Shashwat Aangan
Completion was pushed back 2 years and 6 months to Jan 2026, and that date has passed too; no MahaRERA orders on record; 26% of its units are booked.
Badlapur (M Cl), Thane 421503 · Promoter: Samarth Construction
Completion was pushed back 2 years and 6 months to Jan 2026, and that date has passed too
- P51700023009Registered 14 Nov 2019, completion promised 31 Jul 2023, revised to 30 Jan 2026, and still not shown completed today.
- P51700024178Registered 24 Jan 2020, completion promised 30 Dec 2027.
1 extension certificate on record.
2 registrations · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Wing A8 floors · 109 units56% booked
- Wing B12 floors · 115 units0% booked
- Wing C5 floors · 28 units14% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrations2
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700023009 | 14 Nov 2019 | 31 Jul 2023 | 30 Jan 2026 | Samarth Construction | Project page |
| P51700024178 | 24 Jan 2020 | 30 Dec 2027 | 30 Dec 2027 | Samarth Construction | Project page |
Documents202
3 documents held by Deedo, 199 filings listed on MahaRERA's project page
Registration certificate (2)
Finance
- PAN CardP51700023009 · PAN SAMARTH.pdf · uploaded 2 Nov 2019Source
- PAN CardP51700024178 · PAN SAMARTH.pdf · uploaded 2 Nov 2019Source
- Other – FinanceP51700023009 · IIFL MORTGAGE AANGAN A C WING.pdf · uploaded 3 Nov 2022Source
- Other – FinanceP51700024178 · IIFL MORTGAGE AANGAN B WING.pdf · uploaded 3 Nov 2022Source
- Other – FinanceP51700024178 · SHASHWAT AANGAN B WING.pdf · uploaded 21 Nov 2022Source
Show all 202 documentsShow fewer documents
Legal
- Legal Title reportP51700023009 · title report 1 scan.pdf · uploaded 2 Nov 2019Source
- Legal Title reportP51700023009 · title report 2 scan.pdf · uploaded 2 Nov 2019Source
- Declaration Form BP51700023009 · Declaration wing A C Builders.pdf · uploaded 2 Nov 2019Source
- Legal Title reportP51700024178 · title report 1 scan.pdf · uploaded 2 Nov 2019Source
- Legal Title reportP51700024178 · title report 2 scan.pdf · uploaded 2 Nov 2019Source
- Declaration Form BP51700024178 · Declaration wing B Builders.pdf · uploaded 2 Nov 2019Source
- OtherP51700023009 · C Wing cancellection.pdf · uploaded 3 Nov 2021Source
- Legal Title reportP51700023009 · Title lATEST.pdf · uploaded 13 Aug 2023Source
- Declaration Form BP51700023009 · AFFIDAVITE FINAL.pdf · uploaded 11 Dec 2023Source
- Declaration Form BP51700023009 · B Form FINAL.pdf · uploaded 9 Jan 2024Source
- Declaration Form BP51700023009 · FORM B LATEST.pdf · uploaded 1 May 2025Source
Migrated
- 1 PAN CardP51700023009 · PAN SAMARTH.pdf · uploaded 2 Nov 2019Source
- 1 Copy of the legal title reportP51700023009 · title report 1 scan.pdf · uploaded 2 Nov 2019Source
- 2 Copy of the legal title reportP51700023009 · title report 2 scan.pdf · uploaded 2 Nov 2019Source
- 1 Details of encumbrancesP51700023009 · title report 1 scan.pdf · uploaded 2 Nov 2019Source
- 2 Details of encumbrancesP51700023009 · title report 2 scan.pdf · uploaded 2 Nov 2019Source
- 1 Copy of Layout Approval (in case of layout)P51700023009 · Sheet 1 layout B wing.PDF · uploaded 2 Nov 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentP51700023009 · sheet 2 unit.PDF · uploaded 2 Nov 2019Source
- 2 Building Plan Approval / NA Order for plotted developmentP51700023009 · Sheet 3 Elevaction.PDF · uploaded 2 Nov 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700023009 · Building Peremission.pdf · uploaded 2 Nov 2019Source
- 1 Declaration in FORM BP51700023009 · Declaration wing A C Builders.pdf · uploaded 2 Nov 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · CA CERTIFICATE WING A And C.pdf · uploaded 2 Nov 2019Source
- 1 Proforma of Allotment letterP51700023009 · Allotment letter A And C Walivali PDF.pdf · uploaded 2 Nov 2019Source
- 2 Proforma of Allotment letterP51700023009 · Agreement Draft A and C pdf.pdf · uploaded 2 Nov 2019Source
- 1 PAN CardP51700024178 · PAN SAMARTH.pdf · uploaded 2 Nov 2019Source
- 1 Copy of the legal title reportP51700024178 · title report 1 scan.pdf · uploaded 2 Nov 2019Source
- 2 Copy of the legal title reportP51700024178 · title report 2 scan.pdf · uploaded 2 Nov 2019Source
- 1 Details of encumbrancesP51700024178 · title report 1 scan.pdf · uploaded 2 Nov 2019Source
- 2 Details of encumbrancesP51700024178 · title report 2 scan.pdf · uploaded 2 Nov 2019Source
- 1 Copy of Layout Approval (in case of layout)P51700024178 · Sheet 1 layout B wing.PDF · uploaded 2 Nov 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentP51700024178 · sheet 2 unit.PDF · uploaded 2 Nov 2019Source
- 2 Building Plan Approval / NA Order for plotted developmentP51700024178 · Sheet 3 Elevaction.PDF · uploaded 2 Nov 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700024178 · Building Peremission.pdf · uploaded 2 Nov 2019Source
- 1 Declaration in FORM BP51700024178 · Declaration wing B Builders.pdf · uploaded 2 Nov 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024178 · CA CERTIFICATE WING B.pdf · uploaded 2 Nov 2019Source
- 1 Proforma of Allotment letterP51700024178 · Agreement Draft B PDF.pdf · uploaded 2 Nov 2019Source
- 2 Proforma of Allotment letterP51700024178 · Allotment letter Walivali pdf.pdf · uploaded 2 Nov 2019Source
- 3 Details of encumbrancesP51700024178 · shashwat aangan wing b.pdf · uploaded 19 Nov 2019Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · ARCH CER AANGAN A C.pdf · uploaded 18 Nov 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024178 · ARCH CER AANGAN B.pdf · uploaded 18 Nov 2020Source
- 1 Architect’s Certificate on Completion of Project (Form 4)P51700023009 · Wing C Withdrawal.pdf · uploaded 24 Dec 2020Source
- 1 OtherP51700023009 · C Wing cancellection.pdf · uploaded 3 Nov 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024178 · FORM 1 - ARCHITECT CERTIFICATE WING - B.pdf · uploaded 19 May 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024178 · FORM 2 - ENGINEERS CERTIFICATE WING - B.pdf · uploaded 19 May 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024178 · FORM 3 - CA CERTIFICATE WING - B.pdf · uploaded 19 May 2022Source
- 3 Proforma of Allotment letterP51700024178 · B wing flat sale agreement Draft.pdf · uploaded 19 May 2022Source
- 1 b Details of encumbrances concerned to LegalP51700024178 · DECLARATION OF ENCUMBRANCES.pdf · uploaded 2 Jul 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentP51700024178 · Sheet No 1.pdf · uploaded 2 Jul 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentP51700024178 · Sheet No 2.pdf · uploaded 2 Jul 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentP51700024178 · Sheet No 3.pdf · uploaded 2 Jul 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700024178 · BUILDING PERMISSION NEW 25 02 2021 B 12 C 6.pdf · uploaded 2 Jul 2022Source
- 1 Declaration about Commencement CertificateP51700024178 · Commencement Certificate for Shashwat Aangan B Wing .pdf · uploaded 2 Jul 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024178 · FORM 1 - ARCHITECT CERTIFICATE WING - B.pdf · uploaded 2 Jul 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024178 · FORM 1 - ARCHITECT CERTIFICATE WING - B.pdf · uploaded 2 Jul 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024178 · FORM 2 - ENGINEERS CERTIFICATE WING - B.pdf · uploaded 2 Jul 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024178 · FORM 3 - CA CERTIFICATE WING - B.pdf · uploaded 2 Jul 2022Source
- 4 Proforma of Allotment letterP51700024178 · B wing flat sale agreement Draft.pdf · uploaded 2 Jul 2022Source
- 1 Other – FinanceP51700023009 · IIFL MORTGAGE AANGAN A C WING.pdf · uploaded 3 Nov 2022Source
- 1 Other – FinanceP51700024178 · IIFL MORTGAGE AANGAN B WING.pdf · uploaded 3 Nov 2022Source
- 2 Other – FinanceP51700024178 · SHASHWAT AANGAN B WING.pdf · uploaded 21 Nov 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · Architechture certificate A Wing.pdf · uploaded 28 Dec 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · Form 2 Engineers Certificate Wing A.pdf · uploaded 28 Dec 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · Form 3 shashwat angan wing A.pdf · uploaded 28 Dec 2022Source
- 1 Proforma of Agreement for saleP51700023009 · Agreement For sale Wing A.pdf · uploaded 26 Jan 2023Source
- 1 Declaration about Commencement CertificateP51700023009 · Commencement Certificate for Shashwat Aangan A AND C.pdf · uploaded 2 Feb 2023Source
- 3 Copy of the legal title reportP51700023009 · Title lATEST.pdf · uploaded 13 Aug 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700023009 · BUILDING PERMISSION.pdf · uploaded 13 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P51700023009 · form 2 A C wing aangan.pdf · uploaded 13 Aug 2023Source
- 2 Declaration in FORM BP51700023009 · AFFIDAVITE FINAL.pdf · uploaded 11 Dec 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · C Wing Architecture DEC 22.pdf · uploaded 11 Dec 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · A Wing Architecture MARCH 23.pdf · uploaded 11 Dec 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · C Wing Architecture MARCH 23.pdf · uploaded 11 Dec 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · A Wing Architecture JUNE 23.pdf · uploaded 11 Dec 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · C Wing Architecture JUNE 23.pdf · uploaded 11 Dec 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · A Wing Architecture SEPT 23.pdf · uploaded 11 Dec 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · C Wing Architecture SEPT 23.pdf · uploaded 11 Dec 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · C wing Engineer DEC 22.pdf · uploaded 11 Dec 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · A wing Engineer MARCH 23.pdf · uploaded 11 Dec 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · C wing Engineer MARCH 23.pdf · uploaded 11 Dec 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · A wing Engineer JUNE 23.pdf · uploaded 11 Dec 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · C wing Engineer JUNE 23.pdf · uploaded 11 Dec 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · A wing Engineer SEPT 23.pdf · uploaded 11 Dec 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · C wing Engineer SEPT 23.pdf · uploaded 11 Dec 2023Source
- 1 Disclosure of sold/ booked inventoryP51700023009 · sold unsold c wing shahswar aangan.pdf · uploaded 11 Dec 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · CA Form 3 March 23.pdf · uploaded 11 Dec 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · CA Form 3 June 23.pdf · uploaded 11 Dec 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · CA Form 3 Sept 23.pdf · uploaded 11 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P51700023009 · March 20 Form 5.pdf · uploaded 11 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P51700023009 · March 21 Form 5.pdf · uploaded 11 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700023009 · MArch 23 Form 5.pdf · uploaded 11 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700023009 · March 22 Form 5.pdf · uploaded 11 Dec 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700023009 · Complection Certificate A Wing.pdf · uploaded 11 Dec 2023Source
- 2 Disclosure of sold/ booked inventoryP51700023009 · sold unsold A Wing and Completion certificate F.pdf · uploaded 28 Dec 2023Source
- 3 Disclosure of sold/ booked inventoryP51700023009 · sold unsold final.pdf · uploaded 4 Jan 2024Source
- 3 Declaration in FORM BP51700023009 · B Form FINAL.pdf · uploaded 9 Jan 2024Source
- 4 Disclosure of sold/ booked inventoryP51700023009 · A WING SOLD LIST.pdf · uploaded 9 Jan 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · FORM1Q3 FINAL.pdf · uploaded 28 Mar 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · FORM2Q3 FINAL.pdf · uploaded 28 Mar 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · FORM3Q3 FINAL.pdf · uploaded 28 Mar 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · FORM 1 MARCH 24.pdf · uploaded 12 Aug 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · FORM 1 JUNE 24.pdf · uploaded 12 Aug 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · FORM 2 MARCH 24.pdf · uploaded 12 Aug 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · FORM 2 JUNE 24.pdf · uploaded 12 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700023009 · FORM 2A MARCH 24.pdf · uploaded 12 Aug 2024Source
- 5 Disclosure of sold/ booked inventoryP51700023009 · SOLD UNSOLD A WING.pdf · uploaded 12 Aug 2024Source
- 1 CERSAI detailsP51700023009 · CERSAI LATEST.pdf · uploaded 12 Aug 2024Source
- 6 Disclosure of sold/ booked inventoryP51700023009 · SOLD UNSOLD C WING.pdf · uploaded 12 Aug 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · FORM 3 MARCH 24.pdf · uploaded 12 Aug 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · FORM 3 JUNE 24.pdf · uploaded 12 Aug 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · FORM 3 JUNE FINAL NEW.pdf · uploaded 13 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · form 1 sep.pdf · uploaded 5 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · form 3 sep.pdf · uploaded 5 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · from 2 sep.pdf · uploaded 5 Mar 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · form 2 dec.pdf · uploaded 5 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · DEC-24 FORM 1.pdf · uploaded 7 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · FORM 3 31122024.pdf · uploaded 27 Mar 2025Source
- 1 Declaration in FORM BP51700023009 · FORM B LATEST.pdf · uploaded 1 May 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700023009 · FORM 1 31032025.pdf · uploaded 1 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700023009 · FORM 3 31032025 FINAL.pdf · uploaded 1 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700023009 · FORM 2 31032025.pdf · uploaded 1 May 2025Source
- 1 Disclosure of sold/ booked inventoryP51700023009 · SOLD UNSOLD A WING.pdf · uploaded 1 May 2025Source
- 2 Disclosure of sold/ booked inventoryP51700023009 · SOLD UNSOLD C WING.pdf · uploaded 1 May 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700023009 · FORM 5 MARCH 24 FINAL.pdf · uploaded 18 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · form 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · form 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · form 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · form 3 ..pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1.pdf · uploaded 24 May 2025Source
- Form 2P51700024178 · FORM 2.pdf · uploaded 24 May 2025Source
- Form 3P51700024178 · FORM 3 dec 24.pdf · uploaded 24 May 2025Source
- Form 1P51700024178 · FORM 1 MARCH 25.pdf · uploaded 25 Feb 2026Source
- Form 2P51700024178 · FORM 2 MARCH 25.pdf · uploaded 25 Feb 2026Source
- Form 3P51700024178 · FORM 3 MARCH 25.pdf · uploaded 25 Feb 2026Source
- Disclosure of Sold and Booked InventoryP51700024178 · DISCLOSURE SOLD UNSOLD MARCH 25.pdf · uploaded 25 Feb 2026Source
- Withdrawal Update Form 1P51700024178 · FORM 1 JUN 25.pdf · uploaded 12 Mar 2026Source
- Withdrawal Update Form 2P51700024178 · FORM 2 JUN 25.pdf · uploaded 12 Mar 2026Source
- Withdrawal Update Form 3P51700024178 · FORM 3 JUN 25.pdf · uploaded 12 Mar 2026Source
- Withdrawal Update Form 1P51700024178 · FORM 1 SEPT 25.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 1P51700024178 · FORM 1 DEC 25.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 1P51700024178 · FORM 1 MARCH 26.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 2P51700024178 · FORM 2 SEPT 25.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 2P51700024178 · FORM 2 DEC 25.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 2P51700024178 · FORM 2 MARCH 26.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 3P51700024178 · FORM 3 SEPT 25.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 3P51700024178 · FORM 3 DEC 25.pdf · uploaded 19 May 2026Source
- Withdrawal Update Form 3P51700024178 · FORM 3 MARCH 26.pdf · uploaded 19 May 2026Source
Technical
- DocumentP51700023009 · Sheet 1 layout B wing.PDF · uploaded 2 Nov 2019Source
- DocumentP51700023009 · sheet 2 unit.PDF · uploaded 2 Nov 2019Source
- DocumentP51700023009 · Sheet 3 Elevaction.PDF · uploaded 2 Nov 2019Source
- DocumentP51700024178 · Sheet 1 layout B wing.PDF · uploaded 2 Nov 2019Source
- DocumentP51700024178 · sheet 2 unit.PDF · uploaded 2 Nov 2019Source
- DocumentP51700024178 · Sheet 3 Elevaction.PDF · uploaded 2 Nov 2019Source
- DocumentP51700024178 · Sheet No 1.pdf · uploaded 2 Jul 2022Source
- DocumentP51700024178 · Sheet No 2.pdf · uploaded 2 Jul 2022Source
- DocumentP51700024178 · Sheet No 3.pdf · uploaded 2 Jul 2022Source
Technical (Architect)
- DocumentP51700023009 · FORM 1 JUNE 24.pdf · uploaded 12 Aug 2024Source
- DocumentP51700023009 · form 1 sep.pdf · uploaded 5 Mar 2025Source
- DocumentP51700023009 · DEC-24 FORM 1.pdf · uploaded 7 Mar 2025Source
- DocumentP51700023009 · FORM 1 31032025.pdf · uploaded 1 May 2025Source
- DocumentP51700024178 · FORM 1 MARCH 26.pdf · uploaded 19 May 2026Source
Technical (Engineer)
- DocumentP51700023009 · FORM 2 JUNE 24.pdf · uploaded 12 Aug 2024Source
- DocumentP51700023009 · from 2 sep.pdf · uploaded 5 Mar 2025Source
- DocumentP51700023009 · form 2 dec.pdf · uploaded 5 Mar 2025Source
- DocumentP51700023009 · FORM 2 31032025.pdf · uploaded 1 May 2025Source
- DocumentP51700024178 · FORM 2 MARCH 26.pdf · uploaded 19 May 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals6/5/2, 6/5/3
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Phases
- 2
- Unit types
- 1BHK, 1RK, Shop, 2BHK252 units in all
- Address
- Gut No 6/5/1, 6/5/2, 6/5/3, 6/6, 7, Walivali, WalivaliPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 19.17616, 73.24014
- Designated bank account
- 82
- Developed in phases
- Yes
- Also registered as
- SHASHWAT AANGAN Building / Wing A and C, Shashwat Aangan Building / Wing B
Survey, CTS, gat or plot numbers
Boundaries
- North
- Gut No 31
- South
- Gut No 8
- East
- Gut No 29
- West
- 12 Metre Wide DP Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking252 units
65 of 252 units booked (26%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P51700023009 | Wing A | 1BHK | 23.83 sq m · 257 sq ft | 7 | 3 |
| P51700023009 | Wing A | 1BHK | 26.68 sq m · 287 sq ft | 14 | 11 |
| P51700023009 | Wing A | 1BHK | 26.75 sq m · 288 sq ft | 6 | 4 |
| P51700023009 | Wing A | 1BHK | 26.82 sq m · 289 sq ft | 14 | 8 |
| P51700023009 | Wing A | 1BHK | 26.84 sq m · 289 sq ft | 21 | 7 |
| P51700023009 | Wing A | 1BHK | 27.47 sq m · 296 sq ft | 7 | 3 |
| P51700023009 | Wing A | 1BHK | 29.09 sq m · 313 sq ft | 6 | 5 |
| P51700023009 | Wing A | 1BHK | 29.95 sq m · 322 sq ft | 6 | 2 |
Show all 35 unit rowsShow fewer unit rows
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P51700023009 | Wing A | 1BHK | 30.21 sq m · 325 sq ft | 1 | 1 |
| P51700023009 | Wing A | 1BHK | 31.78 sq m · 342 sq ft | 13 | 9 |
| P51700023009 | Wing A | 1BHK | 31.91 sq m · 343 sq ft | 7 | 3 |
| P51700023009 | Wing A | 1BHK | 32.6 sq m · 351 sq ft | 1 | 1 |
| P51700023009 | Wing A | 1RK | 18.96 sq m · 204 sq ft | 2 | 0 |
| P51700023009 | Wing A | 1RK | 27.62 sq m · 297 sq ft | 2 | 2 |
| P51700023009 | Wing A | Shop | 99.58 sq m · 1,072 sq ft | 1 | 1 |
| P51700023009 | Wing A | Shop | 201.08 sq m · 2,164 sq ft | 1 | 1 |
| P51700024178 | Wing B | 1BHK | 30.38 sq m · 327 sq ft | 12 | 0 |
| P51700024178 | Wing B | 1BHK | 30.54 sq m · 329 sq ft | 24 | 0 |
| P51700024178 | Wing B | 1BHK | 31.39 sq m · 338 sq ft | 12 | 0 |
| P51700024178 | Wing B | 1BHK | 31.48 sq m · 339 sq ft | 1 | 0 |
| P51700024178 | Wing B | 1BHK | 31.91 sq m · 343 sq ft | 12 | 0 |
| P51700024178 | Wing B | 1BHK | 33.55 sq m · 361 sq ft | 12 | 0 |
| P51700024178 | Wing B | 2BHK | 32.08 sq m · 345 sq ft | 1 | 0 |
| P51700024178 | Wing B | 2BHK | 36.26 sq m · 390 sq ft | 12 | 0 |
| P51700024178 | Wing B | 2BHK | 37.66 sq m · 405 sq ft | 12 | 0 |
| P51700024178 | Wing B | 2BHK | 39.67 sq m · 427 sq ft | 11 | 0 |
| P51700024178 | Wing B | Shop | 13.65 sq m · 147 sq ft | 2 | 0 |
| P51700024178 | Wing B | Shop | 16.8 sq m · 181 sq ft | 1 | 0 |
| P51700024178 | Wing B | Shop | 17.55 sq m · 189 sq ft | 1 | 0 |
| P51700024178 | Wing B | Shop | 18.2 sq m · 196 sq ft | 1 | 0 |
| P51700024178 | Wing B | Shop | 20.4 sq m · 220 sq ft | 1 | 0 |
| P51700023009 | Wing C | 1BHK | 29.1 sq m · 313 sq ft | 24 | 1 |
| P51700023009 | Wing C | 1BHK | 33.4 sq m · 360 sq ft | 1 | 1 |
| P51700023009 | Wing C | 1RK | 23.8 sq m · 256 sq ft | 2 | 2 |
| P51700023009 | Wing C | 1RK | 28.5 sq m · 307 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals14
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Architect | Shivam Tiwari | — | P51700024178 |
| Architect | Space Designers | — | P51700023009 |
| Architect | Swastik Creation | — | P51700023009 |
| Chartered accountant | Amrrita Jagnaani | — | P51700024178 |
| Chartered accountant | Amrrita Jagnanni | — | P51700023009 |
| Chartered accountant | Divyesh J Shah & Associates | — | P51700024178 |
| Chartered accountant | Jayesh Suryakant Vora | — | P51700024178 |
| Chartered accountant | Sagar p Shah & Associates | — | P51700023009 |
Show all 14 professionalsShow fewer professionals
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Engineer | Brijesh Parasiya | — | P51700024178 |
| Engineer | Kb Consultants | — | P51700023009 |
| Engineer | Pramod Kamble | — | P51700024178 |
| Engineer | Pramod Kamble | — | P51700023009 |
| Other | Het Construction | — | P51700023009 |
| Other | Het Constuction | — | P51700024178 |
Source: MahaRERA project page. Contact details are not shown.