Ambarnath, Thane
Deedo IDDL-THN-AMBARNATH9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects1,597
Registrations1,682some projects hold several
Completion still due5731,008 past their date
Median extension4 months41% of registrations extended
Regulatory cases89on 25 projects
9 in 10 registrations run late here
1,682 MahaRERA registrations in Ambarnath and the places within it
22 completed137 not yet due435 extended, not yet due987 past even the latest date101 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Ambarnath
1,597 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Pavillion East ViewPavilion Realty | Due Apr 2029, extended 4 mo | — | — |
| Rustomjee Urban Woods - BanyanKeyblue Realtors Private Limited | Due Oct 2030, extended 4 mo | — | — |
| Jai Prathamesh Co-operative Housing Society LtdHousai Builders & Developers | Due Apr 2028 | — | — |
| ShivHari CHSImpero Buildcon | Due Apr 2030, extended 4 mo | — | — |
| Amber SolitaireNamaskar Builders And Developers | Due May 2030, extended 4 mo | — | — |
| Gouri Aangan CHSU S Constructions | Due Jul 2027, extended 4 mo | — | — |
| Laxmivihar Co-Operative Housing Society LimitedShree Saraswati Developers | Due Apr 2030, extended 4 mo | — | — |
| Trident WoodsShri Jagannath Realtors | Due Dec 2028 | — | — |
| Unimax LifeGrowmore Lifespaces LLP | Due Apr 2031, extended 4 mo | — | — |
| Shree Asthavinayak Complex Building No.1Vastu Recon | Due Oct 2028, extended 4 mo | — | — |
| Shivam Heritage Wing BM.K. Enterprises | Due Apr 2029, extended 4 mo | — | — |
| Royale GalaxyProspire Realty Private Limited | Due Oct 2029, extended 4 mo | — | — |
| Vaishnavi HeavenVaishnavi Developers | Due Dec 2029 | — | — |
| Vishnu VertexVishnu Bihar Builders And Developers LLP | Due Jul 2031, extended 4 mo | — | — |
| Thanekar Bkc VistaThanekar Realtor LLP | Due Sep 2029, extended 4 mo | — | — |
| Trident VrindavanShri Krishna Shristi | Due Apr 2029, extended 4 mo | — | — |
| Avighna HeightsAmar Associates | Due Dec 2030, extended 4 mo | — | — |
| Jai Shriram CO-Operative Housing Society Ltd.Praveen Buildcon | Due Apr 2027, extended 4 mo | — | — |
| Swanand Niwas Co Op Housing Society LtdKasturi Life Space | Due Apr 2030, extended 4 mo | — | — |
| Thanekar Bkc ParamountThanekar Realtor LLP | Due Apr 2029, extended 4 mo | — | — |
| Shivam NirvaanaM K Realty | Due Apr 2031, extended 4 mo | — | — |
| Arihant DigvijayArihant Developers | Due Sep 2028, extended 4 mo | — | — |
| Jhalak HillockJhalak Constructions | Due Apr 2028, extended 4 mo | — | — |
| Saurabh SankulS K Developers | Due Dec 2028 | — | — |
| Vishwa ParadiseShree Samarth Vishwa Developers | Due Jul 2030, extended 4 mo | — | — |
Nearby: other talukas in Thane
Most active promoters
- Mohan Lifespaces Llp12 projects
- Ishwar Reality9 projects
- Gulabrao Baburao Karanjule Patil8 projects
- Mohan Hardasmal Tharwani8 projects
- D A Construction7 projects
- Kgi Realty Private Limited7 projects
- Empire Industries Limited6 projects
- Keyblue Realtors Private Limited6 projects
- Panvelkar Infrastructures Private Limited6 projects
- Pramukh Developers6 projects
Ambarnath, in questions
How many projects in Ambarnath run late?
9 in 10 MahaRERA registrations (1,422 of 1,682): their completion date was extended or has passed, data through 2 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ambarnath by Deedo. Medians on fewer than 3 deeds are not shown.
Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology