Residential / Group Housing · 2 buildings · 126 unitsRERA P51700014893

Aawas Deep

Its promised completion date, Dec 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 60% of its units are booked.

Badlapur (M Cl), Thane 421503 · Promoter: Shree Krishna Buildcon

Delivery3 yrs 10 mo past duePromised Dec 2022 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales60% booked76 of 126 units · as the promoter reported to MahaRERA
Aawas Deep project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Dec 2022, has passed and MahaRERA does not show it completed

  • This projectRegistered 9 Jan 2018, completion promised 30 Dec 2022, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700014893
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000148939 Jan 201830 Dec 202230 Dec 2022Shree Krishna BuildconProject page
Documents32

1 document held by Deedo, 31 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 27 Dec 2017Source

Legal

  • Declaration Form Bform b-min.pdf · uploaded 28 Dec 2017Source
  • Legal Title reporttitle certi page 1 to 4.pdf · uploaded 28 Dec 2017Source
  • Legal Title reporttitle certi page 5 to 7.pdf · uploaded 28 Dec 2017Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 27 Dec 2017Source
  • 1 Copy of the legal title reporttitle certi page 1 to 4.pdf · uploaded 28 Dec 2017Source
  • 2 Copy of the legal title reporttitle certi page 5 to 7.pdf · uploaded 28 Dec 2017Source
Show all 32 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesnon ecumbrance.pdf · uploaded 28 Dec 2017Source
  • 1 Copy of Layout Approval (in case of layout)blue print.pdf · uploaded 28 Dec 2017Source
  • 1 Building Plan Approval (IOD)blue print.pdf · uploaded 28 Dec 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentnew pdf of cc-min.pdf · uploaded 28 Dec 2017Source
  • 1 Declaration in FORM Bform b-min.pdf · uploaded 28 Dec 2017Source
  • 1 Certificates of CA (Form 3)Form 3 CA.pdf · uploaded 28 Dec 2017Source
  • 1 Proforma of Allotment letterallotment letter.pdf · uploaded 28 Dec 2017Source
  • 2 Proforma of Allotment letterAGREEMENT FOR SALE.pdf · uploaded 28 Dec 2017Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)CA_Certificate.pdf · uploaded 3 Dec 2019Source
  • 2 Copy of Layout Approval (in case of layout)Plan-1.pdf · uploaded 25 Aug 2021Source
  • 3 Copy of Layout Approval (in case of layout)Plan-2.pdf · uploaded 25 Aug 2021Source
  • 1 Declaration about Commencement CertificateFORMAT-D.pdf · uploaded 26 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 26 Aug 2021Source
  • 2 Certificates of CA (Form 3)Form_3_2019.pdf · uploaded 5 Nov 2021Source
  • 3 Certificates of CA (Form 3)Form_3_2020.pdf · uploaded 5 Nov 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5_19-20.pdf · uploaded 5 Nov 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC_compressed.pdf · uploaded 7 Dec 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form-5_SKB_20-21.pdf · uploaded 17 Jun 2022Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Bldg-2.pdf · uploaded 28 Jun 2022Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)Form-4 (Full OC).pdf · uploaded 28 Jun 2022Source

Technical

  • Documentblue print.pdf · uploaded 28 Dec 2017Source
  • Documentblue print.pdf · uploaded 28 Dec 2017Source
  • DocumentPlan-1.pdf · uploaded 25 Aug 2021Source
  • DocumentPlan-2.pdf · uploaded 25 Aug 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsHISSA NO. 1, PART OF HISSA NO. 4

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Shop126 units in all
Address
Survey No. 166, Hissa No. 1, Survey No. 185, Part Of Hissa No. 4, Badlapur Gaon Road, Yashraj NagarPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Designated bank account
203
Developed in phases
Yes

Survey, CTS, gat or plot numbers

HISSA NO. 1PART OF HISSA NO. 4SURVEY NO. 166SURVEY NO. 185

Boundaries

North
Nallah
South
S No 166 H No 2
East
18 M Wide Road
West
S No 166 Part Of H No 1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking126 units

76 of 126 units booked (60%), as the promoter reported to MahaRERA

1BHK · 60 units1RK · 61 unitsShop · 5 units
BuildingTypeCarpet areaUnitsBooked
Aawas Deep Phase 11BHK21.62 sq m · 233 sq ft11
Aawas Deep Phase 11BHK21.94 sq m · 236 sq ft86
Aawas Deep Phase 11BHK23.64 sq m · 254 sq ft10
Aawas Deep Phase 11BHK23.81 sq m · 256 sq ft33
Aawas Deep Phase 11BHK24.86 sq m · 268 sq ft11
Aawas Deep Phase 11BHK25.83 sq m · 278 sq ft10
Aawas Deep Phase 11BHK25.88 sq m · 279 sq ft32
Aawas Deep Phase 11BHK27 sq m · 291 sq ft86
Show all 40 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Aawas Deep Phase 11BHK27.3 sq m · 294 sq ft88
Aawas Deep Phase 11BHK28.8 sq m · 310 sq ft53
Aawas Deep Phase 11BHK29.08 sq m · 313 sq ft33
Aawas Deep Phase 11BHK29.18 sq m · 314 sq ft88
Aawas Deep Phase 11BHK33 sq m · 355 sq ft11
Aawas Deep Phase 11BHK35.78 sq m · 385 sq ft44
Aawas Deep Phase 11RK16.29 sq m · 175 sq ft53
Aawas Deep Phase 11RK19.28 sq m · 208 sq ft11
Aawas Deep Phase 11RK19.37 sq m · 208 sq ft10
Aawas Deep Phase 11RK19.81 sq m · 213 sq ft10
Aawas Deep Phase 11RK20.28 sq m · 218 sq ft55
Aawas Deep Phase 11RK20.66 sq m · 222 sq ft76
Aawas Deep Phase 11RK20.88 sq m · 225 sq ft112
Aawas Deep Phase 11RK20.94 sq m · 225 sq ft10
Aawas Deep Phase 11RK22.38 sq m · 241 sq ft52
Aawas Deep Phase 11RK22.39 sq m · 241 sq ft10
Aawas Deep Phase 11RK22.49 sq m · 242 sq ft66
Aawas Deep Phase 11RK22.77 sq m · 245 sq ft10
Aawas Deep Phase 11RK24.2 sq m · 260 sq ft11
Aawas Deep Phase 1Shop10.56 sq m · 114 sq ft11
Aawas Deep Phase 1Shop16.22 sq m · 175 sq ft11
Aawas Deep Phase 1Shop18.94 sq m · 204 sq ft11
Aawas Deep Phase 1Shop21.23 sq m · 229 sq ft10
Aawas Deep Phase 1Shop22.4 sq m · 241 sq ft11
Aawas Deep Phase 21BHK32 sq m · 344 sq ft10
Aawas Deep Phase 21BHK33.12 sq m · 357 sq ft40
Aawas Deep Phase 21RK20.8 sq m · 224 sq ft10
Aawas Deep Phase 21RK21.55 sq m · 232 sq ft40
Aawas Deep Phase 21RK24.3 sq m · 262 sq ft10
Aawas Deep Phase 21RK24.8 sq m · 267 sq ft10
Aawas Deep Phase 21RK25.03 sq m · 269 sq ft40
Aawas Deep Phase 21RK25.54 sq m · 275 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSachin Vilas Sahane—
EngineerKb Consultants—
OtherRushabh M Saparia—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology