9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,597
Registrations1,682some projects hold several
Completion still due5731,008 past their date
Median extension4 months41% of registrations extended
Regulatory cases89on 25 projects

9 in 10 registrations run late here

1,682 MahaRERA registrations in Ambarnath and the places within it

22 completed137 not yet due435 extended, not yet due987 past even the latest date101 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Ambarnath

1,597 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Laxmi Narayan Co-op Housing Society LtdPraveen Buildcon RPJTDue Jul 2028, extended 4 mo——
Patels PrimePatel Rpl Realty Private LimitedDue Dec 2028, extended 4 mo——
Vrindavan NidhiSai PropertiesDue Apr 2028, extended 4 mo——
Girija ChsJainam InfraDue Apr 2029, extended 4 mo——
Rosewood Residency Building No. 2Aditya Aanandi AssociatesDue Mar 2031, extended 4 mo——
Shree Shivsai Co. Op. Hsg. Soc.Shiv Sai DevelopersDue Apr 2029, extended 4 mo——
Datar Height D And E WingDatar ConstructionsDue Apr 2029, extended 4 mo——
Om Sagar ParkTown IconDue Jul 2029, extended 4 mo——
Ambernath Vadavali Shrinivas Co.Operative Housing Society Ltd.Shree Sainath DevelopersDue Sep 2027, extended 4 mo——
Hiral Paradise ChsPhoenix ConstructionDue Apr 2028, extended 4 mo——
Shree Sahawas ChslShree Krupa Builders And DevelopersDue Feb 2028, extended 4 mo——
Durvankur Co-op Hsg Soc LtdSuresh Keshavrao YashvantraoDue Mar 2028——
Shilpa Adarsh Co Op Housing Society LimitedShree Rameshwaram Builders & DevelopersDue Jan 2030, extended 4 mo——
Sumant Chs LtdGps LifespaceDue Feb 2029, extended 4 mo——
Sadguru HeightsSai Datta Builders And Developers LLPDue Apr 2029, extended 4 mo——
Merry MansionDivya EnterprisesDue Sep 2028, extended 4 mo——
Shrey SwapnaShree Sai Builders And DevelopersDue Feb 2028, extended 4 mo——
Motiram NakshatraShree Sai InfraDue Jun 2030——
Pandharinath ChsYadav Bros EnterprisesDue Jul 2027, extended 4 mo——
Shree Ganesh Leela Co-operative Housing Society LimitedAbhishek DevelopersDue Feb 2028, extended 4 mo——
Janaki SadanShreeji DevelopersDue Dec 2027, extended 4 mo——
Sharmila SadanShree Vedant KrupaDue Jul 2029, extended 4 mo——
Babaji CHSRelation DevelopersDue Jul 2028, extended 4 mo——
Shiv ElysiumShiv CorporationDue Apr 2029, extended 4 mo——
Padmanabh HeightsCrystal InfraDue Nov 2028, extended 4 mo——
Ambarnath market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Mohan Lifespaces Llp12 projects
  2. Ishwar Reality9 projects
  3. Gulabrao Baburao Karanjule Patil8 projects
  4. Mohan Hardasmal Tharwani8 projects
  5. D A Construction7 projects
  6. Kgi Realty Private Limited7 projects
  7. Empire Industries Limited6 projects
  8. Keyblue Realtors Private Limited6 projects
  9. Panvelkar Infrastructures Private Limited6 projects
  10. Pramukh Developers6 projects

Ambarnath, in questions

How many projects in Ambarnath run late?

9 in 10 MahaRERA registrations (1,422 of 1,682): their completion date was extended or has passed, data through 2 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ambarnath by Deedo. Medians on fewer than 3 deeds are not shown.

Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology