8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects547in 37 localities
Registrations557some projects hold several
Completion still due166330 past their date
Median extension4 months36% of registrations extended
Regulatory cases30on 30 projects

8 in 10 registrations run late here

557 MahaRERA registrations in Solapur and the places within it

43 not yet due123 extended, not yet due330 past even the latest date61 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Solapur

547 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Dwarkadhish EnclaveVaishnavi ConstructionDue Apr 2027, extended 4 mo——
Shri Pralhad Smurti ResidencyVijayratna DevelopersDue Apr 2027, extended 4 mo——
K-S BougainvilleaKaranje-Surana Constructions Pvt. Ltd.Due Apr 2030, extended 4 mo——
KrishnalayamDiddi InfraconsDue Dec 2027, extended 4 mo——
Royal SynergyShree Jagdamb DevelopersDue Apr 2030, extended 4 mo——
Royal HeritageMahadev Iranna AkalwadiDue Jul 2027, extended 4 mo—7%
Lotus ApartmentLotus Apartment1 yr 8 mo late——
Laxmi ResidencyLaxmikant InfraDue Apr 2028, extended 4 mo—12%
Radha Damodar SankulShashikant Marutirao JiddimaniDue Apr 2031, extended 4 mo——
Bahava ApartmentTauseef Jaweed Shaikh & Jaweed Gulam ShaikhDue Dec 2027—40%
Daksh ResidencyBhagyoday BuildersCompleted——
Shivtej PlazaSomanath Jagnnath NikamDue Apr 2027, extended 4 mo——
Paras Business ParkPriyadarshani CorporationDue Apr 2031, extended 4 mo——
Kaizen EmeraldSwapnil Nalin KothadiaDue Dec 2027—4%
Gawade HeightsSwati Ajitkumar GawadeDue Apr 2029, extended 4 mo——
B9 LifestyleDinesh Khushiram AgrawalDue Apr 2028, extended 4 mo——
Aakruti HeritageAakruti DevelopersDue Mar 2028, extended 4 mo——
Construction of 224 LIG Residential T/S on Land Bearing Survey No 25A/1 Pandharpur Dist SolapurPune Housing and Area Development Board PuneDue Apr 2033, extended 4 mo——
Vasant ViharV.a. DevelopersDue Jul 2027, extended 4 mo—39%
Infinity EnclaveInfinity RealityDue Sep 2027, extended 4 mo——
Somnath HeightsSandeep Shivrudra MokashiDue Apr 2027, extended 4 mo——
Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman SansthaAnukarati Homes Private LimitedDue Apr 2027, extended 4 mo——
Flora KalpanaImage Space IncorporatedDue Aug 2027, extended 4 mo——
Pushpakunj ParkManali RealtyCompleted——
Construction of Composite Housing Scheme of 126 T/s EWS and 112 T/s LIGPune Housing and Area Development Board PuneDue Apr 2033, extended 4 mo——
Solapur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Dhariwal And Chhoriya Buildcon Pvt Ltd7 projects
  2. Devendra Vasudeo Sangolkar6 projects
  3. Mohsin Haroon Shaikh6 projects
  4. Dhariwal And Chhoriya Buildcon Pvt Ltd5 projects
  5. Squareone Builders & Developers5 projects
  6. Tirupati Construction Promoters & Developers5 projects
  7. Ayyub Usman Motiwala4 projects
  8. Hanmantu Komarayya Bura4 projects
  9. Image Space Incorporated4 projects
  10. Pandhe Infracons Pvt Ltd4 projects

Solapur, in questions

How many projects in Solapur run late?

8 in 10 MahaRERA registrations (453 of 557): their completion date was extended or has passed, data through 2 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Solapur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology