RERA projects in Lodhivali
7 projects under 7 MahaRERA registrations, registered 2017–2026. 57% have a completion date extended beyond the one promised.
Locality
7RERA projects
7Registrations
3Completion still due4 past their completion date
7 monthsMedian extension beyond promised date57% of registrations extended
0Regulatory casesnone on MahaRERA's lists
10Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 0 |
| 2026 | 2 |
Projects in Lodhivali
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Navkar CelesteNavkar Township & Infra | PR1270002602462 | 19 Oct 2026 | 31 Aug 2030 | — | Not yet due | 0 |
| Dhanraj LegacyDhanraj RealBuild LLP, Dhanraj Global Corporation Private Limited | PR1270002502999 | 18 Mar 2026 | 30 Jan 2031 | 30 May 2031 | Extended 4 mo | 0 |
| Triratna ComplexEmpire Builders And Developers | P52000053814 | 1 Dec 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Panchashil ComplexHonesty Bulder And Developers | P52000026916 | 3 Nov 2020 | 25 Jun 2025 | 25 Jun 2025 | Promised date passed | 0 |
| Sai MohanSwapnil Mohan Kalyankar | P52000018432 | 1 Nov 2018 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Shivam Complex Phase - 1Manoj Ramanand Prajapati | P52000015165 | 2 Feb 2018 | 30 Dec 2020 | 30 Jun 2023 | Extended 30 mo | 0 |
| Pancharatna ComplexHonesty Bulder And Developers | P52000008880 | 19 Aug 2017 | 30 Jul 2018 | 30 Jun 2019 | Extended 11 mo | 0 |
Other localities in Khalapur
Most active promoters
By projects registered here, as named on MahaRERA.
- Honesty Bulder And Developers2 projects
- Dhanraj RealBuild LLP, Dhanraj Global Corporation Private Limited1 project
- Empire Builders And Developers1 project
- Manoj Ramanand Prajapati1 project
- Navkar Township & Infra1 project
- Swapnil Mohan Kalyankar1 project
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology