM1331012500812BalkumCertificate Signed31 Dec 202930 Apr 2030+4 mo
One DostiPC1330002600012BalkumCertificate Signed18 Mar 203118 Jul 2031+4 mo
Show all 15 registrationsShow fewer

Dosti Enterprises, in questions

Does Dosti Enterprises finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Dosti Enterprises registered with MahaRERA?

14 projects under 15 MahaRERA registrations; 2 completed on MahaRERA.

Does Dosti Enterprises have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology