8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects547in 37 localities
Registrations557some projects hold several
Completion still due166330 past their date
Median extension4 months36% of registrations extended
Regulatory cases30on 30 projects

8 in 10 registrations run late here

557 MahaRERA registrations in Solapur and the places within it

43 not yet due123 extended, not yet due330 past even the latest date61 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Solapur

547 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Radhakrishna AvenueMainavi Construction And Developers1 yr 11 mo late—76%
Gurukrupa ResidencyGirish Gurappa Sakhare2 yrs 8 mo late——
Matoshri ResidencyBharat Hambirrav Salunke1 yr late——
Maheshwari HeightsMaheshwari Developers And Builders1 yr 10 mo late——
Royal TowerRoyal Infra1 yr 10 mo late——
Nirmiti LandmarkNirmiti DevelopersDue Nov 2027—45%
Baitul FalahVijayraj EnterprisesDue Dec 2026—100%
Jahagirdar ResidencyParwez Isak Jahagirdar1 yr 11 mo late——
Sankalp HeightsDaiwik DevelopersCompleted——
Bajirao HeightsShekhar Bajirao Jadhav1 yr 10 mo late——
Shree Vasundhara HeightsKishor Rajendra SanjekarDue Apr 2027, extended 4 mo——
Shri Bhandare HeightsGokul Chandrakant BhandareCompleted—39%
Heritage PrimeHeritage Ashcon Properties2 yrs 8 mo late——
AL Awwal HeightsSarfaraz Allauddin Barchi1 yr 10 mo late——
Central ParkUsman Hassam Mansuri1 yr 10 mo late—30%
Panjwani MarketV V Somshetti Builders LLPDue Apr 2031, extended 4 mo——
Gayatri Vihar wing BShriniwas Ashayya ArakalCompleted——
Siddha-Trimbak TowerMinakshi Jayprakash Jankar1 yr 10 mo late—13%
INDRADHANU-Phase-8Ganesh Ramchandra ApteDue Mar 2030, extended 4 mo——
Samruddhi ParkwayNagnath Shivshankar AkkalkoteDue Apr 2031, extended 4 mo—21%
Signature SquareMohsin Haroon Shaikh1 yr 10 mo late——
Gayatri Vihar wing ARahul Rajnikant ArakalCompleted——
RamalayamDiddi Infracon1 yr 11 mo late—80%
Rushi MarvelMeghshyam Mallikarjun Yemul2 yrs 5 mo late——
Millennium TowerHamid Ramzansab Shaikh2 yrs 7 mo late——
Solapur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Dhariwal And Chhoriya Buildcon Pvt Ltd7 projects
  2. Devendra Vasudeo Sangolkar6 projects
  3. Mohsin Haroon Shaikh6 projects
  4. Dhariwal And Chhoriya Buildcon Pvt Ltd5 projects
  5. Squareone Builders & Developers5 projects
  6. Tirupati Construction Promoters & Developers5 projects
  7. Ayyub Usman Motiwala4 projects
  8. Hanmantu Komarayya Bura4 projects
  9. Image Space Incorporated4 projects
  10. Pandhe Infracons Pvt Ltd4 projects

Solapur, in questions

How many projects in Solapur run late?

8 in 10 MahaRERA registrations (453 of 557): their completion date was extended or has passed, data through 2 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Solapur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology