Ambarnath, Thane
Deedo IDDL-THN-AMBARNATH9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects1,597
Registrations1,682some projects hold several
Completion still due5731,008 past their date
Median extension4 months41% of registrations extended
Regulatory cases89on 25 projects
9 in 10 registrations run late here
1,682 MahaRERA registrations in Ambarnath and the places within it
22 completed137 not yet due435 extended, not yet due987 past even the latest date101 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Ambarnath
1,597 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Laxmi Narayan Co-op Housing Society LtdPraveen Buildcon RPJT | Due Jul 2028, extended 4 mo | — | — |
| Patels PrimePatel Rpl Realty Private Limited | Due Dec 2028, extended 4 mo | — | — |
| Vrindavan NidhiSai Properties | Due Apr 2028, extended 4 mo | — | — |
| Girija ChsJainam Infra | Due Apr 2029, extended 4 mo | — | — |
| Rosewood Residency Building No. 2Aditya Aanandi Associates | Due Mar 2031, extended 4 mo | — | — |
| Shree Shivsai Co. Op. Hsg. Soc.Shiv Sai Developers | Due Apr 2029, extended 4 mo | — | — |
| Datar Height D And E WingDatar Constructions | Due Apr 2029, extended 4 mo | — | — |
| Om Sagar ParkTown Icon | Due Jul 2029, extended 4 mo | — | — |
| Ambernath Vadavali Shrinivas Co.Operative Housing Society Ltd.Shree Sainath Developers | Due Sep 2027, extended 4 mo | — | — |
| Hiral Paradise ChsPhoenix Construction | Due Apr 2028, extended 4 mo | — | — |
| Shree Sahawas ChslShree Krupa Builders And Developers | Due Feb 2028, extended 4 mo | — | — |
| Durvankur Co-op Hsg Soc LtdSuresh Keshavrao Yashvantrao | Due Mar 2028 | — | — |
| Shilpa Adarsh Co Op Housing Society LimitedShree Rameshwaram Builders & Developers | Due Jan 2030, extended 4 mo | — | — |
| Sumant Chs LtdGps Lifespace | Due Feb 2029, extended 4 mo | — | — |
| Sadguru HeightsSai Datta Builders And Developers LLP | Due Apr 2029, extended 4 mo | — | — |
| Merry MansionDivya Enterprises | Due Sep 2028, extended 4 mo | — | — |
| Shrey SwapnaShree Sai Builders And Developers | Due Feb 2028, extended 4 mo | — | — |
| Motiram NakshatraShree Sai Infra | Due Jun 2030 | — | — |
| Pandharinath ChsYadav Bros Enterprises | Due Jul 2027, extended 4 mo | — | — |
| Shree Ganesh Leela Co-operative Housing Society LimitedAbhishek Developers | Due Feb 2028, extended 4 mo | — | — |
| Janaki SadanShreeji Developers | Due Dec 2027, extended 4 mo | — | — |
| Sharmila SadanShree Vedant Krupa | Due Jul 2029, extended 4 mo | — | — |
| Babaji CHSRelation Developers | Due Jul 2028, extended 4 mo | — | — |
| Shiv ElysiumShiv Corporation | Due Apr 2029, extended 4 mo | — | — |
| Padmanabh HeightsCrystal Infra | Due Nov 2028, extended 4 mo | — | — |
Nearby: other talukas in Thane
Most active promoters
- Mohan Lifespaces Llp12 projects
- Ishwar Reality9 projects
- Gulabrao Baburao Karanjule Patil8 projects
- Mohan Hardasmal Tharwani8 projects
- D A Construction7 projects
- Kgi Realty Private Limited7 projects
- Empire Industries Limited6 projects
- Keyblue Realtors Private Limited6 projects
- Panvelkar Infrastructures Private Limited6 projects
- Pramukh Developers6 projects
Ambarnath, in questions
How many projects in Ambarnath run late?
9 in 10 MahaRERA registrations (1,422 of 1,682): their completion date was extended or has passed, data through 2 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ambarnath by Deedo. Medians on fewer than 3 deeds are not shown.
Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology