Olympus
Deedo IDDP-RAI-XKYMCompletion was pushed back 4 months, to Apr 2033; no MahaRERA orders on record; 0% of its units are booked.
Panshil, Raigarh 410222 · by Persipina Developers Private Limited · 100% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2033
- This projectRegistered 14 Jan 2026, completion promised 31 Dec 2032, revised to 30 Apr 2033.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1270002502079
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1270002502079 | 14 Jan 2026 | 31 Dec 2032 | 30 Apr 2033 | Persipina Developers Private Limited | Project page |
Documents36
1 document held by Deedo, 35 filings listed on MahaRERA's project page
Finance
Legal
- OthersPDPL BR.pdf · uploaded 18 Dec 2025Source
- Declaration Form BTItle RZ-05.pdf · uploaded 18 Dec 2025Source
- Declaration Form BRegistered Sale Certificate Panvel.pdf · uploaded 18 Dec 2025Source
- OthersDisclosure in other Interst NLH.pdf · uploaded 6 Jan 2026Source
- OthersDisclosure in Other Interest KNH.pdf · uploaded 6 Jan 2026Source
Show all 36 documentsShow fewer documents
Legal
Migrated
- Withdrawal Update Form 1ARC CER OLYMPUS.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 2ENG CER OLYMPUS.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 3FORM 3 Mar 2026 OLYMPUS.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 1FORM 1 ARCH CERT OLYMPUS.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2Form 2 Eng Cert Olympus.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3Form 3 Olympus.pdf · uploaded 17 Jul 2026Source
- Form 5 (FY 2025-2026)OLYMPUS.pdf · uploaded 31 Jul 2026Source
Technical
- OthersFORMAT-D OLYMPUS.pdf · uploaded 18 Dec 2025Source
- OthersEXPLANATION PARKING OLYMPUS.pdf · uploaded 18 Dec 2025Source
- OthersMSCRC CC Email.pdf · uploaded 18 Dec 2025Source
- DocumentMain Sheet.pdf · uploaded 22 Dec 2025Source
- Document1 Olympus - Ground floor level (Full layout).pdf · uploaded 22 Dec 2025Source
- Document2 Olympus - Podium 01 level (Full layout).pdf · uploaded 22 Dec 2025Source
- Document3 Olympus - Basement 01 level (Full layout).pdf · uploaded 22 Dec 2025Source
- Document4 Olympus - Basement 02 level (Full layout).pdf · uploaded 22 Dec 2025Source
- Document5 Olympus - Typical floor plan (Tower footprints).pdf · uploaded 22 Dec 2025Source
- Document6 Olympus - Refuge - Basement 01 floor plan (Tower footprints).pdf · uploaded 22 Dec 2025Source
- Document7 Olympus - Basement 02 level plan (Tower footprints).pdf · uploaded 22 Dec 2025Source
- Document8 Olympus - Ground floor plan (Tower footprints).pdf · uploaded 22 Dec 2025Source
- Document9 Olympus - Ground floor plan (Tower footprints).pdf · uploaded 22 Dec 2025Source
- Document10 Olympus - Section (Tower footprints).pdf · uploaded 22 Dec 2025Source
- DocumentANNEXURE-A OLYMPUS.pdf · uploaded 8 Jan 2026Source
- OthersAdditional Plot area fees payment.pdf · uploaded 12 Jan 2026Source
Technical (Architect)
- DocumentFORM 1 ARCH CERT OLYMPUS.pdf · uploaded 17 Jul 2026Source
Technical (Engineer)
- DocumentForm 2 Eng Cert Olympus.pdf · uploaded 17 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Gut No. 6/1, RZ-05 Gut No. 41/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —313 units in all
- Address
- Old Mumbai Pune Highway, PanshilPIN 410222
- Village
- Panshil, Khalapur taluka
- Location
- 18.83055, 73.28464
- Land area for this project
- 890 sq m (9,580 sq ft)
- Approved layout area
- 65,937 sq m (7,09,744 sq ft)
- Permissible built-up area
- 33,582 sq m (3,61,474 sq ft)
- Sanctioned built-up area
- 33,582 sq m (3,61,474 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
RZ-05 Gut No. 41/1 Village Talegaon, & Gut No. 6/1 Village Panshil, Taluka Khalapur Dist Raigad.
Boundaries
- North
- Future Development
- South
- Granstand
- East
- Internal Driveway
- West
- Internal Driveway
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking313 units
313 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 313 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Gunisha Sanyal | — |
| Chartered accountant | Manoj O. Shah & CO. | — |
| Engineer | Prashanth Nandulamattam | — |