Others · 4 buildings · 41 unitsRERA P51700030491

Tulsi Aagman

Deedo IDDP-THN-QP66

MahaRERA shows it completed; no MahaRERA orders on record; 41% of its units are booked.

Badlapur, Thane 421503 · by Raj Group · 71% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales41% booked17 of 41 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 25 Aug 2021, completion promised 30 Apr 2025.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700030491
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170003049125 Aug 202130 Apr 202530 Apr 2025Raj GroupProject page
Documents77

2 documents held by Deedo, 75 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPan Card.pdf · uploaded 16 Aug 2021Source

Legal

  • Declaration Form BForm B-Clear_compressed.pdf · uploaded 16 Aug 2021Source
  • Legal Title reportLegal and Search Report Com.pdf · uploaded 18 Aug 2021Source

Migrated

  • 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 10 Aug 2021Source
  • 1 Copy of Layout Approval (in case of layout)layout plan-01of 05_compressed.pdf · uploaded 10 Aug 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentlayout plan-01of 05_compressed.pdf · uploaded 10 Aug 2021Source
Show all 77 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC Phase-05.pdf · uploaded 10 Aug 2021Source
  • 1 Declaration about Commencement CertificateForm-D.pdf · uploaded 10 Aug 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 10 Aug 2021Source
  • 1 Proforma of Allotment letterFlat Sale Agreement.pdf · uploaded 10 Aug 2021Source
  • 2 Proforma of Allotment letterShop Sale agreement.pdf · uploaded 10 Aug 2021Source
  • 3 Proforma of Allotment letterFLAT ALLOTTMENT LETTER.pdf · uploaded 10 Aug 2021Source
  • 1 PAN CardPan Card.pdf · uploaded 16 Aug 2021Source
  • 1 Declaration in FORM BForm B-Clear_compressed.pdf · uploaded 16 Aug 2021Source
  • 1 Copy of the legal title reportLegal and Search Report Com.pdf · uploaded 18 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-I up to 31122022 Aagman.pdf · uploaded 15 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5-Tulsi Aagman.pdf · uploaded 15 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-I.pdf · uploaded 27 Mar 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Aagman.pdf · uploaded 27 Mar 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 DATED 31-03-2023.pdf · uploaded 3 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 DATED 31-03-2023.pdf · uploaded 3 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM-2A 31-03-2023.pdf · uploaded 3 Aug 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_2023_Tulsi Aagman.pdf · uploaded 7 Aug 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 JUN-2023 (Aagman)_compressed.pdf · uploaded 16 Aug 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30092023 Aagman.pdf · uploaded 1 Nov 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM- 1 DEC-2023 Aagman.pdf · uploaded 15 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form- Tulsi Aagman PH 5_Apr23 To Jun23-Cpmpressed.pdf · uploaded 15 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form-Tulsi Aagman PH 5_Jul23 To Sep23_Compressed.pdf · uploaded 15 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 31122023 Aagman.pdf · uploaded 29 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3-Tulsi Aagman-Q3_compressed.pdf · uploaded 29 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Raj Group Tulsi Aagman.pdf · uploaded 29 Jan 2024Source
  • 1 Disclosure of sold/ booked inventorySigned Disclosure of Sold_Unsold Inventory Tulsi Aagaman PH 5_compressed.pdf · uploaded 18 May 2024View
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3 Q4 Tulsi Aagman_compressed.pdf · uploaded 18 May 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1 Aagman.pdf · uploaded 23 May 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Aagman.pdf · uploaded 23 May 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBuilding N0-03 OC.pdf · uploaded 8 Jun 2024Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)FORM-4 Build no-3.pdf · uploaded 17 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30062024 Aagman.pdf · uploaded 14 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 300624 (Aagman) compressed.pdf · uploaded 14 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30062024 Aagman.pdf · uploaded 14 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold-unsold inventory (Aagman) Compressed.pdf · uploaded 14 Oct 2024Source
  • 1 Details of encumbrancesAAGMAN ENCUMBRANCE Phase 5.pdf · uploaded 17 Oct 2024Source
  • 1 Proforma of Agreement for salePh 5 Flat Agreement-Final.pdf · uploaded 21 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 22 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3.pdf · uploaded 22 Nov 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)HDFC Bank Ltd Raj Group Tulsi Aagman.pdf · uploaded 22 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 23 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Raj Group - Tulsi Aagman.pdf · uploaded 9 Dec 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Tulsi Aagman Form A.pdf · uploaded 12 Dec 2024Source
  • 3 Disclosure of sold/ booked inventoryDislosure of sold and unsold Inventory.pdf · uploaded 24 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A Aagman.pdf · uploaded 24 Dec 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A Aagman.pdf · uploaded 26 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Aagman Q3.pdf · uploaded 31 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 Aagman_11zon.pdf · uploaded 31 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDiclousure of sold and unsold Q3 Aagman.pdf · uploaded 31 Jan 2025View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Q3 Aagman.pdf · uploaded 7 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Q3 Aagman.pdf · uploaded 7 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31_03_2025 Tulsi Aagman.pdf · uploaded 2 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 31_03_2025_Aagman.pdf · uploaded 2 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 31_03_2025 _Aagman.pdf · uploaded 2 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 31_03_2025 Aagman_11zon.pdf · uploaded 5 May 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold-unsold inventory 31_03_2025 Aagman _11zon.pdf · uploaded 6 May 2025View

Technical

  • Documentlayout plan-01of 05_compressed.pdf · uploaded 10 Aug 2021Source
  • Documentlayout plan-01of 05_compressed.pdf · uploaded 10 Aug 2021Source

Technical (Architect)

  • DocumentFORM1 Aagman.pdf · uploaded 23 May 2024Source
  • DocumentFORM-1 30062024 Aagman.pdf · uploaded 14 Oct 2024Source
  • DocumentFORM-1.pdf · uploaded 22 Nov 2024Source
  • DocumentForm 1 Aagman Q3.pdf · uploaded 31 Jan 2025Source
  • DocumentFORM 1 31_03_2025 Tulsi Aagman.pdf · uploaded 2 May 2025Source

Technical (Engineer)

  • DocumentFORM 2 Aagman.pdf · uploaded 23 May 2024Source
  • DocumentFORM-2 30062024 Aagman.pdf · uploaded 14 Oct 2024Source
  • DocumentFORM-2.pdf · uploaded 23 Nov 2024Source
  • DocumentFORM 2 Q3 Aagman.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 2 Q3 Aagman.pdf · uploaded 7 Feb 2025Source
  • DocumentForm 2 31_03_2025_Aagman.pdf · uploaded 2 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2, 3 S No37 H No1 S No40 H No5

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Address
S No 36 H No-1, 2, 3 S No-37 H No-1 S No-40 H No-5, Kharvai, BadlapurPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
9,270 sq m (99,781 sq ft)
Permissible built-up area
17,917 sq m (1,92,853 sq ft)
Sanctioned built-up area
17,917 sq m (1,92,853 sq ft)
Recreational open space
714 sq m (7,688 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

23 S No37 H No1 S No40 H No5S No 36 H No1

Land as published on MahaRERA's project page

S No 36 H No-1,2,3 S No-37 H No-1 S No-40 H No-5

Boundaries

North
S No-40 37 3 Land
South
30 MW Road
East
S No-37 land
West
S No-46 Land

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectS R Khambayat Partner of RAJ ASSOCIATES—
Chartered accountantCA Ganapath jain—
Chartered accountantCA Rajendra Cjhaplot—
EngineerKamleshkumar Ratilal Patel Prop of KR PATEL & ASSOCIATES—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Badlapur

All 152 projects in Badlapur · Compare Tulsi Aagman with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology