Skip to content
Residential / Group Housing · 3 buildings · 162 unitsRERA P52000005923

Malaga

Completion was pushed back 2 years to Dec 2024, and that date has passed too; no MahaRERA orders on record; 54% of its units are booked.

Vavandal, Raigarh 410206 · Promoter: Devtaa Yash Lifescapes Pvt Ltd

Delivery3 yrs 10 mo latePromised Dec 2022 · revised Dec 2024 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales54% booked88 of 162 units · as the promoter reported to MahaRERA
Malaga project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 2 years to Dec 2024, and that date has passed too

  • This projectRegistered 14 Aug 2017, completion promised 30 Dec 2022, revised to 30 Dec 2024, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000005923
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200000592314 Aug 201730 Dec 202230 Dec 2024Devtaa Yash Lifescapes Pvt LtdProject page
Documents94

2 documents held by Deedo, 92 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 25 Jul 2017Source
  • PAN CardDevtaa Pan card.PDF · uploaded 10 Dec 2019Source

Legal

  • Declaration Form BForm B.pdf · uploaded 25 Jul 2017Source
  • Legal Title reportTitle Cer 15 2B.pdf · uploaded 28 Jul 2017Source
  • Legal Title reportTitle Cer 17 1.pdf · uploaded 29 Jul 2017Source
  • Declaration Form BfORM b.pdf · uploaded 12 Mar 2018Source
Show all 94 documentsShow fewer documents

Legal

  • Declaration Form BForm B.pdf · uploaded 25 Dec 2023Source
  • Declaration Form BForm B (1).pdf · uploaded 28 Dec 2023Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 25 Jul 2017Source
  • 1 Details of encumbrancesEncumbrances.PDF · uploaded 25 Jul 2017Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 25 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Certificate of Arch Form 1.pdf · uploaded 27 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Certificate of Engineer Form 2 bldg 1.PDF · uploaded 27 Jul 2017Source
  • 1 Proforma of Allotment letterFLAT SALE AGREEMENT.pdf · uploaded 27 Jul 2017Source
  • 1 Copy of the legal title reportTitle Cer 15 2B.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Building Layout Plan.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)Building Layout Plan.pdf · uploaded 28 Jul 2017Source
  • 2 Building Plan Approval (IOD)Building Plan Approval 2.pdf · uploaded 28 Jul 2017Source
  • 3 Building Plan Approval (IOD)Building Plan Approval 3.pdf · uploaded 28 Jul 2017Source
  • 4 Building Plan Approval (IOD)Building Plan Approval 4.pdf · uploaded 28 Jul 2017Source
  • 5 Building Plan Approval (IOD)Building Plan Approval 5.pdf · uploaded 28 Jul 2017Source
  • 6 Building Plan Approval (IOD)Building Plan Approval 6.pdf · uploaded 28 Jul 2017Source
  • 7 Building Plan Approval (IOD)Building Plan Approval 7.pdf · uploaded 28 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentComncement Certificate.pdf · uploaded 28 Jul 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Certificate of Engineer Form 2 bldg 2.PDF · uploaded 28 Jul 2017Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Certificate of Engineer Form 2 bldg 3.PDF · uploaded 28 Jul 2017Source
  • 2 Copy of the legal title reportTitle Cer 17 1.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)Form 3 - Alma - New.pdf · uploaded 29 Jul 2017Source
  • 2 Certificates of CA (Form 3)Form 3 - Alta -New.pdf · uploaded 29 Jul 2017Source
  • 3 Certificates of CA (Form 3)Form 3 - Amor - New.pdf · uploaded 29 Jul 2017Source
  • 2 Details of encumbrancesletter of encumbrances.PDF · uploaded 12 Mar 2018Source
  • 2 Declaration in FORM BfORM b.pdf · uploaded 12 Mar 2018Source
  • 2 Proforma of Allotment letterFinal Sale agree.pdf · uploaded 12 Mar 2018Source
  • 1 Certificates of CA (Form 5)Request Letter.pdf · uploaded 1 Oct 2018Source
  • 3 Proforma of Allotment letterFinal Sale Agreement.pdf · uploaded 1 Oct 2018Source
  • 2 PAN CardDevtaa Pan card.PDF · uploaded 10 Dec 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.PDF · uploaded 10 Dec 2019Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer MALAGA BUILDING 1,2,3 11 02 2019 (R1).pdf · uploaded 10 Dec 2019Source
  • 4 Certificates of CA (Form 3)Alta - RERA form 3.PDF · uploaded 10 Dec 2019Source
  • 5 Certificates of CA (Form 3)Amor - RERA form 3.PDF · uploaded 10 Dec 2019Source
  • 6 Certificates of CA (Form 3)RERA Form 3 of Alma.PDF · uploaded 10 Dec 2019Source
  • 8 Building Plan Approval (IOD)MYSCAN_0002.pdf · uploaded 4 Mar 2020Source
  • 9 Building Plan Approval (IOD)MYSCAN_0001.pdf · uploaded 4 Mar 2020Source
  • 10 Building Plan Approval (IOD)MYSCAN_0003-compressed.pdf · uploaded 4 Mar 2020Source
  • 11 Building Plan Approval (IOD)MYSCAN_0004-compressed.pdf · uploaded 4 Mar 2020Source
  • 12 Building Plan Approval (IOD)MYSCAN_0005-converted.pdf · uploaded 4 Mar 2020Source
  • 13 Building Plan Approval (IOD)MYSCAN_0006-compressed.pdf · uploaded 4 Mar 2020Source
  • 14 Building Plan Approval (IOD)MYSCAN_0007.pdf · uploaded 4 Mar 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised Commencement Certificate.pdf · uploaded 4 Mar 2020Source
  • 4 Proforma of Allotment letterupdated Agreement to Sale.pdf · uploaded 1 Sep 2020Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)DYPL form 1.pdf · uploaded 10 May 2023Source
  • 3 Declaration in FORM BForm B.pdf · uploaded 25 Dec 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 26 Dec 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 28 Dec 2023Source
  • 4 Declaration in FORM BForm B (1).pdf · uploaded 28 Dec 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Alma.pdf · uploaded 28 Dec 2023Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Alta.pdf · uploaded 28 Dec 2023Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Amor.pdf · uploaded 28 Dec 2023Source
  • 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 28 Dec 2023Source
  • 7 Certificates of CA (Form 3)Form 3_compressed.pdf · uploaded 28 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 18-19.pdf · uploaded 28 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 19-20.pdf · uploaded 28 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 20-21.pdf · uploaded 28 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 28 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23.pdf · uploaded 28 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)19 20.pdf · uploaded 29 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)20 21.pdf · uploaded 29 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)21 22.pdf · uploaded 29 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)22 23.pdf · uploaded 29 Dec 2023Source
  • 2 Disclosure of sold/ booked inventory29.pdf · uploaded 29 Dec 2023Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)avandhal Form -4 20241005.pdf · uploaded 16 Oct 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentMalaga OC.pdf · uploaded 16 Oct 2024Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 17 Oct 2024Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 5 Nov 2024Source
  • 4 Architect’s Certificate on Completion of Project (Form 4)Form 4 New.pdf · uploaded 11 Nov 2024Source

Technical

  • DocumentBuilding Layout Plan.pdf · uploaded 28 Jul 2017Source
  • DocumentBuilding Plan Approval 5.pdf · uploaded 28 Jul 2017Source
  • DocumentBuilding Layout Plan.pdf · uploaded 28 Jul 2017Source
  • DocumentBuilding Plan Approval 4.pdf · uploaded 28 Jul 2017Source
  • DocumentBuilding Plan Approval 2.pdf · uploaded 28 Jul 2017Source
  • DocumentBuilding Plan Approval 3.pdf · uploaded 28 Jul 2017Source
  • DocumentBuilding Plan Approval 6.pdf · uploaded 28 Jul 2017Source
  • DocumentBuilding Plan Approval 7.pdf · uploaded 28 Jul 2017Source
  • DocumentMYSCAN_0002.pdf · uploaded 4 Mar 2020Source
  • DocumentMYSCAN_0001.pdf · uploaded 4 Mar 2020Source
  • DocumentMYSCAN_0003-compressed.pdf · uploaded 4 Mar 2020Source
  • DocumentMYSCAN_0004-compressed.pdf · uploaded 4 Mar 2020Source
  • DocumentMYSCAN_0005-converted.pdf · uploaded 4 Mar 2020Source
  • DocumentMYSCAN_0006-compressed.pdf · uploaded 4 Mar 2020Source
  • DocumentMYSCAN_0007.pdf · uploaded 4 Mar 2020Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 26 Dec 2023Source

Technical (Engineer)

  • DocumentAmor.pdf · uploaded 28 Dec 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals152, 171

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Studio, 2BHK162 units in all
Address
15-2, 17-1, on Old Mumbai Pune Highway, Nr. Chowk Rly StationPIN 410206
Village
Vavandal, Khalapur taluka
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

152171

Boundaries

North
14-1 B
South
Existing Road
East
15-1 A
West
Gaothan

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking162 units

88 of 162 units booked (54%), as the promoter reported to MahaRERA

1BHK · 55 unitsStudio · 72 units2BHK · 35 units
BuildingTypeCarpet areaUnitsBooked
11BHK38.27 sq m · 412 sq ft52
11BHK38.28 sq m · 412 sq ft20
11BHK38.55 sq m · 415 sq ft22
11BHK40.87 sq m · 440 sq ft1612
11BHK41.15 sq m · 443 sq ft52
11BHK41.16 sq m · 443 sq ft11
11BHK44.5 sq m · 479 sq ft20
11BHK46.64 sq m · 502 sq ft21
Show all 15 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
11BHK49.15 sq m · 529 sq ft159
11BHK49.6 sq m · 534 sq ft52
2Studio21.73 sq m · 234 sq ft55
2Studio21.74 sq m · 234 sq ft30
2Studio25.54 sq m · 275 sq ft6439
32BHK69.58 sq m · 749 sq ft195
32BHK71.35 sq m · 768 sq ft168

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals8

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHafeez Contractor—
ArchitectNeha Jain—
Chartered accountantM G Bhanushali & Co—
EngineerB S Suktankar—
OtherAshok G Sheth—
OtherHimadri Banerjee—
OtherRahul Engineering—
OtherWestern Infracon—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology