Dosti Enterprises
Company or firm · 14 projects · 15 MahaRERA registrations
Projects1415 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Dosti West County - Dosti OakP51700006565 | Thane (M Corp.) | 2017 | Not reported | 30 Jun 2022 | — | On date |
| Dosti Westcounty- Phase 2- Dosti CedarP51700015258 | Thane (M Corp.) | 2018 | Not reported | 30 Dec 2023 | — | On date |
| Dosti Westcounty-Phase 3-Dosti WestwoodP51700015501 | Thane (M Corp.) | 2018 | Not reported | 30 Dec 2026 | — | On date |
| Dosti West County - Phase 4- Dosti PineP51700025834 | Thane (M Corp.) | 2020 | Not reported | 30 Dec 2027 | — | On date |
| Dosti West County - Dosti TulipP51700032666 | Thane (M Corp.) | 2022 | Not reported | 31 Oct 2026 | — | On date |
| Dosti West County - Dosti Nest - Phase 1P51700033640 | Thane (M Corp.) | 2022 | Not reported | 30 Jun 2027 | — | On date |
| Dosti West County - Dosti Nest - Phase 2P51700033663 | Thane (M Corp.) | 2022 | Not reported | 30 Jun 2027 | — | On date |
| Dosti West County Dosti NestP51700049724 | Thane (M Corp.) | 2023 | Not reported | 31 Aug 2027 | — | On date |
| Dosti West County Dosti NestP51700050253 | Thane (M Corp.) | 2023 | Not reported | 31 Dec 2027 | — | On date |
| Dosti West County - Phase 5 - Dosti Olive - Wing BP51700054037 | Thane | 2023 | Not reported | 30 Sep 2028 | — | On date |
| Dosti Westcounty - Phase 6 - Dosti MapleP51700054424 | Thane (M Corp.) | 2024 | Not reported | 31 Dec 2028 | — | On date |
| Dosti West County - Phase 7 - Dosti WillowP51700056278 | Thane (M Corp.) | 2024 | Not reported | 31 Mar 2028 | — | On date |
| Dosti West County - Phase 5 - Dosti Olive - Wing AP51700077484 | Thane | 2024 | Not reported | 30 Sep 2028 | — | On date |
| Dosti Primus-Phase 1PM1331012500812 | Thane (M Corp.) | 2025 | Not reported | 31 Dec 2029 | — | On date |
| One DostiPC1330002600012 | Thane (M Corp.) | 2026 | Not reported | 18 Mar 2031 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology