Majrewadi, Solapur
Deedo IDDL-SOL-MAJREWADI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects31
Registrations31
Completion still due1615 past their date
Median extension4 months39% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
31 MahaRERA registrations in Majrewadi
6 not yet due10 extended, not yet due15 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Majrewadi
31 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shri Swami Samarth PearlShri Swami Samarth Reality | Due Dec 2030 | — | — |
| Vinayak ResidencyGhodake Developer | Due Dec 2028 | — | — |
| Flora ParkImage Space Incorporated | Due Sep 2032, extended 4 mo | — | — |
| Royal Imperial TowerRoyal Buildcon & Associates | Due Aug 2029, extended 4 mo | — | — |
| Vijayraj VishvaAruna Realtors | Due Apr 2033, extended 4 mo | — | — |
| Yarawa ResidencyYarawa Buildcon LLP | Due Jul 2029, extended 4 mo | — | — |
| Royal HeritageMahadev Iranna Akalwadi | Due Jul 2027, extended 4 mo | — | 7% |
| Bahava ApartmentTauseef Jaweed Shaikh & Jaweed Gulam Shaikh | Due Dec 2027 | — | 40% |
| Flora KalpanaImage Space Incorporated | Due Aug 2027, extended 4 mo | — | — |
| AkshataKisan Constructions Pvt Ltd | Completed | — | — |
| Aviraj HeightsVidhyadhar Mallikarjun Akkalwadi | Due Dec 2027 | — | 50% |
| Shri Ram Sankul AppartmentChhaya Kamalakar Chafekar | 1 yr 6 mo late | — | — |
| Kotkunde CrownMurtuz Abdul Razzaque Kotkunde | Due Apr 2027, extended 4 mo | — | — |
| Shazneen GalaxyNazneen Jainodin Nadaf | Due Apr 2027, extended 4 mo | — | — |
| Rajashree HeightsRajashree Builders | Due Dec 2027 | — | — |
| Royal CrownRoyal Buildcon | Completed | — | 80% |
| Saffron SquareMohsin Haroon Shaikh | Due Apr 2028, extended 4 mo | — | 14% |
| Seven Hills ApartmentSeven Hills Developers | 1 yr 2 mo late | — | 63% |
| Motiwala SkylineAyyub Usman Motiwala | Completed | — | — |
| Flora GrandviewImage Space Incorporated | Completed | — | 45% |
| Flora IconImage Space Incorporated | Completed | — | — |
| High MarkNishat Motiwala | 11 mo late | — | — |
| Altamash ResidencyAbdulsattar Shaikh | 11 mo late | — | — |
| Vijayraj ArunodayRajlaxmi Amar Birajdar | Due Apr 2027, extended 4 mo | — | 100% |
| Silver Oak PrimeSkyline builders & Developers | 1 yr 10 mo late | — | 69% |
Nearby: other villages in Solapur North
Most active promoters
- Image Space Incorporated3 projects
- Abdulsattar Shaikh1 project
- Akruti Constructions1 project
- Aruna Realtors1 project
- Ayyub Usman Motiwala1 project
- Chhaya Kamalakar Chafekar1 project
- Fairdeal Constructions1 project
- Ghodake Developer1 project
- Image Space Incorporated1 project
- Kisan Constructions Pvt Ltd1 project
Majrewadi, in questions
How many projects in Majrewadi run late?
8 in 10 MahaRERA registrations (25 of 31): their completion date was extended or has passed, data through 13 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Majrewadi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through13 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology