Deedo IDDL-RAI-PANSHIL10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects9
Registrations9
Completion still due81 past their date
Median extension4 months89% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
9 MahaRERA registrations in Panshil
8 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Panshil
9 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| StadiaPersipina Developers Private Limited | Due Apr 2033, extended 4 mo | — | — |
| OlympusPersipina Developers Private Limited | Due Apr 2033, extended 4 mo | — | — |
| AtheleticaPersipina Developers Private Limited | Due Oct 2032, extended 4 mo | — | — |
| GrandstandPersipina Developers Private Limited | Due Oct 2032, extended 4 mo | — | — |
| PavilionPersipina Developers Private Limited | Due Oct 2032, extended 4 mo | — | — |
Nearby: other villages in Khalapur
Most active promoters
- Persipina Developers Private Limited8 projects
- Riyasat Infra Developers Private Limited1 project
Panshil, in questions
How many projects in Panshil run late?
10 in 10 MahaRERA registrations (9 of 9): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Panshil by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology