Wing A, Shashwat Aangan

Deedo IDDP-THN-QSSP-A

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Shashwat Aangan
Median saleNot on recordneeds 3 or more sales
Booked56%61 of 109 · MahaRERA
Completion30 Jan 202631 Jul 2023 · revised
Units & parking in Wing A
TypeCarpet areaUnitsBooked
1BHK23.8 m² (257 sq.ft)73
1BHK26.7 m² (287 sq.ft)1411
1BHK26.8 m² (288 sq.ft)64
1BHK26.8 m² (289 sq.ft)148
1BHK26.8 m² (289 sq.ft)217
1BHK27.5 m² (296 sq.ft)73
1BHK29.1 m² (313 sq.ft)65
1BHK30 m² (322 sq.ft)62
1BHK30.2 m² (325 sq.ft)11
1BHK31.8 m² (342 sq.ft)139
1BHK31.9 m² (343 sq.ft)73
1BHK32.6 m² (351 sq.ft)11
1RK19 m² (204 sq.ft)20
1RK27.6 m² (297 sq.ft)22
Shop99.6 m² (1,072 sq.ft)11
Shop201.1 m² (2,164 sq.ft)11
As registered with MahaRERA
RERA registration
P51700023009 · registered 14 Nov 2019
Promised completion
31 Jul 2023
Revised completion
30 Jan 2026
Sanctioned habitable floors
8
Sanctioned floors (incl. basement, stilt, podium)
9
Units declared
0
Homes
0
Shops and offices
0
Sanctioned FSI area (sq m)
8
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-QSSP-A
Questions about Wing A

When is Wing A due for completion?

The MahaRERA registration promises 31 Jul 2023, revised to 30 Jan 2026.

How many floors does Wing A have?

8 sanctioned habitable floors, as registered with MahaRERA.