Completion was pushed back 4 months, to Oct 2027; no MahaRERA orders on record; 11% of its units are booked.

Ulawe, Raigarh 410206 · by Century Enterprises

DeliveryExtended 4 moPromised Jun 2027 · now due Oct 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales11% booked10 of 90 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2027

  • This projectRegistered 16 May 2024, completion promised 30 Jun 2027, revised to 30 Oct 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000056180
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005618016 May 202430 Jun 202730 Oct 2027Century EnterprisesProject page
Documents88

1 document held by Deedo, 87 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card-Firm.pdf · uploaded 8 Jan 2024Source

Legal

  • Other – LegalAgreement to lease- B5-2016_11zon.pdf · uploaded 8 Jan 2024Source
  • Other – LegalTP-B5 - 2018_11zon.pdf · uploaded 8 Jan 2024Source
  • Other – LegalAgreement to lease- B5A-2018_11zon.pdf · uploaded 8 Jan 2024Source
  • Other – LegalTP- B5A-2019_11zon.pdf · uploaded 8 Jan 2024Source
  • Other – LegalModified Agreement 5 PLUS 5A.pdf · uploaded 8 Jan 2024Source
  • Declaration Form BRevised Form B (Promoter).pdf · uploaded 11 Jan 2024Source
Show all 88 documentsShow fewer documents

Legal

  • Other – Legal5 Other – Legal.pdf · uploaded 29 Jan 2024Source
  • Other – Legal2 Copy of the legal title report (1).pdf · uploaded 20 Feb 2024Source
  • Other – LegalPLOT NO CORRIGENDUM SUB ACKNO.pdf · uploaded 18 Mar 2024Source
  • Other – LegalCorrigendum Letter.pdf · uploaded 18 Apr 2024Source
  • Legal Title reportShort Title_MsCentury Enterprises.pdf · uploaded 20 Apr 2024Source

Migrated

  • 1 PAN CardPan Card-Firm.pdf · uploaded 8 Jan 2024Source
  • 1 Copy of Layout Approval (in case of layout)CC DRG-1_11zon.pdf · uploaded 8 Jan 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentCC DRG_11zon.pdf · uploaded 8 Jan 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC (1).pdf · uploaded 8 Jan 2024Source
  • 1 Other – LegalAgreement to lease- B5-2016_11zon.pdf · uploaded 8 Jan 2024Source
  • 2 Other – LegalTP-B5 - 2018_11zon.pdf · uploaded 8 Jan 2024Source
  • 3 Other – LegalAgreement to lease- B5A-2018_11zon.pdf · uploaded 8 Jan 2024Source
  • 4 Other – LegalTP- B5A-2019_11zon.pdf · uploaded 8 Jan 2024Source
  • 5 Other – LegalModified Agreement 5 PLUS 5A.pdf · uploaded 8 Jan 2024Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance letter- Finance.pdf · uploaded 11 Jan 2024Source
  • 2 a Details of encumbrances concerned to FinanceNo Encumbrance letter- Legal (2).pdf · uploaded 11 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance letter- Finance.pdf · uploaded 11 Jan 2024Source
  • 2 b Details of encumbrances concerned to LegalNo Encumbrance letter- Legal (2).pdf · uploaded 11 Jan 2024Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 11 Jan 2024Source
  • 1 Declaration in FORM BRevised Form B (Promoter).pdf · uploaded 11 Jan 2024Source
  • 1 CERSAI detailsCersai Declaration.pdf · uploaded 11 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 11 Jan 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Verification- Century Tower.pdf · uploaded 19 Jan 2024Source
  • 1 Proforma of Agreement for sale1 Proforma of Agreement for sale (12).pdf · uploaded 19 Jan 2024Source
  • 1 Proforma of Allotment letterAl_Century Tower_Century Enterprises_16012024.pdf · uploaded 19 Jan 2024Source
  • 1 Other – TechnicalCC Verification- Century Tower.pdf · uploaded 19 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation report of Allotment letter (2).pdf · uploaded 20 Jan 2024Source
  • 1 Deviation Report with respect to model copy of AgreementRevised Deviation report of AFS.pdf · uploaded 20 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)First Form 3 - Century Tower.pdf · uploaded 22 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameRevised Format A.pdf · uploaded 29 Jan 2024Source
  • 6 Other – Legal5 Other – Legal.pdf · uploaded 29 Jan 2024Source
  • 2 Other – TechnicalOrder No-50.pdf · uploaded 29 Jan 2024Source
  • 7 Other – Legal2 Copy of the legal title report (1).pdf · uploaded 20 Feb 2024Source
  • 8 Other – LegalPLOT NO CORRIGENDUM SUB ACKNO.pdf · uploaded 18 Mar 2024Source
  • 9 Other – LegalCorrigendum Letter.pdf · uploaded 18 Apr 2024Source
  • 1 Copy of the legal title reportShort Title_MsCentury Enterprises.pdf · uploaded 20 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Century Tower as on June 2024.pdf · uploaded 18 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Century Tower- as on 30th June 2024 .pdf · uploaded 19 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Century Tower - June 2024.pdf · uploaded 19 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Century Tower Sep 2024.pdf · uploaded 16 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Century Tower as on 30th Sept ,2024.pdf · uploaded 26 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Century Tower- as on 30th Sept 2024.pdf · uploaded 26 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Century Tower as on Sep 2024.pdf · uploaded 10 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Century Tower as on Dec 2024.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Century Tower as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Century Tower- as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Century Tower as on March 2025.pdf · uploaded 5 Apr 2025Source
  • Form 1Form 1 - Century Tower as on June 2025.pdf · uploaded 20 Jul 2025Source
  • Form 2Form 2 - Century Tower as on June 2025.pdf · uploaded 20 Jul 2025Source
  • Form 3Form 3 - Century Tower as on June 2025.pdf · uploaded 20 Jul 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Century Tower as on June 2025.pdf · uploaded 20 Jul 2025Source
  • Form 1Form 1 - Century Tower as on March 2025.pdf · uploaded 4 Sep 2025Source
  • Form 2Form 2 - Century Tower as on March 2025.pdf · uploaded 4 Sep 2025Source
  • Form 3Form 3 - Century Tower as on March 2025.pdf · uploaded 4 Sep 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Century Tower as on March 2025.pdf · uploaded 4 Sep 2025Source
  • Form 1Form 1 - Century Tower as on Sep 2025.pdf · uploaded 19 Oct 2025Source
  • Form 2Form 2 - Century Tower as on Sep 2025.pdf · uploaded 19 Oct 2025Source
  • Form 3Form 3 - Century Tower as on Sep 2025.pdf · uploaded 19 Oct 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Century Tower as on Sep 2025.pdf · uploaded 19 Oct 2025Source
  • Withdrawal Update Form 1Form 1 - Century Tower as on Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2Form 2 - Century Tower as on Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3Form 3 - Century Tower as on Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1Form 1 - Century Tower as on March 2026.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 2Form 2 - Century Tower as on March 2026.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 3Form 3 - Century Tower as on March 2026.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 1Form 1 - Century Tower as on June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Century Tower as on June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Century Tower as on June 2026.pdf · uploaded 21 Jul 2026Source

Technical

  • DocumentCC DRG_11zon.pdf · uploaded 8 Jan 2024Source
  • DocumentCC DRG-1_11zon.pdf · uploaded 8 Jan 2024Source
  • Other – TechnicalCC Verification- Century Tower.pdf · uploaded 19 Jan 2024Source
  • Other – TechnicalOrder No-50.pdf · uploaded 29 Jan 2024Source

Technical (Architect)

  • DocumentForm 1 Century Tower Sep 2024.pdf · uploaded 16 Oct 2024Source
  • DocumentForm 1 - Century Tower as on Sep 2024.pdf · uploaded 10 Dec 2024Source
  • DocumentForm 1 - Century Tower as on Dec 2024.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 1 - Century Tower as on March 2025.pdf · uploaded 5 Apr 2025Source
  • DocumentForm 1 - Century Tower as on June 2026.pdf · uploaded 21 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2- Century Tower- as on 30th Sept 2024.pdf · uploaded 26 Oct 2024Source
  • DocumentForm 2- Century Tower- as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • DocumentForm 2 - Century Tower as on June 2026.pdf · uploaded 21 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No B5 + B5A, Sector 19B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop90 units in all
Address
Plot No- B5 + B5A, Sector- 19B, Ulwe, Sector- 19B, UlwePIN 410206
Village
Ulawe, Panvel taluka
Land area for this project
1,250 sq m (13,455 sq ft)
Permissible built-up area
5,481 sq m (59,001 sq ft)
Sanctioned built-up area
5,481 sq m (59,001 sq ft)
Designated bank account
51
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No B5 + B5ASector 19B

Land as published on MahaRERA's project page

Plot No- B5 + B5A, Sector- 19B, Ulwe

Boundaries

North
15 M Wide Road
South
Plot No- 04
East
30 M Wide Road
West
Plot No- 6 Plot No- 7 and Plot No- 8

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking90 units

10 of 90 units booked (11%), as the promoter reported to MahaRERA

1BHK · 40 units2BHK · 41 unitsShop · 9 units
TypeCarpet areaUnitsBooked
1BHK26.89 sq m · 289 sq ft10
1BHK28.13 sq m · 303 sq ft10
1BHK33.07 sq m · 356 sq ft110
1BHK34.11 sq m · 367 sq ft140
1BHK36.44 sq m · 392 sq ft131
2BHK33.36 sq m · 359 sq ft130
2BHK53.12 sq m · 572 sq ft140
2BHK56.62 sq m · 609 sq ft140
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop13.61 sq m · 146 sq ft11
Shop20.05 sq m · 216 sq ft11
Shop38.63 sq m · 416 sq ft22
Shop42.58 sq m · 458 sq ft22
Shop43.09 sq m · 464 sq ft11
Shop47.31 sq m · 509 sq ft11
Shop47.33 sq m · 509 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Ulawe

All 697 projects in Ulawe · Compare Century Tower with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology