Ulawe, Raigarh
Deedo IDDL-RAI-ULAWE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects697
Registrations698some projects hold several
Completion still due127571 past their date
Median extension4 months27% of registrations extended
Regulatory cases10on 6 projects
10 in 10 registrations run late here
698 MahaRERA registrations in Ulawe
1 completed32 not yet due95 extended, not yet due570 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Ulawe
697 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Infinite SiddhiInfinite Assets Ulwe Realty LLP | Due Nov 2028, extended 4 mo | — | — |
| Rama KunjMahavir Construction | Due Apr 2028, extended 4 mo | — | — |
| Sadguru HeightsSadguru Builders & Developers | Due Jun 2028 | — | — |
| Sai KeshavSulochana Janardan Mhatre | Due Apr 2028, extended 4 mo | — | — |
| Saras DestinyHi Tech Group | Completed | — | 39% |
| Patel AuraMahavir Developers | Due Dec 2026, extended 4 mo | — | — |
| Siddhivinayak Residency IISuyash Sahakar Builders And Developers | 1 yr 11 mo late | — | — |
| Stone VistaPawan Enterprises | Due Nov 2028, extended 4 mo | — | — |
| Hill ViewSaffron Developers | Due Apr 2027, extended 4 mo | — | — |
| Chaitanya ResidencyDhanaji Sampat Katkar | Due Apr 2027 | — | 4% |
| Sai PearlJay Gurudev Construction | Due Apr 2027, extended 4 mo | — | 2% |
| Prime AvenueDevraj Builders & Developers | Due Oct 2027, extended 4 mo | — | 8% |
| HillcrestErdamor Realty LLP | Due Dec 2027 | — | — |
| 99 Silver OaksBombay Construction & Infraprojects Pvt Ltd | Due Apr 2034, extended 4 mo | — | — |
| Krishna AvenueBhanu Group | Due Apr 2027, extended 4 mo | — | 12% |
| Vaikunth BlissDivyesh Dilipbhai Nakrani | Due Apr 2027, extended 4 mo | — | 10% |
| Rudra MahadevRudra Developers | Completed | — | 9% |
| Hari Om BhaktiBhakti Enterprises | Due Apr 2029, extended 4 mo | — | — |
| Century TowerCentury Enterprises | Due Oct 2027, extended 4 mo | — | 11% |
| Sai DarshanRavi Kiran Enterprises | Due Jul 2027, extended 4 mo | — | 2% |
| Ayati AnganAyati Homes Private Limited | Due Apr 2028, extended 4 mo | — | 8% |
| Mega VistaMohammed Yusuf Salim Chaudhary | Due Dec 2026 | — | — |
| Prime NeelkanthPrime Neelkanth LLP | Due Apr 2029, extended 4 mo | — | — |
| Pd OnePragati Developers | Completed | — | — |
| Krishna CrystalShree Krishna Enterprises | Due Apr 2028, extended 4 mo | — | — |
Nearby: other villages in Panvel
Most active promoters
- Mahavir Construction7 projects
- Shree Riddhi Siddhi Constructions7 projects
- Tejas Enterprises7 projects
- Serene Lifespaces5 projects
- Varniraj Group5 projects
- Hare Krishna Enterprises4 projects
- Lakhani Builders Pvt Ltd4 projects
- Manoj Kumar Singh4 projects
- Mmg Landmark Llp4 projects
- Sm Developers4 projects
Ulawe, in questions
How many projects in Ulawe run late?
10 in 10 MahaRERA registrations (665 of 698): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ulawe by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology