Avante

Completion date passed

Vakadi, Raigarh 410206 |Promoter: Swaraj Mega Structure Private Limited

10 May 2018Registered with MahaRERA
31 Dec 2019Promised completion
31 Dec 2025Revised completionPushed back 6 years
1MahaRERA listings and orders

Project summary

As registered with MahaRERA

MahaRERA's search listing gives this project's name, promoter and location only.

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.02788, 73.16704
Avante is at latitude 19.02788, longitude 73.16704.
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 6 years

The latest completion date on record passed 10 months ago.

Registered
10 May 2018
Promised
31 Dec 2019
Revised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200001641110 May 201831 Dec 201931 Dec 2025Swaraj Mega Structure Private LimitedProject page

Documents

2 documents held by Deedo

Registration certificate

Extension certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Regulatory order9 Aug 2024Matched by RERA number

    Regulatory order: PROJECT NAME: AVANTE (Regulatory Case No. 286 OF 2024) dated 09 Aug 2024.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Vakadi

Survey, CTS, gat or plot numbers

139/12139/6140/1/2141/0142/0143/0

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificates · MahaRERA regulatory lists and ordersMethodology