Promised date passed11 floorsRERA P51700014893
Aawas Deep Phase 1, Aawas Deep
Deedo IDDP-THN-400E-1MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked72%76 of 106 · MahaRERA
Completion30 Dec 2022as registered
Units & parking in Aawas Deep Phase 1
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 21.6 m² (233 sq.ft) | 1 | 1 |
| 1BHK | 21.9 m² (236 sq.ft) | 8 | 6 |
| 1BHK | 23.6 m² (254 sq.ft) | 1 | 0 |
| 1BHK | 23.8 m² (256 sq.ft) | 3 | 3 |
| 1BHK | 24.9 m² (268 sq.ft) | 1 | 1 |
| 1BHK | 25.8 m² (278 sq.ft) | 1 | 0 |
| 1BHK | 25.9 m² (279 sq.ft) | 3 | 2 |
| 1BHK | 27 m² (291 sq.ft) | 8 | 6 |
| 1BHK | 27.3 m² (294 sq.ft) | 8 | 8 |
| 1BHK | 28.8 m² (310 sq.ft) | 5 | 3 |
| 1BHK | 29.1 m² (313 sq.ft) | 3 | 3 |
| 1BHK | 29.2 m² (314 sq.ft) | 8 | 8 |
| 1BHK | 33 m² (355 sq.ft) | 1 | 1 |
| 1BHK | 35.8 m² (385 sq.ft) | 4 | 4 |
| 1RK | 16.3 m² (175 sq.ft) | 5 | 3 |
| 1RK | 19.3 m² (208 sq.ft) | 1 | 1 |
| 1RK | 19.4 m² (208 sq.ft) | 1 | 0 |
| 1RK | 19.8 m² (213 sq.ft) | 1 | 0 |
| 1RK | 20.3 m² (218 sq.ft) | 5 | 5 |
| 1RK | 20.7 m² (222 sq.ft) | 7 | 6 |
| 1RK | 20.9 m² (225 sq.ft) | 11 | 2 |
| 1RK | 20.9 m² (225 sq.ft) | 1 | 0 |
| 1RK | 22.4 m² (241 sq.ft) | 5 | 2 |
| 1RK | 22.4 m² (241 sq.ft) | 1 | 0 |
| 1RK | 22.5 m² (242 sq.ft) | 6 | 6 |
| 1RK | 22.8 m² (245 sq.ft) | 1 | 0 |
| 1RK | 24.2 m² (260 sq.ft) | 1 | 1 |
| Shop | 10.6 m² (114 sq.ft) | 1 | 1 |
| Shop | 16.2 m² (175 sq.ft) | 1 | 1 |
| Shop | 18.9 m² (204 sq.ft) | 1 | 1 |
| Shop | 21.2 m² (229 sq.ft) | 1 | 0 |
| Shop | 22.4 m² (241 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P51700014893 · registered 9 Jan 2018
- Promised completion
- 30 Dec 2022
- Revised completion
- 30 Dec 2022
- Sanctioned habitable floors
- 11
- Sanctioned floors (incl. basement, stilt, podium)
- 11
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-400E-1
Questions about Aawas Deep Phase 1
When is Aawas Deep Phase 1 due for completion?
The MahaRERA registration promises 30 Dec 2022.
How many floors does Aawas Deep Phase 1 have?
11 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology