5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects6
Registrations6
Completion still due33 past their date
Median extension4 months50% of registrations extended
Regulatory cases1on 1 project
Vakadi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

6 MahaRERA registrations in Vakadi

1 not yet due2 extended, not yet due3 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Vakadi

6 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Om Vaastu ComplexOm Vaastu Enterprises LLPDue Dec 2030——
Pratham VrundavanPratham InfraDue Apr 2030, extended 4 mo——
Balaji Avvante - Building No. 11 and 12Vishesh Greenscape LLPDue Oct 2026, extended 4 mo—51%
AvanteSwaraj Mega Structure Private Limited6 yrs 10 mo late——
Shanti HarmonyShanti Developers3 yrs 10 mo late—87%
Green Acre- Phase IIDharti Developers7 yrs 10 mo late—86%

Most active promoters

  1. Dharti Developers1 project
  2. Om Vaastu Enterprises LLP1 project
  3. Pratham Infra1 project
  4. Shanti Developers1 project
  5. Swaraj Mega Structure Private Limited1 project
  6. Vishesh Greenscape LLP1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology