9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,597
Registrations1,682some projects hold several
Completion still due5731,008 past their date
Median extension4 months41% of registrations extended
Regulatory cases89on 25 projects

9 in 10 registrations run late here

1,682 MahaRERA registrations in Ambarnath and the places within it

22 completed137 not yet due435 extended, not yet due987 past even the latest date101 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Ambarnath

1,597 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Pavillion East ViewPavilion RealtyDue Apr 2029, extended 4 mo——
Rustomjee Urban Woods - BanyanKeyblue Realtors Private LimitedDue Oct 2030, extended 4 mo——
Jai Prathamesh Co-operative Housing Society LtdHousai Builders & DevelopersDue Apr 2028——
ShivHari CHSImpero BuildconDue Apr 2030, extended 4 mo——
Amber SolitaireNamaskar Builders And DevelopersDue May 2030, extended 4 mo——
Gouri Aangan CHSU S ConstructionsDue Jul 2027, extended 4 mo——
Laxmivihar Co-Operative Housing Society LimitedShree Saraswati DevelopersDue Apr 2030, extended 4 mo——
Trident WoodsShri Jagannath RealtorsDue Dec 2028——
Unimax LifeGrowmore Lifespaces LLPDue Apr 2031, extended 4 mo——
Shree Asthavinayak Complex Building No.1Vastu ReconDue Oct 2028, extended 4 mo——
Shivam Heritage Wing BM.K. EnterprisesDue Apr 2029, extended 4 mo——
Royale GalaxyProspire Realty Private LimitedDue Oct 2029, extended 4 mo——
Vaishnavi HeavenVaishnavi DevelopersDue Dec 2029——
Vishnu VertexVishnu Bihar Builders And Developers LLPDue Jul 2031, extended 4 mo——
Thanekar Bkc VistaThanekar Realtor LLPDue Sep 2029, extended 4 mo——
Trident VrindavanShri Krishna ShristiDue Apr 2029, extended 4 mo——
Avighna HeightsAmar AssociatesDue Dec 2030, extended 4 mo——
Jai Shriram CO-Operative Housing Society Ltd.Praveen BuildconDue Apr 2027, extended 4 mo——
Swanand Niwas Co Op Housing Society LtdKasturi Life SpaceDue Apr 2030, extended 4 mo——
Thanekar Bkc ParamountThanekar Realtor LLPDue Apr 2029, extended 4 mo——
Shivam NirvaanaM K RealtyDue Apr 2031, extended 4 mo——
Arihant DigvijayArihant DevelopersDue Sep 2028, extended 4 mo——
Jhalak HillockJhalak ConstructionsDue Apr 2028, extended 4 mo——
Saurabh SankulS K DevelopersDue Dec 2028——
Vishwa ParadiseShree Samarth Vishwa DevelopersDue Jul 2030, extended 4 mo——
Ambarnath market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Mohan Lifespaces Llp12 projects
  2. Ishwar Reality9 projects
  3. Gulabrao Baburao Karanjule Patil8 projects
  4. Mohan Hardasmal Tharwani8 projects
  5. D A Construction7 projects
  6. Kgi Realty Private Limited7 projects
  7. Empire Industries Limited6 projects
  8. Keyblue Realtors Private Limited6 projects
  9. Panvelkar Infrastructures Private Limited6 projects
  10. Pramukh Developers6 projects

Ambarnath, in questions

How many projects in Ambarnath run late?

9 in 10 MahaRERA registrations (1,422 of 1,682): their completion date was extended or has passed, data through 2 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ambarnath by Deedo. Medians on fewer than 3 deeds are not shown.

Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology