Raj Group
Deedo IDDD-QM45Of 7 registrations whose promised date has arrived, 5 kept it (71%). The rest ran a median 12 mo late.
Delivery record
2 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tulsi AahanP51700000064 | Badlapur | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Tulsi AadvikP51700015302 | Badlapur (M Cl) | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | On date |
| Tulsi AahanP51700025116 | Badlapur | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Tulsi AagmanP51700030491 | Badlapur | Certificate Signed | 30 Apr 2025 | 30 Apr 2025 | On date |
| Tulsi AanandP51700032811 | Badlapur (M Cl) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Tulsi AawasP51700046339 | Badlapur | Certificate Signed | 31 Dec 2024 | 31 Dec 2025 | +12 mo |
| Tulsi AaradhanaP51700047616 | Badlapur | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
Raj Group, in questions
Does Raj Group finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 5 kept it (71%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Raj Group registered with MahaRERA?
6 projects under 7 MahaRERA registrations; 6 completed on MahaRERA.
Does Raj Group have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.