8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects547in 37 localities
Registrations557some projects hold several
Completion still due166330 past their date
Median extension4 months36% of registrations extended
Regulatory cases30on 30 projects

8 in 10 registrations run late here

557 MahaRERA registrations in Solapur and the places within it

43 not yet due123 extended, not yet due330 past even the latest date61 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Solapur

547 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Tuljai RecedencySatyabhamavitthal Construction And Land Developers Private Limited Barshi3 yrs 11 mo late——
Mahalaxmi apartmentnagesh Laxman TakmogeCompleted——
AashrayKisan Constructions Pvt LtdCompleted—65%
Mahaveer TowerMahaveer Developers And Builders11 mo late——
Shree Gururaj ParkGayatri Builders And Developers3 yrs late——
Akruti HeightsAkruti ConstructionsDue Nov 2026——
Shindeshahi ResidencyMaruti Narayan ShindeCompleted, extended 1 yr—4%
Rajyog ResidencyNirmitee Developers&Builders4 yrs 11 mo late—8%
Golden TowerSamir Walmik Ahire Proprietor Of Pallavi Realtors1 yr 11 mo late—35%
Moraya ResidencyGavasane BuildersCompleted—100%
Chhoriya Residency - PandharpurDhariwal And Chhoriya Developers LLPDue Apr 2030, extended 4 mo——
Om Residency Phase IIOmkara Home Construction Private LimitedCompleted—4%
Hmempire210211Heriytage Maniydhari Empire8 mo late——
Khushi HeightsKhushi Builders And Developers1 yr 8 mo late——
Flora GalaxiaImage Space IncorporatedCompleted—93%
Indraprastha ResidencyYashwardhan Constructions Pvt LtdCompleted——
RSM Unity DevelopersRSM Unity DevelopersDue Apr 2028, extended 4 mo——
S B Peace CornerS B ConstructionCompleted——
Deshbhakta Harinarayan Soni City D-WingSoni Somani InfrastructureCompleted—67%
JABs Shaheen ArcadeIrfan Chitasaab Khairdi3 yrs 4 mo late——
Mayuresh Residency Phase 2Devendra Vasudeo SangolkarCompleted—73%
ShishirShri Mauli Buildcon1 yr 5 mo late——
Shakuntal Nagar -Phase 4Kapil Pandurang Dingare1 yr 11 mo late—95%
Shree Krushna Pandhari TowersYogeshwar Buildcon4 yrs 2 mo late——
Suyog ShrushtiSuyog DevelopersCompleted——
Solapur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Dhariwal And Chhoriya Buildcon Pvt Ltd7 projects
  2. Devendra Vasudeo Sangolkar6 projects
  3. Mohsin Haroon Shaikh6 projects
  4. Dhariwal And Chhoriya Buildcon Pvt Ltd5 projects
  5. Squareone Builders & Developers5 projects
  6. Tirupati Construction Promoters & Developers5 projects
  7. Ayyub Usman Motiwala4 projects
  8. Hanmantu Komarayya Bura4 projects
  9. Image Space Incorporated4 projects
  10. Pandhe Infracons Pvt Ltd4 projects

Solapur, in questions

How many projects in Solapur run late?

8 in 10 MahaRERA registrations (453 of 557): their completion date was extended or has passed, data through 2 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Solapur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through2 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology