RERA projects in Vavandal
3 projects under 4 MahaRERA registrations, registered 2017–2026. 50% have a completion date extended beyond the one promised.
3RERA projects
4Registrationssome projects hold several
1Completion still due3 past their completion date
13 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 2 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 0 |
| 2026 | 1 |
Projects in Vavandal
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Riyasat RoyalcrestRiyasat Infra Developers Private Limited | PP1270002600401 | 12 May 2026 | 30 Jun 2027 | — | Not yet due | 0 |
| ParivarammVijay Ashok Jeswani | P52000030422, P52000030442 | 25 Aug 2021 | 31 Aug 2026 | 28 Mar 2025 | Promised date passed | 0 |
| MalagaDevtaa Yash Lifescapes Pvt Ltd | P52000005923 | 14 Aug 2017 | 30 Dec 2022 | 30 Dec 2024 | Extended 24 mo | 0 |
Other localities in Khalapur
Most active promoters
By projects registered here, as named on MahaRERA.
- Devtaa Yash Lifescapes Pvt Ltd1 project
- Riyasat Infra Developers Private Limited1 project
- Vijay Ashok Jeswani1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology