Solapur
Deedo IDDL-SOL-SOLAPUR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects547in 37 localities
Registrations557some projects hold several
Completion still due166330 past their date
Median extension4 months36% of registrations extended
Regulatory cases30on 30 projects
8 in 10 registrations run late here
557 MahaRERA registrations in Solapur and the places within it
43 not yet due123 extended, not yet due330 past even the latest date61 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Solapur
547 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Flora IconImage Space Incorporated | Completed | — | — |
| Atharv Pride Phase 3Devendra Vasudeo Sangolkar | Completed | — | 42% |
| Prime GalaxyPrime Construction | Due Apr 2027, extended 4 mo | — | 48% |
| Shelar ComplexVijay Shrirang Shelar | Due Apr 2031, extended 4 mo | — | — |
| Shhraddha Ellegance Building HShhraddha Properties | Due Dec 2027 | — | 9% |
| Shri Pandurang ReidencyMnk Builders And Developers | Completed, extended 11 mo | — | 31% |
| Kimaya PrimeSamir Amrut Gandhi | 1 yr 8 mo late | — | 45% |
| Laxminarayan HillsVijayshree Construction And Developers | 1 yr 11 mo late | — | — |
| Bhaiji ApartmentBhaiji Apartment | 11 mo late | — | 11% |
| Tirupati Royal HomesTirupati Construction Promoters & Developers | Completed | — | — |
| High MarkNishat Motiwala | 11 mo late | — | — |
| Altamash ResidencyAbdulsattar Shaikh | 11 mo late | — | — |
| Nikunj ResidencySudarshan Umakant Chakre | Due Apr 2027, extended 4 mo | — | 38% |
| PMAY Barshi Nagar Parishad AhpBarshi Nagar Parishad | Due Jan 2027, extended 4 mo | — | — |
| Madur SquareShri Mahalaxmi Developers | 1 yr 10 mo late | — | — |
| Majestic SquareMohsin Haroon Shaikh | Due Apr 2027, extended 4 mo | — | — |
| Venkatesh La-Arka Phase IIP A Sathe & Associates | 3 yrs 8 mo late | — | — |
| Lokhandwala horizonSiddique Iqbal Motiwala | Completed | — | — |
| ShivMalhar ComplexSaisamarth Deep Developers | Due Dec 2026, extended 2 yrs 1 mo | — | — |
| Snc Grand ResidenceA S D C Developers | 8 mo late | — | 45% |
| Heritage PrimeHeritage Ashcon Properties | Completed | — | — |
| Star Icon ResidencyNazneen Jainodin Nadaf | 2 yrs 10 mo late | — | 8% |
| Barchi AvenuoSarfaraz Allauddin Barchi | 2 yrs 10 mo late | — | — |
| Mangalmurti ResidencyGavasane Builders | 1 yr 3 mo late | — | — |
| Alif ResidencyOrion Developers | 11 mo late | — | — |
Localities in Solapur
- Solapur (M Corp.)303 projects
- Solapur North37 projects
- Pandharpur32 projects
- Majrewadi30 projects
- Barshi26 projects
- Isbavi24 projects
- Barshi8 projects
- Tembhurni7 projects
- Karmala (Rural)6 projects
- Sangole (M Cl)6 projects
- Wakhari5 projects
- Pandharpur4 projects
Other districts
Most active promoters
- Dhariwal And Chhoriya Buildcon Pvt Ltd7 projects
- Devendra Vasudeo Sangolkar6 projects
- Mohsin Haroon Shaikh6 projects
- Dhariwal And Chhoriya Buildcon Pvt Ltd5 projects
- Squareone Builders & Developers5 projects
- Tirupati Construction Promoters & Developers5 projects
- Ayyub Usman Motiwala4 projects
- Hanmantu Komarayya Bura4 projects
- Image Space Incorporated4 projects
- Pandhe Infracons Pvt Ltd4 projects
Solapur, in questions
How many projects in Solapur run late?
8 in 10 MahaRERA registrations (453 of 557): their completion date was extended or has passed, data through 2 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Solapur by Deedo. Medians on fewer than 3 deeds are not shown.
Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology